Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: GEORGE'S INC.

Planned inspection · Health discipline

On , OSHA opened a planned health inspection of GEORGE'S INC. in 9066 STATE HWY. W, CASSVILLE, MO 65625 (NAICS 311615). OSHA activity number 337645618.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch George'S INC. — free Get an email when a new federal OSHA severe-injury report for George'S INC. is published. One employer, no account, unsubscribe in one click.
Establishment
GEORGE'S INC.
Site address
9066 STATE HWY. W
City
CASSVILLE
State
MO
ZIP
65625
Mailing
9066 STATE HWY. W, CASSVILLE, MO 65625
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Health
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
311615
Employees
250
Ownership type
A

5 citations on file for this inspection.

1910.119 D03 I B

Serious 6 instances 250 exposed
Issued
Jan 10, 2013
Abate by
Feb 14, 2013
Penalty
Initial $7,000 · Current $4,900 Reduced
29 CFR 1910.119(d)(3)(i)(B):     The employer's piping and instrument diagrams were not accurate and did not represent equipment that was existing and was part of the process:      (a) The piping and instrumentation diagrams were not accurate for the red water chillers in that the drawings showed equipment in a different order from the way they were installed.  Valve#270 was shown on the drawing as being located between valve #269 and a pressure guage #267, but it was on the other side of #267 and after the ninety degree turn in the piping from horizontal to vertical;    (b) The piping and instrumentation diagrams were not accurate for the red water chillers in that a valve present in the unit and was part of the ammonia process was not on the drawings.  The hand valve located near valve #279 did not have an identification number;    (c) The piping and instrumentation diagrams were not accurate for the red water chillers in that the identification tags for some valves and other equipment did not match the numbers depicted on the P&ID drawings. Tag#281 was on a cylanoid and not on a hand valve where the drawings showed it to be;    (d) The piping and instrumentation diagrams were not accurate for the red water chillers in that a guage with the identification tag #286 did not appear on the P&ID drawings;    (e) The piping and instrumentation diagrams were not accurate in that old tag numbers were present on the equipment that were not on the P&ID drawings.  Those tag numbers included #101, #102 and #286; and    (f) The piping and instrumentation diagrams were not accurate for the red water chillers in that the drawings did not reflect the digital controls operating the system from a remote location.
Recent events (2)
  • — I (S) $4900
  • — Z (S) $7000

1910.119 J04 II

Deleted Serious Gravity 10 3 instances 250 exposed
Issued
Jan 10, 2013
Abate by
Feb 14, 2013
Penalty
Initial $7,000 · Current $0 Reduced
29 CFR 1910.119(j)(4)(ii):     Inspection and testing did not follow recognized and generally accepted good engineering practices:    (a) George's, Inc. did not do inspection and testing of lines covered by insulation and did not have a procedure to determine if insulated lines were corroding. They did not follow any recognized and generally accepted practices for inspecting for corrosion;    (b) George's, Inc. did not have a procedure or schedule for inspecting and testing thickness of tanks to determine if the thickness of the tank walls had changed.  Inspection and testing of tanks in the PSM covered ammonia refrigeration units did not follow recognized and generally accepted good engineering practices; and    (c) Inspection and testing of the thickness of the red water chiller tank walls was done after a leak was discovered.  Inspection and testing of the red water chiller tanks was not done per a preventive maintenance schedule that followed the guidelines of a recognized and generally accepted good engineering plan.
Recent events (2)
  • — I (S) $0
  • — Z (S) $7000

1910.119 J05

Deleted Serious Gravity 10 4 instances 20 exposed
Issued
Jan 10, 2013
Abate by
Feb 14, 2013
Penalty
Initial $7,000 · Current $0 Reduced
29 CFR 1910.119(j)(5):     The employer did not correct deficiencies in equipment that were outside acceptable limits (defined by the process safety information on paragraph (d) of this section) before use:    (a) George's, Inc. did not correct deficiencies in equipment wiring that did not meet the National Electric Code for Class I Division II and did not meet acceptable wiring procedures for commercial wiring per the National Electric Code including the following wiring hazards:         (i) Conduit was not completely sealed between two bidirectional valves located in the engine room on a Frick C-3 compressor, an area that was Class I Division II;       (ii) Conduit and junction box covers were left open with wires hanging out on a red water chillers located on the roof in open air and exposed to the weather;       (iii) A wire was left extending out from under the edge of a cover plate with copper exposed at the red water chillers on the roof in open air and exposed to the weather; and       (iv) The seal tite cover for TW wiring at the red water chillers had separated from the junction box on the roof in open air and exposed to the weather.
Recent events (2)
  • — I (S) $0
  • — Z (S) $7000

1910.119 L01

Deleted Serious Gravity 10 3 instances 250 exposed
Issued
Jan 10, 2013
Abate by
Feb 14, 2013
Penalty
Initial $7,000 · Current $0 Reduced
29 CFR 1910.119(l)(1):     The employer did not implement procedures to manage changes to process chemicals, technology, equipment, and procedures, and changes to facilities that affect a covered process:    (a) George's Inc. did not implement a procedure to manage changes made to the faility when they installed tarps and stands to hold the tarps over the red water chillers;    (b) George's Inc. did not implement a procedure to manage changes made to the red water chillers which included changing the analog monitoring system to a digital control system; and    (c) George's Inc. did not implement a procedure to manage changes and the installation of new equipment on the #3 screw that included installing a different bidirectional slide valve requiring a change in wiring.
Recent events (2)
  • — I (S) $0
  • — Z (S) $7000

1910.146 C02

Deleted Serious Gravity 5 2 instances 250 exposed
Issued
Jan 10, 2013
Abate by
Feb 14, 2013
Penalty
Initial $5,000 · Current $0 Reduced
29 CFR 1910.146(c)(2):     The employer did not inform exposed employees, by posting danger signs or by any other equally effective means, of the existence and location of and the danger posed by the permit spaces:    (a) The ventilation system duct on the roof was not labeled as a permit required confined space;    (b) Tanks at the waste water treatment plant were not labeled as a permit required confined space;
Recent events (2)
  • — I (S) $0
  • — Z (S) $5000

View George'S INC.'s full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 337645618.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.