Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: THE MAGGIORE COMPANIES

Referral inspection · Health discipline

On , OSHA opened a referral health inspection of THE MAGGIORE COMPANIES in 179 ALLYN STREET, HARTFORD, CT 06103 (NAICS 236116). OSHA activity number 339746919.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch The Maggiore Companies — free Get an email when a new federal OSHA severe-injury report for The Maggiore Companies is published. One employer, no account, unsubscribe in one click.
Site address
179 ALLYN STREET
City
HARTFORD
State
CT
ZIP
06103
Mailing
13 WHEELING AVENUE, WOBURN, MA 01801
Inspection type
Referral (C)
Scope
Partial (B)
Discipline
Health
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
236116
Employees
2
Ownership type
A

12 citations on file for this inspection.

1910.1200 E01

Serious Gravity 5 1 instance 2 exposed
Issued
Sep 19, 2014
Abate by
Nov 6, 2014
Penalty
Initial $2,000 · Current $1,200 Reduced

Hazardous substances 9020

29 CFR 1910.1200(e)(1): The employer did not develop, implement, and/or maintain at the workplace a written hazard communication program which describes how the criteria specified in 29 CFR 1910.1200(f), (g), and (h) will be met: (Construction Reference: 1926.59):  179 ALLYN STREET, HARTFORD, CONNECTICUT  On or about April 4, 2014, the employer had not developed a written hazard communication program addressing hazardous chemicals that may be used and/or encountered on this job site.  Hazardous chemicals expected on-site include, but are not limited to, asbestos and asbestos-containing materials.
Recent events (2)
  • — I (S) $1200
  • — Z (S) $2000

1926.1101 K01 II

Serious Gravity 5 2 instances 1 exposed
Issued
Sep 19, 2014
Abate by
Nov 6, 2014
Penalty
Initial $0 · Current $0

Hazardous substances 9020

29 CFR 1926.1101(k)(1)(ii): The employer did not include asbestos in the program established to comply with the Hazard Communication Standard (HCS) (� 1910.1200), did not ensure that each employee had access to labels on containers of asbestos and safety data sheets, did not ensure hazard communication training on asbestos in accordance with the provisions of the Hazard Communication Standard 29 CFR 1910.1200 as well as paragraphs (k)(9) and (10) of this section. The employer did not provide information on at least the following hazards: Cancer and lung effects.  179 ALLYN STREET, HARTFORD, CONNECTICUT  1.  On or about April 4, 2014, the employer instructed a laborer to cut four holes in the roof of the building to allow for installation of beams to support a cooling tower.  The employer was aware that the roofing material contained asbestos but did not provide the laborer with information pertaining to the health hazards of asbestos.  2.  On or about April 21, 2014, the employer instructed a laborer to dry sweep an area of the 6th floor that was coated with dust generated as asbestos-containing roofing material was removed using a power cutter.  Engineering controls and proper work practices were not employed when the roof was being cut.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1926.1101 E01

Serious Gravity 5 1 instance 2 exposed
Issued
Sep 19, 2014
Abate by
Nov 6, 2014
Penalty
Initial $2,000 · Current $1,200 Reduced

Hazardous substances 9020

29 CFR 1926.1101(e)(1): All Class I, II, and III asbestos work was not conducted within regulated areas:  179 ALLYN STREET, HARTFORD, CONNECTICUT  1.  On or about April 4, 2014, the employer did not ensure that a regulated area was established when asbestos-containing roofing material was penetrated in four locations using a Sawz-All.
Recent events (2)
  • — I (S) $1200
  • — Z (S) $2000

1926.1101 F01 I

Serious Gravity 5 1 instance 1 exposed
Issued
Sep 19, 2014
Abate by
Nov 6, 2014
Penalty
Initial $2,000 · Current $1,200 Reduced

Hazardous substances 9020

29 CFR 1926.1101(f)(1)(i): Where exposure monitoring was required under 29 CFR 1926.1101, the employer did not perform monitoring to determine accurately the airborne concentrations of asbestos to which employees were or potentially were exposed:  ROOF, 179 ALLYN STREET, HARTFORD, CONNECTICUT  On or about April 4, 2014, the employer directed an employee to use a SawzAll to cut four holes in asbestos-containing roofing material without conducting exposure monitoring.
Recent events (2)
  • — I (S) $1200
  • — Z (S) $2000

1926.1101 G01 II

Serious Gravity 5 1 instance 2 exposed
Issued
Sep 19, 2014
Abate by
Nov 6, 2014
Penalty
Initial $2,000 · Current $1,200 Reduced

Hazardous substances 9020

29 CFR 1926.1101(g)(1)(ii): The employer did not use engineering controls and work practices in all operations covered by 29 CFR 1926.1101, regardless of the levels of exposure, in the form of wet methods or wetting agents to control employee exposures during asbestos handling, mixing, removal, cutting, application and cleanup:  179 ALLYN STREET, HARTFORD, CONNECTICUT  On or about April 4, 2014, the employer directed an employee to use a SawzAll to cut four holes in asbestos-containing roofing material without providing instructions to use continuous misting and/or HEPA vacuuming during the cutting process.
Recent events (2)
  • — I (S) $1200
  • — Z (S) $2000

1926.1101 G07 I

Serious Gravity 5 1 instance 2 exposed
Issued
Sep 19, 2014
Abate by
Nov 6, 2014
Penalty
Initial $2,000 · Current $1,200 Reduced

