WASHINGTON, DC —
OSHA Inspection: EURO CONSTRUCTION LLC
Planned inspection · Safety discipline
At a glance
On , OSHA opened a planned safety inspection of EURO CONSTRUCTION LLC in 12 ST AND H ST, NE, WASHINGTON, DC 20010 (NAICS 238140). OSHA activity number 339795940.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- EURO CONSTRUCTION LLC
- Site address
- 12 ST AND H ST, NE
- City
- WASHINGTON
- State
- DC
- ZIP
- 20010
- Mailing
- 13555 POINT PLEASANT DRIVE, CHANTILLY, VA 20151
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238140
- Employees
- 5
- Ownership type
- A
Citations
4 citations on file for this inspection.
1926.451 B01
- Issued
- Aug 27, 2014
- Abate by
- Sep 3, 2014
- Penalty
- Initial $1,600 · Current $800 Reduced
General-duty citation text
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds was not fully planked or decked between the front uprights and the guardrail supports as specified in paragraphs 1926.451(b)(1)(i)-(ii): a) 2nd Level Scaffold Section - Workers were observed installing stone blocks on a wall while working from a scaffold section that was not fully planked on or about May 28, 2014. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $800
- — Z (S) $1600
1926.451 E01
- Issued
- Aug 27, 2014
- Abate by
- Sep 3, 2014
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1926.451(e)(1): When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, structure, personnel hoist, or similar surface was not used. Cross braces were used as a means of access: a) Upper and Lower Scaffold Sections - Workers were observed using scaffold members to step up and step down 2 feet 6 inches to and from their working level on a tubular weld scaffold, on or about May 28, 2014. b) 2nd Level Scaffold Section and Transformer Rooftop - Workers were observed using the scaffold cross braces to climb up and down 3 feet 2 inches to and from the transformer's rooftop on or about May 28, 2014. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $0
- — Z (S) $0
1926.451 E08
- Issued
- Aug 27, 2014
- Abate by
- Sep 3, 2014
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1926.451(e)(8): Direct access to or from another surface was used when the scaffold was more than 14 inches (36 cm) horizontally and/or 24 inches (61 cm) vertically from the other surface: a) Transformer - Worker was observed stepping down 3 feet 2 inches from the rooftop to the scaffold's cross brace on or about May 28, 2014. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $0
- — Z (S) $0
1926.451 G04 I
- Issued
- Aug 27, 2014
- Abate by
- Sep 3, 2014
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1926.451(g)(4)(i): Guardrail systems were not installed along all open sides and ends of platforms: a) 2nd Scaffold Section - Workers were observed installing stone blocks on a wall while working from a tubular weld scaffold section that was missing some of its guardrails, on or about May 28, 2014. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $0
- — Z (S) $0
More inspections in this industry (NAICS 238140)
More inspections in DC
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 339795940.