OSHA Inspection: J.P. CONSTRUCTION ENTERPRISES, CORP.

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of J.P. CONSTRUCTION ENTERPRISES, CORP. in 2445 HOLLYWOOD BLVD, HOLLYWOOD, FL 33021 (NAICS 238140). OSHA activity number 336794987.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch J.P. Construction Enterprises, Corp. — free Get an email when a new federal OSHA severe-injury report for J.P. Construction Enterprises, Corp. is published. One employer, no account, unsubscribe in one click.
Site address
2445 HOLLYWOOD BLVD
City
HOLLYWOOD
State
FL
ZIP
33021
Mailing
6261 SW 5TH STREET, MARGATE, FL 33068
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238140
Employees
4
Ownership type
A

8 citations on file for this inspection.

1926.451 B01

Serious Gravity 5 1 instance 2 exposed
Issued
Oct 31, 2012
Abate by
Nov 7, 2012
Penalty
Initial $1,600 · Current $1,600
29 CFR 1926.451(b)(1): Platform(s) on all working levels of scaffolds, were not fully planked or decked between the front uprights and guardrail supports such that the space between adjacent units, and the space between the platform and the uprights is no more than 1 inch wide:    On or about 10/10/2012, at 2445 Hollywood Blvd, Hollywood, Florida, two employees were working from a scaffold platform performing stucco work which was not fully planked exposing one of the employees to a fall hazard of approximately 13 feet to the ground.    NOTE: CERTIFICATION OF ABATEMENT IS REQUIRED FOR THIS VIOLATION.
Recent events (1)
  • — Z (S) $1600

1926.454 A

Serious Gravity 5 1 instance 2 exposed
Issued
Oct 31, 2012
Abate by
Nov 7, 2012
Penalty
Initial $0 · Current $0
29 CFR 1926.454(a): The employer did not have each employee who performed work while on a scaffold trained by a person qualified in the subject matter to recognize the hazards associated with the type of scaffold being used and to understand the procedures to control or minimize those hazards.      On or about 10/10/2012, at 2445 Hollywood Blvd, Hollywood, FL, employees working from a scaffold platform were not trained on how to recognize hazards associated with the scaffold.          NOTE: CERTIFICATION OF ABATEMENT IS REQUIRED FOR THIS VIOLATION.
Recent events (1)
  • — Z (S) $0

1926.451 E01

Serious Gravity 5 1 instance 2 exposed
Issued
Oct 31, 2012
Abate by
Nov 7, 2012
Penalty
Initial $1,600 · Current $1,600
29 CFR 1926.451(e)(1):When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, sturcure, personnel hoist, or similar surface was not used.  Crossbraces were used as a means of access:    On or about 10/10/2012, at 2445 Hollywood Blvd, Hollywood, FL, employees were working from a scaffold platform without a means of access.            NOTE: CERTIFICATION OF ABATEMENT IS REQUIRED FOR THIS VIOLATION.
Recent events (1)
  • — Z (S) $1600

1926.451 G01 VII

Serious Gravity 5 1 instance 1 exposed
Issued
Oct 31, 2012
Abate by
Nov 7, 2012
Penalty
Initial $1,600 · Current $1,600
29 CFR 1926.451(g)(1)(vii): Each employee on a scaffold, not otherwise specified in paragraphs (g)(1)(i) through (g)(1)(vi) of this section, more than 10 feet (3.1 m) above lower level was not protected from falls by the use of personal fall arrest systems or guardrail systems meeting the requirements of paragraph (g)(4) of this section:    On or about 10/10/2012, at 2445 Hollywood Blvd, Hollywood, FL, an employee was working from a scaffold platform without personal fall arrest system or guardrail system exposing the employee to a fall hazard of approximately 13 feet.    NOTE: CERTIFICATION OF ABATEMENT IS REQUIRED FOR THIS VIOLATION.
Recent events (1)
  • — Z (S) $1600

1926.451 F03

Serious Gravity 5 1 instance 2 exposed
Issued
Oct 31, 2012
Abate by
Nov 7, 2012
Penalty
Initial $0 · Current $0
29 CFR 1926.451(f)(3):Scaffolds and scaffold components were not inspected for visible defects by a competent person before each work shift, and after any occurrence which could affect a scaffold's structural integrity:    On or about 10/10/2012, at 2445 Hollywood Blvd, Hollywood, FL, an employee was working from a scaffold platform which was not inspected by a competent person exposing the employees to a fall hazard of approximately 13 feet.    NOTE: CERTIFICATION OF ABATEMENT IS REQUIRED FOR THIS VIOLATION.
Recent events (1)
  • — Z (S) $0

1926.454 B

Serious Gravity 5 1 instance 2 exposed
Issued
Oct 31, 2012
Abate by
Nov 7, 2012
Penalty
Initial $0 · Current $0
29 CFR 1926.454(b): The employer did not have each employee involved in erecting, disassembling, moving, operating, repairing, maintaining, or inspecting a scaffold trained by a competent person to recognize any hazards associated with the work in question.    On or about 10/10/2012, at 2445 Hollywood Blvd, Hollywood, FL, employees were conducting stucco work on a scaffold platform which was not erected by a competent person.          NOTE: CERTIFICATION OF ABATEMENT IS REQUIRED FOR THIS VIOLATION.
Recent events (1)
  • — Z (S) $0

1926.452 C02

Serious Gravity 5 1 instance 2 exposed
Issued
Oct 31, 2012
Abate by
Nov 7, 2012
Penalty
Initial $1,600 · Current $1,600
29 CFR 1926.452(c)(2): Tubular welded frame scaffold(s) were not properly braced by crossbracing or diagonal braces, or both, to secure vertical members laterally and to align them so that the erected scaffold was plumb, square, and rigid:    On or about 10/10/2012, at 2445 Hollywood Blvd, Hollywood, FL, employees were conducting stucco work on a scaffold platform with missing cross braces.    NOTE: CERTIFICATION OF ABATEMENT IS REQUIRED FOR THIS VIOLATION.
Recent events (1)
  • — Z (S) $1600

1926.451 C02

Other-than-serious 1 instance 2 exposed
Issued
Oct 31, 2012
Abate by
Nov 13, 2012
Penalty
Initial $0 · Current $0
29 CFR 1926.451(c)(2):Supported scaffold poles, legs, posts, frames, and uprights did not bear on base plates and mud sills or other adequate firm foundation:    On or about 10/10/2012, at 2445 Hollywood Blvd, Hollywood, FL, employees were working from a scaffold platform that was missing base plates.    NOTE: CERTIFICATION OF ABATEMENT IS REQUIRED WITH THIS VIOLATION.
Recent events (1)
  • — Z (O) $0

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 336794987.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.