OSHA Inspection: AGUILAR MASONRY

Planned inspection · Health discipline

On , OSHA opened a planned health inspection of AGUILAR MASONRY in SHERIDAN & DEWEY, OKLAHOMA CITY, OK 73102 (NAICS 238140). OSHA activity number 339673345.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Aguilar Masonry — free Get an email when a new federal OSHA severe-injury report for Aguilar Masonry is published. One employer, no account, unsubscribe in one click.
Establishment
AGUILAR MASONRY
Site address
SHERIDAN & DEWEY
City
OKLAHOMA CITY
State
OK
ZIP
73102
Mailing
3501 LUPINE DRIVE, ROGERS, AR 72758
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Health
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238140
Employees
6
Ownership type
A

9 citations on file for this inspection.

1910.1200 E01

Serious Gravity 5 1 instance 5 exposed
Issued
Sep 17, 2014
Abate by
Sep 19, 2014
Penalty
Initial $2,000 · Current $2,000

Hazardous substances 9010

29 CFR 1910.1200(e)(1): The employer did not develop, implement, and/or maintain at the workplace a written hazard communication program which describes how the criteria specified in 29 CFR 1910.1200(f), (g), and (h) will be met: (Construction Reference: 1926.59)    a. On or about March 28, 2014, North Building, a written hazard communication program was not maintained at the school construction site where employees worked with hazards chemicals including but not limited to limestone (irritant), brick (crystalline silica hazard, irritant), and masonry cement (crystalline silica hazard, irritant).
Recent events (1)
  • — Z (S) $2000

1910.1200 G08

Serious Gravity 5 1 instance 5 exposed
Issued
Sep 17, 2014
Abate by
Sep 19, 2014
Penalty
Initial $0 · Current $0

Hazardous substances 9010

29 CFR 1910.1200(g)(8): The employer did not ensure that material safety data sheets were readily accessible to the employees in their work area during each work shift: (Construction Reference: 1926.59)   a. On or about March 28, 2014, North Building, a safety data sheets were not maintained at the school construction site where employees worked with hazards chemicals including but not limited to limestone (irritant), brick (crystalline silica hazard, irritant), and masonry cement (crystalline silica hazard, irritant).
Recent events (1)
  • — Z (S) $0

1910.1200 H03 II

Serious Gravity 5 1 instance 5 exposed
Issued
Sep 17, 2014
Abate by
Sep 19, 2014
Penalty
Initial $0 · Current $0

Hazardous substances 9010

29 CFR 1910.1200(h)(3)(ii): Employee training did not include the physical and health hazards of the chemicals in the work area:  (Construction Reference: 1926.59)    a. On or about March 28, 2014, North Building, the employer did not provide effective hazard communication training on the health effects of crystalline silica containing materials.  Employees worked with hazards chemicals including but not limited to brick (crystalline silica hazard, irritant), and masonry cement (crystalline silica hazard, irritant).
Recent events (1)
  • — Z (S) $0

1926.52 A

Serious Gravity 5 1 instance 1 exposed
Issued
Sep 17, 2014
Abate by
Sep 19, 2014
Penalty
Initial $2,000 · Current $2,000

Hazardous substances 8110

29 CFR 1926.52(a): Protection against the effects of noise was not provided for employee(s) exposed to sound levels which exceeded those listed in Table D-2 of 29 CFR part 1926.52:    a. On or about April 11, 2014, North Building, an employee who operated a cut-off saw was exposed to workplace noise at an 8-hr TWA of 95.7 dBA, or equivalently a noise dose of 222%.  The noise monitoring result was derived from a personal sampling time of 249 minutes and a non-sampled time of 231 minutes, assumed to be a zero noise exposure period.
Recent events (1)
  • — Z (S) $2000

1926.52 B

Serious Gravity 5 1 instance 1 exposed
Issued
Sep 17, 2014
Abate by
Sep 19, 2014
Penalty
Initial $0 · Current $0

Hazardous substances 8110

29 CFR 1926.52(b): Employees were subjected to sound levels exceeding those listed in table D-2 of 29 CFR 1926.52 and feasible administrative or engineering controls were not utilized to reduce sound levels:    a. On or about April 11, 2014, North Building, feasible administrative controls were not established and implemented to reduce work place noise for cutting bricks such as an employee rotation schedule for brick cut-off saw operation.
Recent events (1)
  • — Z (S) $0

1926.52 D01

Serious Gravity 5 1 instance 1 exposed
Issued
Sep 17, 2014
Abate by
Sep 19, 2014
Penalty
Initial $0 · Current $0

Hazardous substances 8110

29 CFR 1926.52(d)(1): In all cases where the sound levels exceeded the values shown in Table D-2 of 29 CFR 1926.52, a continuing, effective hearing conservation program was not administered:  a. On or about April 11, 2014, North Building, a hearing conservation program which included hearing conservation training, noise monitoring, and baseline and annual hearing tests, was not established for an employee who operated a cut-off saw.
Recent events (1)
  • — Z (S) $0

1926.451 B01 I

Serious Gravity 1 1 instance 5 exposed
Issued
Sep 17, 2014
Abate by
Sep 19, 2014
Penalty
Initial $1,200 · Current $1,200
29 CFR 1926.451(b)(1)(i): Each platform unit (e.g., scaffold plank, fabricated plank, fabricated deck, or fabricated platform) was not installed so that the space between adjacent units and the space between the platform and the uprights were no more than 1 inch (2.5 cm) wide, except where the employer can demonstrate that a wider space is necessary.    a. On or about March 28, 2014, North School Building, the blue fabricated metal frame scaffold platform was not fully planked and employees worked from scaffold platform to lay stone which exposes them to fall hazards.
Recent events (1)
  • — Z (S) $1200

1926.451 E01

Serious Gravity 1 1 instance 5 exposed
Issued
Sep 17, 2014
Abate by
Sep 19, 2014
Penalty
Initial $1,200 · Current $1,200
29 CFR 1926.451(e)(1): When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, structure, personnel hoist, or similar surface was not used.     a. On or about March 28, 2014, North Building, a ladder or other adequate means of scaffold access was not provided where five employees worked from scaffolding to lay stone which exposes them to fall hazards.
Recent events (1)
  • — Z (S) $1200

1926.451 H02 II

Serious Gravity 1 1 instance 5 exposed
Issued
Sep 17, 2014
Abate by
Sep 19, 2014
Penalty
Initial $1,200 · Current $1,200
29 CFR 1926.451(h)(2)(ii): A toeboard was not erected along the edge of platforms more than 10 feet (3.1 m) above lower levels for a distance sufficient to protect employees below:   a. On or about March 28, 2014, North School Building, the blue fabricated metal frame scaffold platform lacked toeboards and employees walking below the scaffold platform were exposed to struck-by hazards.
Recent events (1)
  • — Z (S) $1200

View Aguilar Masonry's full OSHA safety record →