OSHA Inspection: WEST BLOCK, INC.

Complaint inspection · Safety discipline

On , OSHA opened a complaint safety inspection of WEST BLOCK, INC. in 94 RIVER STREET, EAST ELLIJAY, GA 30540 (NAICS 327331). OSHA activity number 339532244.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch West Block, INC. — free Get an email when a new federal OSHA severe-injury report for West Block, INC. is published. One employer, no account, unsubscribe in one click.
Establishment
WEST BLOCK, INC.
Site address
94 RIVER STREET
City
EAST ELLIJAY
State
GA
ZIP
30540
Mailing
PO BOX 128, EAST ELLIJAY, GA 30539
Inspection type
Complaint (B)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
327331
Employees
15
Ownership type
A

14 citations on file for this inspection.

1910.23 C03

Serious Gravity 5 1 instance 1 exposed
Issued
Mar 10, 2014
Abate by
Apr 10, 2014
Penalty
Initial $1,600 · Current $960 Reduced
29 CFR 1910.23(c)(3): Regardless of height, open-sided floors, walkways, platforms, or runways above or adjacent to dangerous equipment, pickling or galvanizing tanks, degreasing units, and similar hazards were not guarded with a standard railing and toe board.  a) Plant, Block Machine - The platform on the border of the hopper was not guarded, and employees were exposed to 7.0 ft. falls inside the hopper.  In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (2)
  • — I (S) $960
  • — Z (S) $1600

1910.147 C04 I

Serious Gravity 5 1 instance 2 exposed
Issued
Mar 10, 2014
Abate by
Apr 10, 2014
Penalty
Initial $2,000 · Current $1,200 Reduced
29 CFR 1910.147(c)(4)(i): Procedures were not developed, documented and utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section:  a) Plant - Authorized employees performed maintenance, lubrication and cleaning of the block machine. The employer did not develop, implement, and utilize a written lockout/tagout procedure to protect workers from hydraulic energy, electric energy, and moving and rotating parts.  In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
  • — I (S) $1200
  • — Z (S) $2000

1910.147 C06 II

Serious Gravity 5 1 instance 3 exposed
Issued
Mar 10, 2014
Abate by
Apr 10, 2014
Penalty
Initial $0 · Current $0
29 CFR 1910.147(c)(6)(ii): The employer did not certify that periodic inspections of the energy control procedures had been performed:  a) Plant - On or about 12/24/13 workers operated, maintained, cleaned, and lubricated equipment including (but not limited to) the Mixer (Block Plant), the Air Compressor (Block  Plant), the Boiler (Block Plant) , the Air Compressor (Ready Mix Plant), and the Gear Boxes/Conveyor (Ready Mix Plant). The employer did not certify that periodic, and at least annual inspections of the written lockout/tagout procedures had been performed and kept up to date.   In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.147 C07 IV

Serious Gravity 5 1 instance 4 exposed
Issued
Mar 10, 2014
Abate by
Apr 10, 2014
Penalty
Initial $0 · Current $0
29 CFR 1910.147(c)(7)(iv): The employer did not certify that employee training had been accomplished and kept up to date:  a) Plant - On or about 12/24/13 workers operated, maintained, cleaned, and lubricated equipment including (but not limited to) the Mixer (Block Plant), the Air Compressor (Block  Plant), the Boiler (Block Plant) , the Air Compressor (Ready Mix Plant), and the Gear Boxes/Conveyor (Ready Mix Plant). The employer did not certify that the training for the Control of Hazardous Energy and Lockout/Tagout had been completed and kept up to date.   In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.147 C05 II C 1

Serious Gravity 5 1 instance 3 exposed
Issued
Mar 10, 2014
Abate by
Apr 10, 2014
Penalty
Initial $2,000 · Current $1,200 Reduced
29 CFR 1910.147(c)(5)(ii)(C)(1): Lockout devices were not substantial enough to prevent removal without the use of excessive force or unusual techniques, such as with the use of bolt cutters or other metal cutting tools:(a)(LOCATION)(IDENTIFY SPECIFIC OPERATIONS AND/OR CONDITIONS)(IDENTIFY MACHINERY OR EQUIPMENT)  Plant - On or about 12/24/13 employees entered the cylindrical rotary mixer for (daily) cleaning. The plastic adapter for locking the panel switch was broken and loose, and came off without force or tools.  Employees were exposed to crush hazards.    In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
  • — I (S) $1200
  • — Z (S) $2000

1910.212 A01

Serious Gravity 10 1 instance 2 exposed
Issued
Mar 10, 2014
Abate by
Apr 10, 2014
Penalty
Initial $2,800 · Current $1,680 Reduced
29 CFR 1910.212(a)(1): One or more methods of machine guarding was not provided to protect the operator and other employees in the machine area from hazards such as those created by point of operation, ingoing nip points, and rotating parts:  a) Plant - On or about 12/24/13 a side of the block machine was not guarded, exposing employees to rotating parts, ingoing nip points, and mechanical components in reciprocating movement in the vertical direction.   In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
  • — I (S) $1680
  • — Z (S) $2800

