OSHA Inspection: ALLIANCE CONSTRUCTION, INC.

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of ALLIANCE CONSTRUCTION, INC. in 2045 POLARIS PARKWAY, COLUMBUS, OH 43240 (NAICS 236118). OSHA activity number 339671950.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Alliance Construction, INC. — free Get an email when a new federal OSHA severe-injury report for Alliance Construction, INC. is published. One employer, no account, unsubscribe in one click.
Site address
2045 POLARIS PARKWAY
City
COLUMBUS
State
OH
ZIP
43240
Mailing
600 ENTERPRISE DRIVE, LEWIS CENTER, OH 43035
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
236118
Employees
15
Ownership type
A

6 citations on file for this inspection.

1926.350 A01

Serious Gravity 5 1 instance 15 exposed
Issued
May 21, 2014
Abate by
Jun 11, 2014
Penalty
Initial $2,244 · Current $1,122 Reduced
29 CFR 1926.350(a)(1): Valve protection caps shall be in place and secured.   a. In the first floor lobby area of the hotel where an Acetylene tank was stored, the valve protection cap was not in place, thereby exposing employees to struck-by and/or contact hazards.
Recent events (2)
  • — I (S) $1122
  • — Z (S) $2244

1926.350 A10

Serious Gravity 5 1 instance 15 exposed
Issued
May 21, 2014
Abate by
Jun 11, 2014
Penalty
Initial $0 · Current $0
29 CFR 1926.350(a)(10): Oxygen cylinders in storage shall be separated from fuel-gas cylinders or combustible materials (especially oil or grease), a minimum distance of 20 feet (6.1 m) or by a noncombustible barrier at least 5 feet (1.5 m) high having a fire-resistance rating of at least one-half hour.  a. In the first floor lobby area of the hotel where an Oxygen and Acetylene tanks were being stored, the tanks were stored 4 feet apart, thereby exposing employees to struck-by and/or contact hazards.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1926.350 A11

Serious Gravity 5 1 instance 15 exposed
Issued
May 21, 2014
Abate by
Jun 11, 2014
Penalty
Initial $0 · Current $0
29 CFR 1926.350(a)(11): Inside of buildings, cylinders shall be stored in a well-protected, well-ventilated, dry location, at least 20 feet (6.1 m) from highly combustible materials such as oil or excelsior. Cylinders should be stored in definitely assigned places away from elevators, stairs, or gangways. Assigned storage places shall be located where cylinders will not be knocked over or damaged by passing or falling objects, or subject to tampering by unauthorized persons. Cylinders shall not be kept in unventilated enclosures such as lockers and cupboards.  a. In the first floor lobby where oxygen and acetylene tanks were stored, the tanks were left unsecured in the open where they could be knocked over and damaged, thereby exposing employees to struck-by and/or contact hazards.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1926.501 B04 II

Serious Gravity 1 2 instances 15 exposed
Issued
May 21, 2014
Abate by
Jun 11, 2014
Penalty
Initial $1,122 · Current $561 Reduced
29 CFR 1926.501(b)(4)(ii): Each employee on a walking/working surface shall be protected from tripping in or stepping into or through holes (including skylights) by covers.  a. In the north stairwell 4th floor landing where construction workers accessed the 4th floor, a hole had been cut through the floor for an HVAC duct and a gap of 4.5 inches x 30.5 inches was left exposed, exposing employees to a trip hazard.   b. In the north stairwell 3rd floor landing where construction workers accessed the 4th floor, a hole had been cut through the floor for an HVAC duct and a gap of 4.5 inches x 30.5 inches was left exposed, exposing employees to a trip hazard.
Recent events (2)
  • — I (S) $561
  • — Z (S) $1122

1926.502 I03

Serious Gravity 1 1 instance 15 exposed
Issued
May 21, 2014
Abate by
Jun 11, 2014
Penalty
Initial $0 · Current $0
29 CFR 1926.502(i)(3): All covers shall be secured when installed so as to prevent accidental displacement by the wind, equipment, or employees.   a. In the north stairwell 2nd floor landing where construction workers accessed the 2nd floor, a hole had been cut through the floor for an HVAC duct and a gap of 4.5 inches x 30.5 inches was covered, but not secured, exposing employees to a trip hazard.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1926.502 I04

Serious Gravity 1 1 instance 15 exposed
Issued
May 21, 2014
Abate by
Jun 11, 2014
Penalty
Initial $0 · Current $0
29 CFR 1926.502(i)(4): All covers shall be color coded or they shall be marked with the word "HOLE" or "COVER" to provide warning of the hazard. Note: This provision does not apply to cast iron manhole covers or steel grates used on streets or roadways.   a. In the north stairwell 2nd floor landing where construction workers accessed the 2nd floor, a hole had been cut through the floor for an HVAC duct and a gap of 4.5 inches x 30.5 inches was covered, but not marked with Hole or Cover, exposing employees to a trip hazard.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

View Alliance Construction, INC.'s full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 339671950.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.