OSHA Inspection: MARCEL POIRIER CONSTRUCTION

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of MARCEL POIRIER CONSTRUCTION in PORTLAND ROAD, YARMOUTH, ME 04096 (NAICS 238160). OSHA activity number 338920747.

What this inspection record means

OSHA opens inspections for many reasons: routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Marcel Poirier Construction for free Get an email when a new federal OSHA severe-injury report for Marcel Poirier Construction is published. One employer, no account, unsubscribe in one click.
Site address
PORTLAND ROAD
City
YARMOUTH
State
ME
ZIP
04096
Mailing
61 SOUTH STREET, BIDDEFORD, ME 04005
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
Non-union (B)
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238160
Employees
2
Ownership type
Private (A)

2 citations on file for this inspection.

1903.19 C01

Other-than-serious 1 instance 2 exposed
Issued
Jun 10, 2013
Abate by
Jul 26, 2013
Penalty
Initial $400 · Current $400
29 CFR 1903.19(c)(1): Within 10 calendar days after the abatement date, the employer must certify to OSHA (the Agency) that each cited violation has been abated, except as provided in paragraph (c)(2) of this section.  At the jobsite - The employer did not furnish the abatement required for citations issued within 10 calendar days, nor did they respond to the progress report letters sent 04/29/2013 and 05/14/2013.
Recent events (1)
  • · Z (O) $400

1926.453 B02 V

Serious Gravity 1 1 instance 1 exposed
Issued
Feb 28, 2013
Abate by
Mar 6, 2013
Penalty
Initial $1,200 · Current $1,200
29 CFR 1926.453(b)(2)(v): A body belt with lanyard attached to the boom or basket was not worn by employee(s) working from an aerial lift:    At the Jobsite - The employee working in the aerial lift was not tied off with belt or harness and lanyard.
Recent events (1)
  • · Z (S) $1200

View Marcel Poirier Construction's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). OSHA publishes its own view of this case as inspection number 338920747.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.