DES PLAINES, IL —
OSHA Inspection: JRC DESIGN BUILD, INC.
Planned inspection · Safety discipline
At a glance
On , OSHA opened a planned safety inspection of JRC DESIGN BUILD, INC. in 391 ARDMORE RD., DES PLAINES, IL 60016 (NAICS 238160). OSHA activity number 336765581.
Where did this inspection happen?
- Establishment
- JRC DESIGN BUILD, INC.
- Site address
- 391 ARDMORE RD.
- City
- DES PLAINES
- State
- IL
- ZIP
- 60016
- Mailing
- 1275 DAVIS, ARLINGTON HEIGHTS, IL 60005
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238160
- Employees
- 12
- Ownership type
- A
Citations
5 citations on file for this inspection.
1926.300 B01
- Issued
- Abate by
- Penalty
- Initial $1600.00 · Current $520.00 Reduced
General-duty citation text
29 CFR 1926.300(b)(1): Power operated tool(s), designed to accommodate guards, were not equipped with such guards when in use: a) Employees were using unguarded grinder. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (2)
- — I (S) $520
- — Z (S) $1600
1926.416 A01
- Issued
- Abate by
- Penalty
- Initial $2800.00 · Current $1120.00 Reduced
General-duty citation text
29 CFR 1926.416(a)(1): Employees were permitted to work in proximity to electric power circuits and were not protected against electric shock by de-energizing and grounding the circuits or effectively guarding the circuits by insulation or other means: a) Employees were not protected against accidental contact with energized overhead power lines during framing and carpentry work of the new addition to the house. The overhead power lines consisted of secondary lines having a voltage rating of 120/240 volts. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
- — I (S) $1120
- — Z (S) $2800
1926.501 B13
- Issued
- Penalty
- Initial $2800.00 · Current $1120.00 Reduced
General-duty citation text
29 CFR 1926.501(b)(13): Each employee engaged in residential construction activities 6 feet or more above lower levels was not protected by guardrail systems, safety net systems, or personal fall arrest systems, nor did the employer demonstrate that it is infeasible or creates a greater hazard to use these systems and develop and implement a fall protection plan which meets the requirements of paragraph (k) of section 1926.502: a) Employees engaged in roofing activity were not protected from fall hazards while working at an elevation of approximately 19 feet above the ground. No abatement certification or documentation is required for this item.
Recent events (2)
- — I (S) $1120
- — Z (S) $2800
1926.503 A01
- Issued
- Abate by
- Penalty
- Initial $2000.00 · Current $0.00 Reduced
General-duty citation text
29 CFR 1926.503(a)(1): The employer did not provide a training program for each employee who might be exposed to fall hazards: a) Employer did not provide training to each employee in order to recognize hazards associated with working at an elevation and to understand procedures to control or minimize those hazards. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (2)
- — I (S) $0
- — Z (S) $2000
1926.1053 B04
- Issued
- Abate by
- Penalty
- Initial $1600.00 · Current $520.00 Reduced
General-duty citation text
29 CFR 1926.1053(b)(4): Ladder(s) were used for purposes other than the purpose for which they were designed: a) Employees were exposed to fall hazards while using an a-frame ladder which was not unfolded. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (2)
- — I (S) $520
- — Z (S) $1600
More inspections at JRC DESIGN BUILD, INC.
ARLINGTON HEIGHTS, IL—2017-12-19 00:00:00
JRC DESIGN BUILD, INC.
ARLINGTON HEIGHTS, IL—2012-10-02 00:00:00
JRC DESIGN BUILD, INC.
View JRC DESIGN BUILD, INC.'s full OSHA safety record →
More inspections in this industry (NAICS 238160)
FAIRVIEW, TN—2026-07-16
MARVIN PINERA
CARSON CITY, NV—2026-07-16
UNKNOWN/INVALID ESTABLISHMENT
BANNOCKBURN, IL—2026-07-16
ROOFING H.P. LLC
LOXLEY, AL—2026-07-16
CARLOS CHE
BALTIMORE, MD—2026-07-16
VAL CONSTRUCTION INC
More inspections in IL
DEERFIELD, IL—2026-07-16
JOHN BURNS CONSTRUCTION COMPANY, LLC
BANNOCKBURN, IL—2026-07-16
BUILDER SERVICES GROUP, INC. DBA CJ INSULATION
BANNOCKBURN, IL—2026-07-16
ROOFING H.P. LLC
HIGHLAND PARK, IL—2026-07-16
UNITED PLUMBING AND DRAIN, INC.
FRANKLIN PARK, IL—2026-07-16
B & M PLASTIC INC.
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 336765581.