OSHA Inspection: TROPICAL STONE LLC

Complaint inspection · Safety discipline

On , OSHA opened a complaint safety inspection of TROPICAL STONE LLC in 4 LEE BOULEVARD, MALVERN, PA 19355 (NAICS 423320). OSHA activity number 336521588.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Tropical Stone LLC — free Get an email when a new federal OSHA severe-injury report for Tropical Stone LLC is published. One employer, no account, unsubscribe in one click.
Establishment
TROPICAL STONE LLC
Site address
4 LEE BOULEVARD
City
MALVERN
State
PA
ZIP
19355
Mailing
4 LEE BOULEVARD, MALVERN, PA 19355
Inspection type
Complaint (B)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
423320
Employees
5
Ownership type
A

8 citations on file for this inspection.

1910.37 A03

Serious Gravity 5 2 instances 3 exposed
Issued
Mar 20, 2013
Abate by
Mar 26, 2013
Penalty
Initial $2,000 · Current $1,200 Reduced
29 CFR 1910.37(a)(3):     Exit route(s) were not kept free and unobstructed. Materials or equipment were placed, either permanently or temporarily, within the exit route. The exit access led into a dead-end corridor:    a) Jobsite: 4 Lee Boulevard, Malvern, Main Floor, East and South sides of building - Two exit routes were obstructed by stone materials and equipment that were placed within the exit routes exposing the employees to entrapment and serious injuries. Observed on or about 09/21/2012.    b) Jobsite: 4 Lee Boulevard, Malvern, Main Floor, East side of building - A sign showing an exit access led into a dead-end corridor exposing employees to entrapment and serious injuries. Observed on or about 09/21/2012.
Recent events (2)
  • — I (S) $1200
  • — Z (S) $2000

1910.36 D02

Serious Gravity 5 1 instance 3 exposed
Issued
Mar 20, 2013
Abate by
Apr 1, 2013
Penalty
Initial $0 · Current $0
29 CFR 1910.36(d)(2):     Exit route doors must be free of any device or alarm that could restrict emergency use of the exit route if the device or alarm fails.    a) Jobsite: 4 Lee Boulevard, Malvern, Main Floor, West side of building - Employees were exposed to entrapment and serious injuries such as burns as the employer installed a sliding door pin lock to secure the door from inside. Observed on or about 09/21/2012.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.37 B04

Serious Gravity 5 1 instance 3 exposed
Issued
Mar 20, 2013
Abate by
Apr 1, 2013
Penalty
Initial $0 · Current $0
29 CFR 1910.37(b)(4):     Signs were not posted along the exit access indicating the direction of travel to the nearest exit and exit discharge when the direction of travel to the exit or exit discharge was not immediately apparent:    a) Jobsite: 4 Lee Boulevard, Malvern, Main Floor - The direction of travel to an exit was not immediately apparent because large stone slabs located at the worksite blocked the view of emergency exits at different places within the main floor. Observed on or about 09/21/2012.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.305 G01 IV A

Serious Gravity 1 1 instance 3 exposed
Issued
Mar 20, 2013
Abate by
Apr 8, 2013
Penalty
Initial $1,200 · Current $800 Reduced
29 CFR 1910.305(g)(1)(iv)(A):     Flexible cords and/or cables were used as a substitute for the fixed wiring of a structure:    a) Jobsite: 4 Lee Boulevard, Malvern, Main floor - A flexible cord was used as a substitute for a fixed wiring structure exposing the employees to potential electrical shock hazards. The flexible cable was intalled to provide greater lighting to show case areas on the main floor. Observed on or about 09/21/2012.
Recent events (2)
  • — I (S) $800
  • — Z (S) $1200

1910.332 B02

Serious Gravity 10 1 instance 1 exposed
Issued
Mar 20, 2013
Abate by
Mar 26, 2013
Penalty
Initial $2,800 · Current $1,500 Reduced
29 CFR 1910.332(b)(2):     Employees, who were not qualified persons, were not trained in and familiar with any electrically related safety practices not specifically addressed by 29 CFR 1910.331 through 29 CFR 1910.335, but which were necessary for their safety:    a) Jobsite: 4 Lee Boulevard, Malvern, Office Area, Bathroom - An employee was not trained in and familiar with any electrically related safety practices prior to installing fixtures for the bathroom and office areas. The employee was exposed to electrical hazards due to the lack of training as required by this section. Observed on or about 09/21/2012.
Recent events (2)
  • — I (S) $1500
  • — Z (S) $2800

1910.157 C01

Serious Gravity 5 1 instance 3 exposed
Issued
Mar 20, 2013
Abate by
Mar 28, 2013
Penalty
Initial $1,600 · Current $500 Reduced
29 CFR 1910.157(c)(1):     Portable fire extinguishers were not mounted, located and identified so that they were readily accessible without subjecting the employees to injuries:    a) Jobsite: 4 Lee Boulevard, Malvern - Portable fire extinguishers were not mounted, located and identified so that they were readily accessible without subjecting the employees to injuries. Observed on or about 09/21/2012.
Recent events (2)
  • — I (S) $500
  • — Z (S) $1600

1910.157 G01

Serious Gravity 5 1 instance 3 exposed
Issued
Mar 20, 2013
Abate by
Apr 22, 2013
Penalty
Initial $0 · Current $0
29 CFR 1910.157(g)(1):     An educational program was not provided for all employees to familiarize them with the general principles of fire extinguisher use and the hazards involved with incipient stage fire fighting:    a) Jobsite: 4 Lee Boulevard, Malvern - The employer did not provide an educational program for the employees to familiarize them with the general principles of fire extinguisher use and the hazards involved with incipient stage firefighting. Noted on or about 09/21/2012.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.157 E02

Serious Gravity 5 1 instance 3 exposed
Issued
Mar 20, 2013
Abate by
May 2, 2013
Penalty
Initial $0 · Current $0
29 CFR 1910.157(e)(2):     Portable fire extinguishers were not visually inspected at least monthly:      a) Jobsite: 4 Lee Boulevard, Malvern, Facility - The employer did not ensure that portable fire extinguishers were visually inspected at least monthly. Observed on or about 09/21/2012.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 336521588.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.