WASHINGTON, DC ·
OSHA Inspection: H&H CONSTRUCTION DEVELOPMENT CO.
Planned inspection · Safety discipline
At a glance
On , OSHA opened a planned safety inspection of H&H CONSTRUCTION DEVELOPMENT CO. in 307 S ST.,NE, WASHINGTON, DC 20002 (NAICS 236118). OSHA activity number 339640021.
OSHA opens inspections for many reasons: routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- H&H CONSTRUCTION DEVELOPMENT CO.
- Site address
- 307 S ST.,NE
- City
- WASHINGTON
- State
- DC
- ZIP
- 20002
- Mailing
- 1300 CONGRESS ST.,SE, WASHINGTON, DC 20032
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Complete (A)
- Discipline
- Safety
- Advance notice
- No
- Union status
- Non-union (B)
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 236118
- Employees
- 15
- Ownership type
- Private (A)
Citations
3 citations on file for this inspection.
1926.252 A
- Issued
- Apr 17, 2014
- Abate by
- Apr 23, 2014
- Penalty
- Initial $1,600 · Current $1,600
General-duty citation text
29 CFR 1926.252(a): An enclosed chute of wood, or equivalent material, was not used where materials were dropped more than 20 feet to points lying outside the exterior walls of the building(s): a) Employees engaged in debris and roofing material removal from the approximately 35 foot high roof were throwing the debris and material to the ground exposing the foreman to struck-by hazards, on or about 03/20/14. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (1)
- · Z (S) $1600
1926.501 B13
- Issued
- Apr 17, 2014
- Abate by
- Apr 23, 2014
- Penalty
- Initial $2,800 · Current $2,800
General-duty citation text
29 CFR 1926.501(b)(13): Each employee(s) engaged in residential construction activities 6 feet (1.8 m) or more above lower levels were not protected by guardrail systems, safety net system, or personal fall arrest system, nor were employee(s) provided with an alternative fall protection measure under another provision of paragraph 1926.501 (b): a) Employees engaged in roofing activities on a flat roof approximately 35 feet in height were not using any form of fall protection exposing them to fall hazards, on or about 03/20/14. b) Employees engaged in roofing activities were working around an unguarded sun roof exposed to a fall hazard, on or about 03/20/14. c) Employees engaged in roofing activities were working around an unguarded roof hatch exposing them to a fall hazard, on or about 03/20/14. Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (1)
- · Z (S) $2800
1926.1052 C01 I
- Issued
- Apr 17, 2014
- Abate by
- Apr 23, 2014
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1926.1052(c)(1)(i): Stairways having four or more risers or rising more than 30 inches (76 cm), whichever is less, were not equipped with at least one handrail: a) Employees entered the building using a set of stairs which were 4 risers in height with no hand rail creating a fall hazard, on or about 03/20/14. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (1)
- · Z (O) $0
More inspections in this industry (NAICS 236118)
More inspections in DC
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). OSHA publishes its own view of this case as inspection number 339640021.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.