Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,191,288Inspections Most recent open 2026-07-24 Last loaded 2026-07-29

OSHA Inspection: ALL PRO PAINTING & STUCCO

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of ALL PRO PAINTING & STUCCO in 22305 GOSSLING RD., SPRING, TX 77389 (NAICS 238140). OSHA activity number 339260838.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch ALL PRO Painting & Stucco — free Get an email when a new federal OSHA severe-injury report for ALL PRO Painting & Stucco is published. One employer, no account, unsubscribe in one click.
Site address
22305 GOSSLING RD.
City
SPRING
State
TX
ZIP
77389
Mailing
27200 BLUEBERRY HILL DR., OAK RIDGE NORTH, TX 77385
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238140
Employees
5
Ownership type
A

2 citations on file for this inspection.

1926.451 B01

Serious Gravity 10 1 instance 1 exposed
Issued
Aug 20, 2013
Abate by
Aug 26, 2013
Penalty
Initial $2,800 · Current $1,680 Reduced
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds was not fully planked or decked between the front uprights and the guardrail supports as specified in paragraphs 1926.451(b)(1)(i)-(ii):   The employer does not ensure that all working levels of scaffolds are fully planked.  This violation was observed on or about August 7, 2013, at the job site where an employee was exposed to a fall hazard when working from the third tier of a scaffold that was not fully planked.     Pursuant to 29 C.F.R. 1903.19, within ten (10) calendar days of the abatement date, the employer must submit documentation showing that it is in compliance with the standard, including describing the steps that it is taking to ensure that each platform on all working levels of scaffolds are fully planked.
Recent events (2)
  • — I (S) $1680
  • — Z (S) $2800

1926.451 G04 I

Serious Gravity 10 1 instance 1 exposed
Issued
Aug 20, 2013
Abate by
Aug 26, 2013
Penalty
Initial $0 · Current $0
29 CFR 1926.451(g)(4)(i): Guardrail systems were not installed along all open sides and ends of platforms.   The employer does not install guardrails along all open sides and ends of scaffold platforms.  This violation was observed on or about August 7, 2013, on the east side of the structure where an employee was exposed to a fall hazard when working from the third tier of a scaffold without guardrails.        Pursuant to 29 C.F.R. 1903.19, within ten (10) calendar days of the abatement date, the employer must submit documentation showing that it is in compliance with the standard, including describing the steps that it is taking to ensure that employees are protected from falling when working from scaffold platforms.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

View ALL PRO Painting & Stucco's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 339260838.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.