Safety Incidents OSHA Severe Injury Reports · 2015–2025
2,004,209Inspections Most recent open 2026-07-13 Last loaded 2026-07-17

OSHA Inspection: OLIVER & COMPANY

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of OLIVER & COMPANY in MIS HISTORICAL CENTER PROJECT, PRESIDIO OF SAN FRANCISCO 640 MASON STREET, SAN FRANCISCO, CA 94129 (NAICS 236220). OSHA activity number 338983307.

Watch Oliver & Company — free Get an email when a new federal OSHA severe-injury report for Oliver & Company is published. One employer, no account, unsubscribe in one click.
Establishment
OLIVER & COMPANY
Site address
MIS HISTORICAL CENTER PROJECT, PRESIDIO OF SAN FRANCISCO 640 MASON STREET
City
SAN FRANCISCO
State
CA
ZIP
94129
Mailing
1300 SOUTH 51ST STREET, RICHMOND, CA 94804
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
A
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
236220
Employees
70
Ownership type
A

5 citations on file for this inspection.

1910.1200 H01

Other-than-serious 1 instance 1 exposed
Issued
Abate by
Penalty
Initial $1785.00 · Current $1785.00
29 CFR 1910.1200(h)(1): Employees were not provided effective information and training on hazardous chemicals in their work area at the time of their initial assignment and whenever a new hazard that the employees had not been previously trained about was introduced into their work area:        Building 640 construction project, Presidio of San Francisco, CA - On or about March 29, 2013, and at times prior thereto, the employer did not protect its employees by training them on the hazards associated with Portland cement.  Employees had not been trained on all chemical and materials used at the worksite including the hazards, exposures, PPE, labeling and other forms of warnings on worksite chemicals and materials including Portland cement.
Recent events (2)
  • — I (O) $1785
  • — Z (S) $1785

1926.95 A

Deleted Serious Gravity 1 1 instance 3 exposed
Issued
Abate by
Penalty
Initial $1785.00 · Current $0.00 Reduced
29 CFR 1926.95(a): Personal protective equipment, including personal protective equipment for eyes, face, head, and extremities, protective clothing, respiratory devices, and protective shields and barriers, was not provided, used, or maintained in a sanitary and reliable condition it was necessary by reason of hazards of processes or environment, chemical hazards, radiological hazards, or mechanical irritants encountered in a manner capable of causing injury or impairment in the function of any part of the body through absorption, inhalation, or physical contact:   Building 640 construction project, Presidio of San Francisco, CA - On or about March 29, 2013, and at times prior thereto, thin latex cleaning gloves and gloves with rubber palms and a cotton mesh back side were used instead of gloves made of nitrile or butyl materials for protection against caustic materials such as wet Portland cement.
Recent events (2)
  • — I (S) $0
  • — Z (S) $1785

1926.300 B02

Deleted Serious Gravity 5 1 instance 3 exposed
Issued
Abate by
Penalty
Initial $2975.00 · Current $0.00 Reduced
29 CFR 1926.300(b)(2): Moving part(s) of equipment exposed to contact by employees or which otherwise created a hazard, were not guarded:   a) Building 640 construction project, Presidio of San Francisco, CA - On or about March 29, 2013, and at times prior, the employer did not protect its employees by failing to fully guard the belt of a table saw exposing workers to serious physical harm.     b) Building 640 construction project, Presidio of San Francisco, CA - On or about March 29, 2013, and at times prior, the employer did not protect its employees by failing to fully guard the saw blade of a table saw exposing workers to serious physical harm.
Recent events (2)
  • — I (S) $0
  • — Z (S) $2975

1926.403 B02

Other-than-serious 1 instance 1 exposed
Issued
Abate by
Penalty
Initial $1785.00 · Current $1785.00
29 CFR 1926.403(b)(2): Listed, labeled, or certified equipment was not installed and used in accordance with instructions included in the listing, labeling, or certification:     Building 640 construction project, Presidio of San Francisco, CA - On or about March 29, 2013, and at times prior thereto, the employer did not protect its employees against electrical hazards by having providing and using an Ace 6 Outlet Home Appliance Power Strip designed for use with low-powered loads and not intended for use at construction sites and with power tools that exceed its capacity.
Recent events (2)
  • — I (O) $1785
  • — Z (S) $1785

1926.452 W02

Other-than-serious 1 instance 1 exposed
Issued
Abate by
Penalty
Initial $3570.00 · Current $2678.00 Reduced
29 CFR 1926.452(w)(2): Scaffold casters and wheels were not locked with positive wheel and/or wheel and swivel locks, or equivalent means, to prevent movement of the scaffold while the scaffold was used in a stationary manner:     Building 640 construction project, Presidio of San Francisco, CA - On or about March 29, 2013, and at times prior thereto, the General Contractor, Oliver & Company, did not ensure that the Subcontractor, Basco Drywall, protected their employees when working on a mobile scaffold. The mobile scaffold did not have the wheels/casters locked while the work tasks were performed exposing employees to serious fall injuries.
Recent events (2)
  • — I (O) $2677.5
  • — Z (S) $3570

View OLIVER & COMPANY's full OSHA safety record →