Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: INTEGRITY PLASTICS, INCORPORATED

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of INTEGRITY PLASTICS, INCORPORATED in 10 INDUSTRIAL DRIVE, DENVER, PA 17517 (NAICS 326199). OSHA activity number 336442785.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Integrity Plastics, Incorporated — free Get an email when a new federal OSHA severe-injury report for Integrity Plastics, Incorporated is published. One employer, no account, unsubscribe in one click.
Site address
10 INDUSTRIAL DRIVE
City
DENVER
State
PA
ZIP
17517
Mailing
10 INDUSTRIAL DRIVE, DENVER, PA 17517
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
326199
Employees
38
Ownership type
A

5 citations on file for this inspection.

1910.215 A04

Serious Gravity 1 1 instance 1 exposed
Issued
Oct 17, 2012
Penalty
Initial $2,100 · Current $1,575 Reduced
29 CFR 1910.215(a)(4):  Work rest(s) on grinding machinery were not adjusted closely to the wheel with a maximum opening of one-eighth inch:    (a)  Integry Plastics, Inc., 10 Industrial Drive, Denver, PA - Employees used a Dewalt 6-inch bench grinder (# 756, Serial number 290338-YL0232) to remove clips on air hoses and were exposed to an impact/flying particle hazard when the space between the work rest and grinding wheel was three-quarters of an inch, on or about September 19, 2012.    No abatement certification or documentation required.
Recent events (2)
  • — I (S) $1575
  • — Z (S) $2100

1910.215 B09

Serious Gravity 1 1 instance 1 exposed
Issued
Oct 17, 2012
Penalty
Initial $0 · Current $0
29 CFR 1910.215(b)(9):  The distance between the abrasive wheel periphery(s) and the adjustable tongue or the end of the safety guard peripheral at the top exceeded one fourth inch:    (a)  Integrity Plastics, Inc., 10 Industrial Drive, Denver, PA - Employees used a Dewalt 6-inch bench grinder (# 756, Serial number 290338-YL0232) to remove clips on air hoses and were exposed to an impact/flying particle hazard when the space between the tongue guard and grinding wheel exceeded one fourth of an inch, on or about September 19, 2012.    No abatement certification or documentation required.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.304 G05

Serious Gravity 5 1 instance 2 exposed
Issued
Oct 17, 2012
Abate by
Nov 7, 2012
Penalty
Initial $3,500 · Current $2,625 Reduced
29 CFR 1910.304(g)(5): The path to ground from circuits, equipment, and enclosures was not permanent, continuous, and effective:    (a)  Integrity Plastics, Inc., 10 Industrial Way, Denver, PA - An ungrounded 110-volt soda machine in the breakroom contained an energized outer casing, thus exposing employees to possible electrical shock hazards, on or about September 19, 2012.    (b)  Integrity Plastics, Inc., 10 Industrial Way, Denver, PA - Two (2) 110-volt ungrounded pedestal fans contained energized outer coverings, thus exposing employees to possible electrical shock hazards, on or about September 19, 2012.    Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (S) $2625
  • — Z (S) $3500

1910.22 D01

Other-than-serious 1 instance 1 exposed
Issued
Oct 17, 2012
Abate by
Nov 7, 2012
Penalty
Initial $0 · Current $0
29 CFR 1910.22(d)(1):  In every building or other structure, or part thereof, used for mercantile, business, industrial, or storage purposes, the loads approved by the building official were not marked on plates of approved design which must be supplied and securely affixed by the owner of the building, or his duly authorized agent, in a conspicuous place in each space to which they relate:    (a)  Integrity Plastics, Inc., 10 Industrial Drive, Denver, PA - Employees stored boxes and skids of various items on the top of the tool room and did not have a posted load rating sign, exposing employees working underneath to a potential crush hazard, on or about September 19, 2012.    Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (O) $0
  • — Z (O) $0

1910.23 C01

Other-than-serious 1 instance 1 exposed
Issued
Oct 17, 2012
Abate by
Nov 7, 2012
Penalty
Initial $0 · Current $0
29 CFR 1910.23(c)(1):  Every open-sided floor or platform 4 feet or more above adjacent floor or ground level was not guarded by a standard railing (or the equivalent as specified in paragraph (e)(3) of this section) on all open sides except where there is entrance to a ramp, stairway, or fixed ladder. The railing shall be provided with a toeboard wherever, beneath the open sides:    (a)  Integrity Plastics, Inc., 10 Industrial Drive, Denver, PA - Employees performing work activities above the tool room were exposed to an approximate 10.5 foot fall hazard when the midrail was missing on the guardrail system which surrounded the frontside (approximately 20.5 feet long) of the top of the tool room, on or about September 19, 2012.    Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (O) $0
  • — Z (O) $0

View Integrity Plastics, Incorporated's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 336442785.