OSHA Inspection: H&H CONSTRUCTION DEVELOPMENT CO.

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of H&H CONSTRUCTION DEVELOPMENT CO. in 307 S ST.,NE, WASHINGTON, DC 20002 (NAICS 236118). OSHA activity number 339640021.

What this inspection record means

OSHA opens inspections for many reasons: routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch H&H Construction Development CO. for free Get an email when a new federal OSHA severe-injury report for H&H Construction Development CO. is published. One employer, no account, unsubscribe in one click.
Site address
307 S ST.,NE
City
WASHINGTON
State
DC
ZIP
20002
Mailing
1300 CONGRESS ST.,SE, WASHINGTON, DC 20032
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
Non-union (B)
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
236118
Employees
15
Ownership type
Private (A)

3 citations on file for this inspection.

1926.252 A

Serious Gravity 5 1 instance 1 exposed
Issued
Apr 17, 2014
Abate by
Apr 23, 2014
Penalty
Initial $1,600 · Current $1,600
29 CFR 1926.252(a): An enclosed chute of wood, or equivalent material, was not used where materials were dropped more than 20 feet to points lying outside the exterior walls of the building(s):  a) Employees engaged in debris and roofing material removal from the approximately 35 foot high roof were throwing the debris and material to the ground exposing the foreman to struck-by hazards, on or about 03/20/14.   Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (1)
  • · Z (S) $1600

1926.501 B13

Serious Gravity 10 3 instances 5 exposed
Issued
Apr 17, 2014
Abate by
Apr 23, 2014
Penalty
Initial $2,800 · Current $2,800
29 CFR 1926.501(b)(13): Each employee(s) engaged in residential construction activities 6 feet (1.8 m) or more above lower levels were not protected by guardrail systems, safety net system, or personal fall arrest system, nor were employee(s) provided with an alternative fall protection measure under another provision of paragraph 1926.501 (b):    a) Employees engaged in roofing activities on a flat roof approximately 35 feet in height were not using any form of fall protection exposing them to fall hazards, on or about 03/20/14.   b) Employees engaged in roofing activities were working around an unguarded sun roof exposed to a fall hazard, on or about 03/20/14.   c) Employees engaged in roofing activities were working around an unguarded roof hatch exposing them to a fall hazard, on or about 03/20/14.    Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (1)
  • · Z (S) $2800

1926.1052 C01 I

Other-than-serious 1 instance 5 exposed
Issued
Apr 17, 2014
Abate by
Apr 23, 2014
Penalty
Initial $0 · Current $0
29 CFR 1926.1052(c)(1)(i): Stairways having four or more risers or rising more than 30 inches (76 cm), whichever is less, were not equipped with at least one handrail:  a) Employees entered the building using a set of stairs which were 4 risers in height with no hand rail creating a fall hazard, on or about 03/20/14.   Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (1)
  • · Z (O) $0