COLUMBUS, OH —
OSHA Inspection: MOORE DRYWALL COMPANY, INC.
Unprogrammed Other inspection · Safety discipline
At a glance
On , OSHA opened an unprogrammed Other safety inspection of MOORE DRYWALL COMPANY, INC. in 720 WEST THIRD STREET, COLUMBUS, OH 43214 (NAICS 238130). OSHA activity number 336056783.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- MOORE DRYWALL COMPANY, INC.
- Site address
- 720 WEST THIRD STREET
- City
- COLUMBUS
- State
- OH
- ZIP
- 43214
- Mailing
- 697 GREEN CREST DRIVE, WESTERVILLE, OH 43081
What kind of inspection was it?
- Inspection type
- Unprogrammed Other (I)
- Scope
- Complete (A)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238130
- Employees
- 18
- Ownership type
- A
Citations
4 citations on file for this inspection.
1926.404 B01 III C
- Issued
- Sep 12, 2012
- Penalty
- Initial $1,360 · Current $1,360
General-duty citation text
29 CFR 1926.404(b)(1)(iii)(C): Each cord set, attachment cap, plug and receptacle of cord sets, and any equipment connected by cord and plug, except cord sets and receptacles which are fixed and not exposed to damage, shall be visually inspected before each day's use for external defects, such as deformed or missing pins or insulation damage, and for indications of possible internal damage. Equipment found damaged or defective shall not be used until repaired. a. On the fourth floor of tower A, employees were using an extension cord with a missing ground prong, thereby being exposed to a contact hazard. b. On the fourth floor of tower A in apartment 442, employees were using an extension cord with exposed interior wiring insulation at the plug, thereby being exposed to a contact hazard. c. On the fourth floor of tower A in apartment 442, employees were using a job made power receptacle with exposed interior wiring insulation, thereby being exposed to a contact hazard.
Recent events (1)
- — Z (S) $1360
1926.405 G02 IV
- Issued
- Sep 12, 2012
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1926.405(g)(2)(iv): Strain relief. Flexible cords shall be connected to devices and fittings so that strain relief is provided which will prevent pull from being directly transmitted to joints or terminal screws. a. On the fourth floor of tower A in apartment 442, employees were using an extension cord with exposed interior wiring insulation at the plug due to a failure of the strain relief, thereby being exposed to a contact hazard. b. On the fourth floor of tower A in apartment 442, employees were using a job made power receptacle with exposed interior wiring insulation due to a failure of the strain relief clamp assembly, thereby being exposed to a contact hazard.
Recent events (1)
- — Z (S) $0
1926.502 B01
- Issued
- Sep 12, 2012
- Penalty
- Initial $1,020 · Current $1,020
General-duty citation text
29 CFR 1926.502(b)(1): Top edge height of top rails, or equivalent guardrail system members, shall be 42 inches (1.1 m) plus or minus 3 inches (8 cm) above the walking/working level. When conditions warrant, the height of the top edge may exceed the 45-inch height, provided the guardrail system meets all other criteria of this paragraph. Note: When employees are using stilts, the top edge height of the top rail, or equivalent member, shall be increased an amount equal to the height of the stilts. a. At the elevator shaft in the north/east corner of tower A, the top-rail guard rail was installed at approximately 47 inches, thereby exposing employees to a fall hazard.
Recent events (1)
- — Z (S) $1020
1926.502 B02 I
- Issued
- Sep 12, 2012
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1926.502(b)(2)(i): Midrails, when used, shall be installed at a height midway between the top edge of the guardrail system and the walking/working level. a. At the elevator shaft in the north/east corner of tower A, the mid rail guard rail was installed at 28.5 inches, thereby exposing employees to a fall hazard.
Recent events (1)
- — Z (S) $0
More inspections at Moore Drywall Company, INC.
View Moore Drywall Company, INC.'s full OSHA safety record →
More inspections in this industry (NAICS 238130)
More inspections in OH
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 336056783.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.