1910.219 D01

Serious Gravity 10 1 instance 2 exposed
Issued
Mar 10, 2014
Abate by
Apr 10, 2014
Penalty
Initial $0 · Current $0
29 CFR 1910.219(d)(1): Pulley(s) with part(s) seven feet or less from the floor or work platform were not guarded in accordance with the requirements specified in 29 CFR 1910.219(m) and (o):  a) Plant - On or about 12/24/13 a side of the block machine was not guarded, exposing employees to an unprotected four-belt and pulley system.  In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.219 E03 I

Serious Gravity 10 1 instance 2 exposed
Issued
Mar 10, 2014
Abate by
Apr 10, 2014
Penalty
Initial $0 · Current $0
29 CFR 1910.219(e)(3)(i): Vertical or inclined belt(s) were not enclosed by guard(s) conforming to the requirements specified at 29 CFR 1910.219(m) and (o):  a) Plant - On or about 12/24/14 a side of the block machine was not guarded, exposing employees to an unprotected four-belt and pulley system.     In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.219 F03

Serious Gravity 10 1 instance 2 exposed
Issued
Mar 10, 2014
Abate by
Apr 10, 2014
Penalty
Initial $0 · Current $0
29 CFR 1910.219(f)(3): Sprocket wheels and chains which were seven -7 feet or less above floors or platforms were not enclosed:  a) Plant- On or about 12/24/13 a side of the block machine was not guarded, exposing employees to unprotected roller chains and sprockets.   In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.1200 H01

Serious Gravity 1 1 instance 5 exposed
Issued
Mar 10, 2014
Abate by
Apr 10, 2014
Penalty
Initial $1,200 · Current $720 Reduced
29 CFR 1910.1200(h)(1): Employees were not provided effective information and training on hazardous chemicals in their work area at the time of their initial assignment and whenever a new hazard that the employees had not been previously trained about was introduced into their work area:  a) Plant - On or about 12/24/13 employees came in contact with chemicals including (but not limited to) hydraulic fluid, Diesel fuel, Portland cement Type I/II, Portland cement Type S, and concrete additives. The employer did not train the employees in relation to the Hazard Communication Program, the "Right to Know", the hazardous properties of materials at the workplace, and the Globally Harmonized System of Classification and Labeling of Chemicals(GHS). (December 1, 2013 first compliance date for training on Labeling Elements and a standardized format for Safety Data Sheets (SDSs)).  In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET)
Recent events (2)
  • — I (S) $720
  • — Z (S) $1200

1910.95 D01

Other-than-serious 1 instance 5 exposed
Issued
Mar 10, 2014
Abate by
Apr 10, 2014
Penalty
Initial $0 · Current $0
29 CFR 1910.95(d)(1): When information indicated that any employee's exposure equaled or exceed the 8-hour time-weighted average of 85 decibels, the employer did not develop and implement a monitoring program:  a) Plant - On or about 12/24/13 employees operated jack hammers and worked in proximity of the block machine, and the employer did not assess the level of noise in the different sectors of the facility. (Two instantaneous measurements at 15.0 ft. from the block machine indicated 98.9 dB and 100.1 dB, respectively).    In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
  • — I (O) $0
  • — Z (O) $0

1910.157 E03

Other-than-serious 1 instance 2 exposed
Issued
Mar 10, 2014
Abate by
Apr 10, 2014
Penalty
Initial $0 · Current $0
29 CFR 1910.157(e)(3): Portable fire extinguishers were not subjected to an annual maintenance check:  a) Plant - On or about 12/24/13 the fire extinguisher situated in proximity of the rotary mixer was not subjected to an annual maintenance check.  The label indicated inspection due in one year after June 30, 2011.  In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (2)
  • — I (O) $0
  • — Z (O) $0

1910.178 L06

Other-than-serious 1 instance 1 exposed
Issued
Mar 10, 2014
Abate by
Apr 10, 2014
Penalty
Initial $0 · Current $0
29 CFR 1910.178(l)(6): The employer did not certify that each operator has been trained and evaluated as required by this paragraph (l):  On or about 12/24/13 workers operated the Hyster 80 Fortis forklift (turbo-Diesel) to transport blocks out of the conveyor, and the employer did not certify that the employees were trained and evaluated in relation to the safe operation of the vehicles.  In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (2)
  • — I (O) $0
  • — Z (O) $0

1910.303 B07 IV

Other-than-serious 1 instance 1 exposed
Issued
Mar 10, 2014
Abate by
Apr 10, 2014
Penalty
Initial $0 · Current $0
29 CFR 1910.303(b)(7)(iv): There were damaged parts that adversely affected safe operation or mechanical strength of the equipment, such as parts that were broken, bent, cut, or deteriorated by corrosion, chemical action, or overheating:  a) Plant - On or about 12/24/13 the control panel adjacent to the splitter machine had a damaged component. The  push (OFF) / pull (ON) button for the automatic mode was broken, and a steel bolt with hexagonal head was inserted to allow operation.  In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (2)
  • — I (O) $0
  • — Z (O) $0

View West Block, INC.'s full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 339532244.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.