OSHA Inspection: ROSE PLASTIC USA, L.L.L.P.

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of ROSE PLASTIC USA, L.L.L.P. in 525 TECHNOLOGY DRIVE, COAL CENTER, PA 15423 (NAICS 326113). OSHA activity number 339793705.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Rose Plastic USA, L.L.L.P. — free Get an email when a new federal OSHA severe-injury report for Rose Plastic USA, L.L.L.P. is published. One employer, no account, unsubscribe in one click.
Site address
525 TECHNOLOGY DRIVE
City
COAL CENTER
State
PA
ZIP
15423
Mailing
P.O. BOX 698, CALIFORNIA, PA 15419
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
326113
Employees
90
Ownership type
A

3 citations on file for this inspection.

1910.147 C04 II

Other-than-serious 1 instance 3 exposed
Issued
Sep 17, 2014
Abate by
Jan 5, 2015
Penalty
Initial $2,800 · Current $1,680 Reduced
29 CFR 1910.147(c)(4)(ii): The energy control procedures did not clearly and specifically outline the scope, purpose, authorization, rules, and techniques to be utilized for the control of hazardous energy, including, but not limited to Items of this section:    (a) Facility, Blow and Injection Molding Machines: On or before July 22, 2014, the employer has not specifically developed energy isolation procedures designed for mold changes.
Recent events (2)
  • — I (O) $1680
  • — Z (S) $2800

1910.147 C07 I A

Other-than-serious 1 instance 3 exposed
Issued
Sep 17, 2014
Abate by
Jan 5, 2015
Penalty
Initial $0 · Current $0
29 CFR 1910.147(c)(7)(i)(A): Authorized employee(s) did not receive training in the recognition of applicable hazardous energy sources, the type and magnitude of the energy available in the workplace, and the methods and means necessary for energy isolation:     (a) Facility, Blow and Injection Molding Machines: On or before July 22, 2014, machine operators that change molds have not been trained to an authorized level under the employers hazardous energy control program.
Recent events (2)
  • — I (O) $0
  • — Z (S) $0

1910.147 D04 I

Other-than-serious 1 instance 1 exposed
Issued
Sep 17, 2014
Abate by
Jan 5, 2015
Penalty
Initial $0 · Current $0
29 CFR 1910.147(d)(4)(i): Lockout or tagout devices were not affixed to each energy isolating device by authorized employees:     (a) Facility, Blow Molding Machine Number Two: On or before July 22, 2014, an employee did not apply energy isolating devices to previously identified energy sources prior to performing a mold change.
Recent events (2)
  • — I (O) $0
  • — Z (S) $0

View Rose Plastic USA, L.L.L.P.'s full OSHA safety record →