Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,196,991Inspections Most recent open 2026-08-24 Last loaded 2026-08-27

OSHA Inspection: ATLANTIC 3 CONSTRUCTION CO.

Referral inspection · Safety discipline

On , OSHA opened a referral safety inspection of ATLANTIC 3 CONSTRUCTION CO. in UMBRIA VILLAGE 4892 UMBRIA ST., PHILADELPHIA, PA 19128 (NAICS 238140). OSHA activity number 339149072.

What this inspection record means

OSHA opens inspections for many reasons: routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Atlantic 3 Construction CO. for free Get an email when a new federal OSHA severe-injury report for Atlantic 3 Construction CO. is published. One employer, no account, unsubscribe in one click.
Site address
UMBRIA VILLAGE 4892 UMBRIA ST.
City
PHILADELPHIA
State
PA
ZIP
19128
Mailing
605 COUNTY LINE RD., HUNTINGDON VALLEY, PA 19006
Inspection type
Referral (C)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
Union (A)
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238140
Employees
15
Ownership type
Private (A)

5 citations on file for this inspection.

1926.451 G01 VII

Serious Gravity 10 2 instances 2 exposed
Issued
Nov 14, 2013
Abate by
Nov 20, 2013
Penalty
Initial $2,800 · Current $2,800
29 CFR 1926.451(g)(1)(vii): Each employee on a scaffold, not otherwise specified in paragraphs (g)(1)(i) through (g)(1)(vi) of this section, more than 10 feet (3.1 m) above lower level was not protected from falls by the use of personal fall arrest systems or guardrail systems meeting the requirements of paragraph (g)(4) of this section.  a) Jobsite:  Umbria Village - An employee was performing masonry operations from a fabricated frame scaffold, approximately 33 feet above ground level with no fall protection.  Observed on or about 6/27/13.    b) Jobsite:  Umbria Village - An employee was performing masonry operations from a fabricated frame scaffold, approximately 26 feet above ground level with no fall protection.  Observed on or about 6/27/13.    Note:  Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (1)
  • · Z (S) $2800

1926.451 G04 I

Serious Gravity 10 2 instances 2 exposed
Issued
Nov 14, 2013
Abate by
Nov 20, 2013
Penalty
Initial $0 · Current $0
29 CFR 1926.451(g)(4)(i): Guardrail systems were not installed along all open sides and ends of platforms.   a) Jobsite:  Umbria Village - An employee was performing masonry operations within approximately 2 feet of the open end of an outrigger with no guardrail system approximately 31 feet above ground level, exposing the employee to a fall hazard.  Observed on or about 6/27/13.     b) Jobsite:  Umbria Village - An employee was performing masonry operations from a fabricated frame scaffold, within 2 feet of the open end with no guardrail system approximately 26 feet above ground level, exposing the employee to a fall hazard.  Observed on or about 6/27/13.     Note:  Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (1)
  • · Z (S) $0

1926.451 B01

Serious Gravity 10 1 instance 1 exposed
Issued
Nov 14, 2013
Abate by
Nov 20, 2013
Penalty
Initial $2,800 · Current $2,800
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds was not fully planked or decked between the front uprights and the guardrail supports as specified in paragraphs 1926.451(b)(1)(i)-(ii)  a) Jobsite:  Umbria Village - An employee was performing masonry operations from a fabricated frame scaffold approximately 33 feet above ground level which was not fully planked, exposing the employee to a fall hazard.  Observed on or about 6/27/13.    Note:  Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (1)
  • · Z (S) $2800

1926.451 F14

Serious Gravity 10 1 instance 1 exposed
Issued
Nov 14, 2013
Abate by
Nov 20, 2013
Penalty
Initial $0 · Current $0
29 CFR 1926.451(f)(14): Makeshift devices, such as but not limited to boxes and barrels, were used on top of scaffold platforms to increase the working level height of employees:  a) Jobsite:  Umbria Village - An employee working from a fabricated frame scaffold approximately 26 feet above ground level with no fall protection climbed on top of three stacked cinderblocks, with bricks which he stacked on planks on the level above, exposing the employee to a fall hazard.  Observed on or about 6/27/13.    Note:  Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (1)
  • · Z (S) $0

1926.451 E01

Serious Gravity 5 2 instances 3 exposed
Issued
Nov 14, 2013
Abate by
Nov 20, 2013
Penalty
Initial $2,000 · Current $2,000
29 CFR 1926.451(e)(1): When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, structure, personnel hoist, or similar surface was not used:  a) Jobsite:  Umbria Village - A ladder or other means of access was not provided for employees performing masonry operations on the 5th level of a fabricated frame scaffold approximately 26 feet above ground level, exposing employees to a fall hazard.  Observed on or about 6/27/13.     b) Jobsite:  Umbria Village - A ladder or other means of access was not provided for employees performing masonry operations on an outrigger, approximately 5 feet above the working platform on the 5th level of a fabricated frame scaffold, exposing employees to a fall hazard.  Observed on or about 6/27/13.    Note:  Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (1)
  • · Z (S) $2000

View Atlantic 3 Construction CO.'s full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). OSHA publishes its own view of this case as inspection number 339149072.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.