Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: RAMOS CONSTRUCTION, CORP.

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of RAMOS CONSTRUCTION, CORP. in 2500 MEADOW DR., ROLLING MEADOWS, IL 60008 (NAICS 238170). OSHA activity number 337034797.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Ramos Construction, Corp. — free Get an email when a new federal OSHA severe-injury report for Ramos Construction, Corp. is published. One employer, no account, unsubscribe in one click.
Site address
2500 MEADOW DR.
City
ROLLING MEADOWS
State
IL
ZIP
60008
Mailing
769 CALICO DR., AURORA, IL 60506
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238170
Employees
7
Ownership type
A

9 citations on file for this inspection.

1903.19 C01

Other-than-serious 1 instance 1 exposed
Issued
Apr 12, 2013
Abate by
May 15, 2013
Penalty
Initial $400 · Current $400
29 CFR 1903.19(c)(1):  The employer did not certify to OSHA, within 10 calendar days after the abatement date, that the cited violation had been abated:    Ramos Construction, Corp. failed to certify to OSHA within 10 calendar days after the abatement date that each of the following cited violations had been corrected:     Citation Number                     Item Number                           Abatement Date  01                                           01                                           11/19/2012  01                                           02                                           11/19/2012  01                                           03                                           11/19/2012  01                                           04                                           11/19/2012  01                                           05                                           11/19/2012  01                                           06                                           11/19/2012 01                                           07a                                         12/17/2012 01                                           07b                                         12/17/2012  In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
  • — Z (O) $400

1926.100 A

Serious Gravity 5 1 instance 2 exposed
Issued
Nov 13, 2012
Abate by
Nov 19, 2012
Penalty
Initial $1,600 · Current $1,600
29 CFR 1926.100(a):  Employees were not protected by protective helmets while working in areas where there was a possible danger of head injury from impact, or from falling or flying objects, or from electrical shock and burns:    a)  Employees were not wearing protective helmets where there was a possible danger of head injury from falling objects.    In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
  • — Z (S) $1600

1926.451 B05 II

Serious Gravity 5 1 instance 2 exposed
Issued
Nov 13, 2012
Abate by
Nov 19, 2012
Penalty
Initial $1,600 · Current $1,600
29 CFR 1926.451(b)(5)(ii): The end of a platform greater than 10 feet in length extended over its support more than 18 inches and the platform was not designed and installed so that the cantilevered portion of the platform is able to support employees without tipping, or has guardrails which block employee access to the cantilevered end:    a)  Employees were working from a ladder jack scaffold platform which was extended approximately 3 feet over the end support.     In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
  • — Z (S) $1600

1926.451 E01

Serious Gravity 5 2 instances 3 exposed
Issued
Nov 13, 2012
Abate by
Nov 19, 2012
Penalty
Initial $2,400 · Current $2,400
29 CFR 1926.451(e)(1): When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, structure, personnel hoist, or similar surface was not used.     a)  Employees were not provided with safe access to a ladder jack scaffold platform being used at an elevation of up to approximately 13 feet above the ground.     In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
  • — Z (S) $2400

1926.451 F03

Serious Gravity 5 2 instances 4 exposed
Issued
Nov 13, 2012
Abate by
Nov 19, 2012
Penalty
Initial $1,600 · Current $1,600
29 CFR 1926.451(f)(3): Scaffolds and scaffold components were not inspected for visible defects by a competent person before each work shift, and after any occurrence which could affect a scaffold's structural integrity.    a) The scaffold and scaffold components were not inspected by a competent person.    In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
  • — Z (S) $1600

1926.451 F06

Serious Gravity 10 1 instance 2 exposed
Issued
Nov 13, 2012
Abate by
Nov 19, 2012
Penalty
Initial $2,800 · Current $2,800
29 CFR 1926.451(f)(6): Scaffolds were erected, used, dismantled, altered, or moved such that they, or any conductive material handled on them, could have come closer than the minimum distances established for specific voltages as set forth in the table in subparagraph (f)(6).    a)  Employer permitted to erect and use ladder jack scaffolding in close proximity to energized power lines having a voltage of 120/240 volts.     In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification.  This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (1)
  • — Z (S) $2800

1926.451 G01 I

Serious Gravity 5 2 instances 4 exposed
Issued
Nov 13, 2012
Abate by
Nov 19, 2012
Penalty
Initial $2,400 · Current $2,400
29 CFR 1926.451(g)(1)(i): Each employee on a boatswains' chair, catenary scaffold, float scaffold, needle beam scaffold, or ladder jack scaffold was not protected by a personal fall arrest system:    a) Employees were exposed to the hazard of falling while working from ladder jack scaffold platform elevated up to approximately 13 feet above the ground.     In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
  • — Z (S) $2400

1926.454 A

Serious Gravity 5 1 instance 4 exposed
Issued
Nov 13, 2012
Abate by
Dec 17, 2012
Penalty
Initial $1,600 · Current $1,600
29 CFR 1926.454(a):  The employer did not have each employee who performed work while on a scaffold trained by a person qualified in the subject matter to recognize the hazards associated with the type of scaffold being used and to understand the procedures to control or minimize those hazards:    a)  Employees were not trained to recognize and eliminate the hazards associated with working from scaffolding.    In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
  • — Z (S) $1600

1926.454 B

Serious Gravity 5 1 instance 4 exposed
Issued
Nov 13, 2012
Abate by
Dec 17, 2012
Penalty
Initial $0 · Current $0
29 CFR 1926.454(b): The employer did not have each employee involved in erecting, disassembling, moving, operating, repairing, maintaining, or inspecting a scaffold trained by a competent person to recognize any hazards associated with the work in question.    a) Employees were not trained in the recognition of hazards associated with erecting, disassembling, moving, or inspecting a scaffold.    In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
  • — Z (S) $0

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 337034797.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.