Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,194,531Inspections Most recent open 2026-08-11 Last loaded 2026-08-14

OSHA Inspection: DIRECT CONSTRUCTION

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of DIRECT CONSTRUCTION in 5001 PALISADES NW, WASHINGTON, DC 20002 (NAICS 238140). OSHA activity number 339214355.

What this inspection record means

OSHA opens inspections for many reasons: routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Direct Construction for free Get an email when a new federal OSHA severe-injury report for Direct Construction is published. One employer, no account, unsubscribe in one click.
Establishment
DIRECT CONSTRUCTION
Site address
5001 PALISADES NW
City
WASHINGTON
State
DC
ZIP
20002
Mailing
10 BYRD'S EYE COURT, GERMANTOWN, MD 20874
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238140
Employees
3
Ownership type
A

3 citations on file for this inspection.

1926.100 A

Serious Gravity 10 1 instance 1 exposed
Issued
Sep 9, 2013
Penalty
Initial $2,520 · Current $2,520
29 CFR 1926.100(a): Employees were not protected by protective helmets while working in areas where there was a possible danger of head injury from impact, or from falling or flying objects, or from electrical shock and burns:  a) On June 24, 2013 and at times prior thereto; front of residential home; employees were observed working near and/or under the scaffold system or roof area without any head protection that would protect them from fall debris, materials or tools used in the process.
Recent events (1)
  • · Z (S) $2520

1926.451 E01

Serious Gravity 10 1 instance 1 exposed
Issued
Sep 9, 2013
Abate by
Oct 3, 2013
Penalty
Initial $2,520 · Current $2,520
29 CFR 1926.451(e)(1): When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, structure, personnel hoist, or similar surface was not used.  Cross-braces were used as a means of access.    a) On June 24, 2013 and at times prior thereto; front of building, employees were exposed to a fall of approximately 24 feet when accessing the scaffold system by climbing the frame.   Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (1)
  • · Z (S) $2520

1926.451 G01 VI

Serious Gravity 10 1 instance 1 exposed
Issued
Sep 9, 2013
Abate by
Oct 3, 2013
Penalty
Initial $2,520 · Current $2,520
29 CFR 1926.451(g)(1)(vi): Each employee performing overhand bricklaying operations from a supported scaffold was not protected from falling from all open sides and ends of the scaffold (except at the side next to the wall being laid) by the use of a personal fall arrest system or guard-rail system (with minimum 200 pound top-rail capacity).   a) On June 24, 2013 and at times prior thereto; Front of building; employees working on a scaffold system conducting masonry work were exposed to a 30 foot fall at the ends and work area of the working platform.   Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (1)
  • · Z (S) $2520

View Direct Construction's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 339214355.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.