Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: CARUSONE CONSTRUCTION INC.

Planned inspection · Health discipline

On , OSHA opened a planned health inspection of CARUSONE CONSTRUCTION INC. in 100 BLOCK ROCHELLE AVE. PHILADELPHIA, PHILADELPHIA, PA 19128 (NAICS 238910). OSHA activity number 336190996.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Carusone Construction INC. — free Get an email when a new federal OSHA severe-injury report for Carusone Construction INC. is published. One employer, no account, unsubscribe in one click.
Site address
100 BLOCK ROCHELLE AVE. PHILADELPHIA
City
PHILADELPHIA
State
PA
ZIP
19128
Mailing
3245 SOUTH 74TH STREET, PHILADELPHIA, PA 19153
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Health
Advance notice
No
Union status
A
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238910
Employees
22
Ownership type
A

7 citations on file for this inspection.

1926.651 I03

Serious Gravity 10 2 instances 3 exposed
Issued
Mar 6, 2013
Abate by
Mar 25, 2013
Penalty
Initial $3,080 · Current $2,150 Reduced
29 CFR 1926.651(i)(3):  Sidewalks, pavements, or appurtenant structures had been undermined and a support system or another method was not provided to protect employees from the possible collapse of such structures:      a) Jobsite, 100 Block Rochelle Ave. - An employee was unclogging a pipe below an undermined section of the street, on the west side of an excavation.  The undermined section was not supported to prevent possible crushing hazards.   Observed on or about 9/6/12.     b) Jobsite, 100 Block Rochelle Ave. -  An employee was unclogging a pipe below an undermined section of the street, on the east side of an excavation.  The undermined section was not supported to prevent possible crushing hazards.  Observed on or about 9/6/12.     NOTE:    Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (3)
  • — F (S) $2150
  • — C (S) $3080
  • — Z (S) $3080

1926.651 C02

Other-than-serious 1 instance 3 exposed
Issued
Mar 6, 2013
Penalty
Initial $0 · Current $0
29 CFR 1926.651(c)(2):  A stairway, ladder, ramp or other safe means of egress was not located in trench excavations that were 4 feet (1.22m) or more in depth so as to require no more than 25 feet (7.62m) of lateral travel for employees:      a) Jobsite, 100 Block Rochelle Ave. - Employees were not provided with a ladder, structural ramp, or other safe means of access or egress from an excavation so as to require no more than 25' of lateral travel, exposing the employees to serious injuries.    Observed on or about 9/6/12.      NOTE:  No abatement certification or documentation required.
Recent events (3)
  • — F (O) $0
  • — C (S) $0
  • — Z (S) $0

1926.100 A

Serious Gravity 5 1 instance 3 exposed
Issued
Mar 6, 2013
Penalty
Initial $0 · Current $0
29 CFR 1926.100(a):  Employees working in areas where there is a possible danger of head injury from impact, or from falling or flying objects, or from electrical shock and burns, shall be protected by protective helmets.    a) Jobsite, 100 Block Rochelle Ave. - Employees working beneath an undermined street were not wearing hard hats, exposing the employees to serious head injury.  Observed on or about 9/6/12.      NOTE:  No abatement certification or documentation required.
Recent events (3)
  • — F (S) $0
  • — C (S) $0
  • — Z (S) $0

1926.652 G02

Serious Gravity 5 1 instance 2 exposed
Issued
Mar 6, 2013
Abate by
Mar 25, 2013
Penalty
Initial $2,200 · Current $1,540 Reduced
29 CFR 1926.652(g)(2):  Additional requirement for shield systems used in trench excavations. Excavations of earth material to a level not greater than 2 feet (.61 m) below the bottom of a shield shall be permitted, but only if the shield is designed to resist the forces calculated for the full depth of the trench, and there are no indications while the trench is open of a possible loss of soil from behind or below the bottom of the shield:      a) Jobsite, 100 Block Rochelle Ave. - Employees were installing a sanitary main in an excavation.  The employees were inside a trench shield which had been installed 30" (2.6') above the base of the excavation, exposing the employees to multiple serious injuries.  Observed on or about 9/7/12.      NOTE:  Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (3)
  • — F (S) $1540
  • — C (S) $2200
  • — Z (S) $2200

