OSHA Inspection: DC ELECTRIC/HEARTLAND LIGHTING, INC.

Unprogrammed Related inspection · Safety discipline

On , OSHA opened an unprogrammed Related safety inspection of DC ELECTRIC/HEARTLAND LIGHTING, INC. in 17889 CHICAGO ST., OMAHA, NE 68118 (NAICS 238210). OSHA activity number 339753212.

What this inspection record means

OSHA opens inspections for many reasons: routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch DC Electric/Heartland Lighting, INC. for free Get an email when a new federal OSHA severe-injury report for DC Electric/Heartland Lighting, INC. is published. One employer, no account, unsubscribe in one click.
Site address
17889 CHICAGO ST.
City
OMAHA
State
NE
ZIP
68118
Mailing
P.O. BOX 544, BELLEVUE, NE 68005
Inspection type
Unprogrammed Related (G)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
Non-union (B)
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238210
Employees
8
Ownership type
Private (A)

4 citations on file for this inspection.

1926.405 A02 II F

Serious Gravity 5 1 instance 1 exposed
Issued
Jul 7, 2014
Abate by
Jul 31, 2014
Penalty
Initial $1,600 · Current $1,600
29 CFR 1926.405(a)(2)(ii)(F):   Temporary lights were suspended by their electric cords when such lights and cords were not designed for suspension:   Worksite located at 17889 Chicago Street, Omaha, NE:  Temporary light fixtures installed on the 2nd floor were suspended by their cords.  The fixtures are designed to be suspended from a loop located at the top of the unit.     Abatement certification is required for this violation.  The abatement certification sheet is enclosed with the citations.
Recent events (1)
  • · Z (S) $1600

1926.403 I02 I

Serious Gravity 5 1 instance 1 exposed
Issued
Jul 7, 2014
Abate by
Jul 31, 2014
Penalty
Initial $1,600 · Current $1,600
29 CFR 1926.403(i)(2)(i):   Live parts of electric equipment operating at 50 volts or more were not guarded against accidental contact by cabinets or other forms of enclosures, nor by any of the means listed in subparagraphs (A) through (D) of this paragraph.  Worksite located at 17889 Chicago Street, Omaha, NE:  In the North stair tower on the 1st level, there was a light string were the splice left exposed live parts operating at 120 volts.  The splice was attempted using wire nuts and electrical tape but left the energized conductor exposed.      Abatement certification is required for this violation.  The abatement certification sheet is enclosed with the citations.
Recent events (1)
  • · Z (S) $1600

1926.405 G02 III

Serious Gravity 5 1 instance 1 exposed
Issued
Jul 7, 2014
Abate by
Jul 31, 2014
Penalty
Initial $1,600 · Current $1,600
29 CFR 1926.405(g)(2)(iii):   The repair splice in a hard service flexible cord No. 12 or larger did not retain the insulation, outer sheath properties, and usage characteristics of the cord which was being used:   Worksite located at 17889 Chicago Street, Omaha, NE:  At a number of locations throughout the structure (1st, 2nd, and 3rd floors), temporary lights strings were spliced without retaining the insulation and outer sheath properties or the cord.  The insulation was stripped back and the wire was spliced using wire nuts.      Abatement certification is required for this violation.  The abatement certification sheet is enclosed with the citations.
Recent events (1)
  • · Z (S) $1600

1926.405 G02 IV

Serious Gravity 5 1 instance 1 exposed
Issued
Jul 7, 2014
Abate by
Jul 31, 2014
Penalty
Initial $1,600 · Current $1,600
29 CFR 1926.405(g)(2)(iv):   Flexible cords were not connected to devices and fittings so that strain relief is provided to prevent pull from being directly transmitted to joints or terminal screws:   Worksite located at 17889 Chicago Street, Omaha, NE:  A cord and plug combination for the temporary lights on the 3rd floor had separated creating a strain relief issue with the plug.  Additionally, the initial installation created a strain issue between the male and female sections of the plug (suspended and pulling apart).      Abatement certification is required for this violation.  The abatement certification sheet is enclosed with the citations.
Recent events (1)
  • · Z (S) $1600

View DC Electric/Heartland Lighting, INC.'s full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). OSHA publishes its own view of this case as inspection number 339753212.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.