OSHA Inspection: CROSSTOWN CONSTRUCTION, LLC

Unprogrammed Other inspection · Safety discipline

On , OSHA opened an unprogrammed Other safety inspection of CROSSTOWN CONSTRUCTION, LLC in 1447 NORTH 17TH STREET, PHILADELPHIA, PA 19122 (NAICS 236116). OSHA activity number 335669396.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Crosstown Construction, LLC — free Get an email when a new federal OSHA severe-injury report for Crosstown Construction, LLC is published. One employer, no account, unsubscribe in one click.
Site address
1447 NORTH 17TH STREET
City
PHILADELPHIA
State
PA
ZIP
19122
Mailing
P.O. BOX 30299, ELKINS PARK, PA 19027
Inspection type
Unprogrammed Other (I)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
236116
Employees
5
Ownership type
A

3 citations on file for this inspection.

1926.451 G01 VII

Serious Gravity 5 1 instance 2 exposed
Issued
Jan 22, 2013
Abate by
Jan 26, 2013
Penalty
Initial $2,000 · Current $2,000
29 CFR 1926.451(g)(1)(vii):     Each employee on a scaffold, not otherwise specified in paragraphs (g)(1)(i) through (g)(1)(vi) of this section, more than 10 feet (3.1 m) above lower level was not protected from falls by the use of personal fall arrest systems or guardrail systems meeting the requirements of paragraph (g)(4) of this section.    a) Jobsite -1447 North 17th Street - Employees performing siding operations from the tubular welded frame scaffold were exposed to fall hazards of approximately 13 feet without adequate means of fall protection. Observed on or about 07/27/12.     Abatement certification required within 10 days after abatement date.  The certification shall include a statement that abatement is complete, date and method of abatement and states employees and their representatives were informed of this abatement.
Recent events (1)
  • — Z (S) $2000

1926.451 B01

Serious Gravity 5 1 instance 2 exposed
Issued
Jan 22, 2013
Abate by
Jan 26, 2013
Penalty
Initial $0 · Current $0
29 CFR 1926.451(b)(1):     Each platform on all working levels of scaffolds shall be fully planked or decked between the front uprights and the guardrail supports as follows:    a) Jobsite - The 2nd working level of the tubular welded frame scaffold was not fully planked between the front and rear uprights.  The working levels contained 1 and 2 planks where two employees were performing siding operations.  Observed on or about 07/27/2012.    Abatement certification required within 10 days after abatement date.  The certification shall include a statement that abatement is complete, date and method of abatement and states employees and their representatives were informed of this abatement.
Recent events (1)
  • — Z (S) $0

1926.454 A

Serious Gravity 5 1 instance 2 exposed
Issued
Jan 22, 2013
Abate by
Jan 30, 2013
Penalty
Initial $0 · Current $0
29 CFR 1926.454(a):     The employer shall have each employee who performs work while on a scaffold trained by a person qualified in the subject matter to recognize the hazards associated with the type of scaffold being used and to understand the procedures to control or minimize those hazards. The training shall include the following areas, as applicable:    a) Jobsite-1414 North 17th Street - The employer did not provide each employee performing siding operations from a tubular welded frame scaffold with training to recognize the hazards and to understand the procedures to control the hazards associated with operations, on or about 07/27/12.    Abatement certification required within 10 days after abatement date.  The certification shall include a statement that abatement is complete, date and method of abatement and states employees and their representatives were informed of this abatement.
Recent events (1)
  • — Z (S) $0

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 335669396.