Hazardous substances 9020

29 CFR 1926.1101(g)(7)(i): All Class II work was not supervised by a competent person as defined in 29 CFR 1926.1101(b):  179 ALLYN STREET, HARTFORD, CONNECTICUT   On or about April 4, 2014, the employer directed an employee to cut four holes in asbestos-containing roofing material for installation of support beams for a cooling tower.  The roof work was not supervised by a competent person.
Recent events (2)
  • — I (S) $1200
  • — Z (S) $2000

1926.1101 G08 II A

Serious Gravity 5 1 instance 2 exposed
Issued
Sep 19, 2014
Abate by
Nov 6, 2014
Penalty
Initial $2,000 · Current $1,200 Reduced

Hazardous substances 9020

29 CFR 1926.1101(g)(8)(ii)(A): Roofing materials containing asbestos were not removed in an intact state to the extent feasible:  ROOF, 179 ALLYN STREET, HARTFORD, CONNECTICUT  On or about April 4, 2014, the employer instructed an employee to use a SawzAll to cut four holes in asbestos-containing roofing material without using continuous misting of the blade or a HEPA vacuum to collect the resultant dust.
Recent events (2)
  • — I (S) $1200
  • — Z (S) $2000

1926.1101 G08 II C

Serious Gravity 5 1 instance 2 exposed
Issued
Sep 19, 2014
Abate by
Nov 6, 2014
Penalty
Initial $0 · Current $0
29 CFR 1926.1101(g)(8)(ii)(C): Cutting machines were not continuously misted during use:    ROOF, 179 ALLYN STREET, HARTFORD, CONNECTICUT  On or about April 4, 2014, the employer instructed an employee to cut four holes in asbestos-containing roofing material using a SawzAll power cutter.  The employer did not provide a means for misting the blade of the SawzAll nor did he instruct the employee to continuously mist the blade while cutting the roofing material.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1926.1101 G08 II D

Serious Gravity 5 1 instance 2 exposed
Issued
Sep 19, 2014
Abate by
Nov 6, 2014
Penalty
Initial $0 · Current $0

Hazardous substances 9020

29 CFR 1926.1101(g)(8)(ii)(D): When built-up roofing with asbestos-containing roofing felts and an aggregate surface were removed using a power roof cutter, the dust resulting from the cutting operation was not collected by a HEPA dust collector or was not vacuumed along the cut line:  ROOF, 179 ALLYN STREET, HARTFORD, CONNECTICUT  On or about April 4, 2014, the employer instructed an employee to cut four holes in asbestos-containing roofing material using a SawzAll power cutter.  The employer did not provide a means for collecting the dust generated during the cutting process with a HEPA dust collector or a HEPA vacuum for vacuuming along the cut line.  The employer also did not instruct the employee that the material needed to be wetted or the dust needed to be collected.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1926.1101 H01 II

Serious Gravity 5 1 instance 1 exposed
Issued
Sep 19, 2014
Abate by
Nov 6, 2014
Penalty
Initial $2,000 · Current $1,200 Reduced

Hazardous substances 9020

29 CFR 1926.1101(h)(1)(ii): Respirators were not used during Class II work where asbestos containing material was not removed in a substantially intact state:  179 ALLYN STREET, HARTFORD, CONNECTICUT  On or about April 4, 2014, the employer directed an employee to cut four holes in asbestos-containing roofing material using a SawzAll power cutter.  The power cutter does not maintain the intact state of the roofing material and dust is generated.  The employee was not provided with respiratory protection while doing the work.
Recent events (2)
  • — I (S) $1200
  • — Z (S) $2000

1926.1101 K02 I

Serious Gravity 5 1 instance 40 exposed
Issued
Sep 19, 2014
Abate by
Nov 6, 2014
Penalty
Initial $2,400 · Current $1,440 Reduced
29 CFR 1926.1101(k)(2)(i): Before work subject to this standard began, the building and/or facility owner(s) did not determine the presence, location and quantity of asbestos containing material (ACM) and/or presumed asbestos containing material (PACM) at the worksite pursuant to 29 CFR 1926.1101(k)(1):  179 ALLYN STREET, HARTFORD, CONNECTICUT  On or about April 4, 2014, the general contractor, who is also part owner of the building, directed subcontractors to conduct demolition activities without having a comprehensive pre-demolition asbestos survey completed prior to commencement of work.
Recent events (2)
  • — I (S) $1440
  • — Z (S) $2400

1926.1101 K09 I

Serious Gravity 5 2 instances 1 exposed
Issued
Sep 19, 2014
Abate by
Nov 6, 2014
Penalty
Initial $2,000 · Current $1,200 Reduced

Hazardous substances 9020

29 CFR 1926.1101(k)(9)(i): The employer did not institute, at no cost to employees, a training program for each employee who was likely to be exposed in excess of the permissible exposure limit (PEL) and for each employee who performed Class I through IV asbestos operations:  179 ALLYN STREET, HARTFORD, CONNECTICUT  1.  On or about April 4, 2014, the employer had not provided training related to asbestos for a laborer who would be cutting holes in asbestos-containing roofing material using a SawzAll power cutter.  2. On or about April 21, 2014, the employer had not provided training related to asbestos for a laborer who would be cleaning up dust and debris generated from removal of asbestos-containing roofing material.
Recent events (2)
  • — I (S) $1200
  • — Z (S) $2000

View The Maggiore Companies's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 339746919.