1926.21 B02

Other-than-serious 1 instance 5 exposed
Issued
Mar 6, 2013
Abate by
Mar 25, 2013
Penalty
Initial $0 · Current $0
29 CFR 1926.21(b)(2):  The employer did not instruct each employee in the recognition and avoidance of unsafe conditions and the regulations applicable to his/her environment to control or eliminate any hazards or other exposure to illness or injury:    a) Jobsite, 100 Block Rochelle Ave. - The employer did not instruct each employee in the recognition and avoidance of unsafe conditions pertaining to excavation operations, exposing the employees to crushing, struck-by and cave-in hazards.  Observed on or about 9/6/12.      NOTE:  Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (3)
  • — F (O) $0
  • — C (S) $0
  • — Z (S) $0

1926.652 A01

Repeat Gravity 10 1 instance 5 exposed
Issued
Mar 6, 2013
Abate by
Mar 25, 2013
Penalty
Initial $6,160 · Current $4,315 Reduced
29 CFR 1926.652(a)(1):  Each employee in an excavation was not protected from cave-ins by an adequate protective system designed in accordance with 29 CFR 1926.652(b) or (c). The employer had not complied with the provisions of 29 CFR 1926.652(b)(1)(i) in that the excavation was sloped at an angle steeper than one and one-half horizontal to one vertical (34 degrees from the horizontal):    a) Jobsite, 100 Block Rochelle Ave. - Employees were installing a sanitary main and performing ancillary activities in an excavation ranging from 5 feet to 9.8 feet in depth.  The employees were not protected by an adequate protective system, exposing the employees to crushing, struck-by and cave-in hazards.  Observed on or about 9/6/12.      CARUSONE CONSTRUCTION INC. WAS PREVIOUSLY CITED FOR A VIOLATION OF THIS OCCUPATIONAL SAFETY AND HEALTH STANDARD OR ITS EQUIVALENT STANDARD 1926.652(a)(1) WHICH WAS CONTAINED IN OSHA INSPECTION NUMBER 314228990, CITATION 1 ITEM 1, AND WAS AFFIRMED AS A FINAL ORDER ON 8/23/10 WITH RESPECT TO A WORKPLACE LOCATED AT 12TH AND PORTER STREETS, PHILADELPHIA PA 19145.        NOTE:  Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (3)
  • — F (R) $4315
  • — C (R) $6160
  • — Z (R) $6160

1926.651 K01

Repeat Gravity 10 1 instance 5 exposed
Issued
Mar 6, 2013
Abate by
Mar 25, 2013
Penalty
Initial $6,160 · Current $4,315 Reduced
29 CFR 1926.651(k)(1):  An inspection of the excavations, the adjacent areas, and protective systems was not conducted by the competent person prior to the start of work and as needed throughout the shift:    a) Jobsite, 100 Block Rochelle Ave. - Employees installing a sanitary main and performing ancillary activities, were in an excavation ranging from 5 feet to 9.8 feet in depth.  An inspection of the excavation, the adjacent areas, and protective systems was not conducted by the competent person prior to the start of work and as needed throughout the shift, exposing employees to crushing, struck-by and cave-in hazards.  Observed on or about 9/6/12 and 9/7/12.        CARUSONE CONSTRUCTION INC. WAS PREVIOUSLY CITED FOR A VIOLATION OF THIS OCCUPATIONAL SAFETY AND HEALTH STANDARD OR ITS EQUIVALENT STANDARD 1926.651(k)(1) WHICH WAS CONTAINED IN OSHA INSPECTION NUMBER 314228990, CITATION 1 ITEM 2, AND WAS AFFIRMED AS A FINAL ORDER ON 8/23/10 WITH RESPECT TO A WORKPLACE LOCATED AT 12TH AND PORTER STREETS, PHILADELPHIA PA 19145.        NOTE:  Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (3)
  • — F (R) $4315
  • — C (R) $6160
  • — Z (R) $6160

View Carusone Construction INC.'s full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 336190996.