Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,645Inspections Most recent open 2026-07-16 Last loaded 2026-07-20

OSHA Inspection: LAUREN MANUFACTURING, LLC

Complaint inspection · Safety discipline

On , OSHA opened a complaint safety inspection of LAUREN MANUFACTURING, LLC in 2228 REISER AVENUE, S.E., NEW PHILADELPHIA, OH 44663 (NAICS 326299). OSHA activity number 340221191.

Watch Lauren Manufacturing, LLC — free Get an email when a new federal OSHA severe-injury report for Lauren Manufacturing, LLC is published. One employer, no account, unsubscribe in one click.
Site address
2228 REISER AVENUE, S.E.
City
NEW PHILADELPHIA
State
OH
ZIP
44663
Mailing
2228 REISER AVENUE, S.E., NEW PHILADELPHIA, OH 44663
Inspection type
Complaint (B)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
A
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
326299
Employees
275
Ownership type
A

6 citations on file for this inspection.

1910.147 C04 II B

Serious Gravity 10 1 instance 19 exposed
Issued
Abate by
Penalty
Initial $7000.00 · Current $6000.00 Reduced
29 CFR 1910.147(c)(4)(ii): The procedures shall clearly and specifically outline the scope, purpose, authorization, rules, and techniques to be utilized for the control of hazardous energy, and the means to enforce compliance including, but not limited to, the following:    29 CFR 1910.147(c)(4)(ii)(B): Specific procedural steps for shutting down, isolating, blocking and securing machines or equipment to control hazardous energy;    a. The lockout procedure for the HSP-001 hydraulic press did not contain specific procedural steps for shutting down, isolating, blocking, and securing the electrical and gravitational energy sources.     b. The lockout procedure for the HSP-002 hydraulic press did not contain specific procedural steps for shutting down, isolating, blocking, and securing the electrical and gravitational energy sources.     c. The lockout procedure for the HSP-003 hydraulic press did not contain specific procedural steps for shutting down, isolating, blocking, and securing the electrical and gravitational energy sources.     d. The lockout procedure for the HSP-004 hydraulic press did not contain specific procedural steps for shutting down, isolating, blocking, and securing the electrical and gravitational energy sources.
Recent events (3)
  • — F (S) $6000
  • — C (S) $7000
  • — Z (S) $7000

1910.147 D02

Serious Gravity 10 2 instances 19 exposed
Issued
Abate by
Penalty
Initial $7000.00 · Current $0.00 Reduced
29 CFR 1910.147(d)(2): Machine or equipment shutdown. The machine or equipment shall be turned off or shut down using the procedures established for the machine or equipment. An orderly shutdown must be utilized to avoid any additional or increased hazard(s) to employees as a result of the equipment stoppage.      a. In the splice department, the employer does not require the hydraulic press HSP-002 to be locked out and de-energized during mold changes.     b. In the splice department, the employer does not require the hydraulic press HSP-003 to be locked out and de-energized during mold changes.
Recent events (3)
  • — F (S) $0
  • — C (S) $7000
  • — Z (S) $7000

1910.147 D05 I

Serious Gravity 10 4 instances 19 exposed
Issued
Abate by
Penalty
Initial $7000.00 · Current $0.00 Reduced
29 CFR 1910.147(d)(5)(i): Following the application of lockout or tagout devices to energy isolating devices, all potentially hazardous stored or residual energy shall be relieved, disconnected, restrained, and otherwise rendered safe.    a. During the lockout of hydraulic press HSP-001, the gravitational energy is not relieved, disconnected, restrained, or otherwise rendered safe.     b. During the lockout of hydraulic press HSP-002, the gravitational energy is not relieved, disconnected, restrained, or otherwise rendered safe.     c. During the lockout of hydraulic press HSP-003, the gravitational energy is not relieved, disconnected, restrained, or otherwise rendered safe.     d. During the lockout of hydraulic press HSP-004, the gravitational energy is not relieved, disconnected, restrained, or otherwise rendered safe.
Recent events (3)
  • — F (S) $0
  • — C (S) $7000
  • — Z (S) $7000

1910.147 C07 I A

Serious Gravity 10 1 instance 19 exposed
Issued
Abate by
Penalty
Initial $7000.00 · Current $6000.00 Reduced
29 CFR 1910.147(c)(7)(i)(A): Each authorized employee shall receive training in the recognition of applicable hazardous energy sources, the type and magnitude of the energy available in the workplace, and the methods and means necessary for energy isolation and control.    a. In the splice department, the employer did not provide lockout training for employees performing mold changes on the HSP-001, HSP-002, HSP-003, and HSP-004 hydraulic presses.
Recent events (3)
  • — F (S) $6000
  • — C (S) $7000
  • — Z (S) $7000

1910.212 A03 II

Repeat Gravity 10 2 instances 19 exposed
Issued
Abate by
Penalty
Initial $70000.00 · Current $50000.00 Reduced
29 CFR 1910.212(a)(3)(ii): The point of operation of machines whose operation exposes an employee to injury, shall be guarded. The guarding device shall be in conformity with any appropriate standards therefor, or, in the absence of applicable specific standards, shall be so designed and constructed as to prevent the operator from having any part of his body in the danger zone during the operating cycle.      a. In the splice department, the point of operation on hydraulic press HSP-002 was not adequately guarded, resulting in employee injuries.     b. In the splice department, the point of operation on hydraulic press HSP-003 was not adequately guarded, resulting in employee injuries.
Recent events (3)
  • — F (R) $50000
  • — C (W) $70000
  • — Z (W) $70000

1904.39 A02

Other-than-serious 1 instance 1 exposed
Issued
Abate by
Penalty
Initial $7000.00 · Current $1000.00 Reduced
29 CFR 1904.39(a)(2): Basic Requirement. Within twenty-four (24) hours after the in-patient hospitalization of one or more employees or an employee's amputation or an employee's loss of an eye, as a result of a work-related incident, you must report the in-patient hospitalization, amputation, or loss of an eye to OSHA.    a. On or about January 19, 2015, the employer did not report to OSHA an employee injury resulting in an in-patient hospitalization.
Recent events (3)
  • — F (O) $1000
  • — C (O) $7000
  • — Z (O) $7000

PRETRED

PRETRED

LIPPERT

PROVIA

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 340221191.