OSHA Inspection: IB CONTRACTORS

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of IB CONTRACTORS in 3707 14TH. ST., NW, WASHINGTON, DC 20005 (NAICS 238130). OSHA activity number 340508548.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch IB Contractors — free Get an email when a new federal OSHA severe-injury report for IB Contractors is published. One employer, no account, unsubscribe in one click.
Establishment
IB CONTRACTORS
Site address
3707 14TH. ST., NW
City
WASHINGTON
State
DC
ZIP
20005
Mailing
7651 OAKRIDGE WOODS COURT APT. B, LORTON, VA 22079
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238130
Employees
4
Ownership type
A

8 citations on file for this inspection.

1926.451 B01

Serious Gravity 5 1 instance 3 exposed
Issued
Sep 22, 2015
Abate by
Oct 10, 2015
Penalty
Initial $2,400 · Current $2,400
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds were not fully planked or decked between the front uprights and the guardrail supports as follows:   a)  Roof  On or about 03/31/2015, carpenters were exposed to a 9 foot fall from a wooden pole scaffold whose platform had not been fully or tightly planed between its uprights.  Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (1)
  • — Z (S) $2400

1926.452 A02

Serious Gravity 10 1 instance 3 exposed
Issued
Sep 22, 2015
Abate by
Oct 10, 2015
Penalty
Initial $0 · Current $0
29 CFR 1926.452(a)(2): Crossbracing was not installed between the inner and outer sets of poles on double pole scaffolds:    a)  Roof  On or about 03/31/2015, carpenters were exposed to a 9 foot fall from a wooden pole scaffold which had not been provided with cross bracing between its inside and outside vertical support poles.  Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (1)
  • — Z (S) $0

1926.452 A04

Serious Gravity 5 1 instance 3 exposed
Issued
Sep 22, 2015
Abate by
Oct 10, 2015
Penalty
Initial $0 · Current $0
29 CFR 1926.452(a)(4): Diagonal bracing in both directions were not installed across the entire outside face of all double- and single-pole scaffolds:   a)  Roof  On or about 03/31/2015, carpenters were exposed to a 9 foot fall from a wooden pole scaffold which had not been provided with diagonal bracing across all of its outside legs or face.  Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (1)
  • — Z (S) $0

1926.1053 B01

Serious Gravity 5 1 instance 3 exposed
Issued
Sep 22, 2015
Penalty
Initial $1,600 · Current $1,600
29 CFR 1926.1053(b)(1): Where (a) portable ladder(s) was/were used for access to an upper level landing surface and the ladder's length did not allow the ladder side rails to extend at least 3 feet (0.9 m) above the upper landing surface being accessed, the ladder was not secured at its top to a rigid support that will not deflect, and/or a grasping device was not provided to assist employees in mounting and dismounting the ladder:   a)  Roof  On or about 03/31/2015, carpenters were exposed to an 8 foot fall while using a step which did not project 3 feet above a pole scaffold platform and was not secured in place and provided with a grabrail.
Recent events (1)
  • — Z (S) $1600

1926.1053 B13

Serious Gravity 5 1 instance 3 exposed
Issued
Sep 22, 2015
Penalty
Initial $0 · Current $0
29 CFR 1926.1053(b)(13): The top or top step of a stepladder was used as a step:   a)  Roof  On or about 03/31/2015, carpenters were exposed to an 8 foot fall while using the top step of a 8 foot fiberglass ladder as they were gaining access the platform of a wooden pole scaffold.
Recent events (1)
  • — Z (S) $0

1926.452 A05

Serious Gravity 5 1 instance 3 exposed
Issued
Jun 12, 2015
Abate by
Jul 2, 2015
Penalty
Initial $0 · Current $0
29 CFR 1926.452(a)(5): Runners and bearers were not installed on edge:   a)  Roof  On or about 03/31/2015, carpenters were exposed to a 9 foot fall from a wooden pole scaffold whose 2 x 4 runners which were supporting the scaffold platform were not on their edges and were instead lying flat.    Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (1)
  • — Z (S) $0

1926.451 G01

Serious Gravity 10 1 instance 3 exposed
Issued
Jun 12, 2015
Abate by
Jul 2, 2015
Penalty
Initial $2,800 · Current $2,800
29 CFR 1926.451(g)(1): Each employee on a scaffold more than 10 feet (3.1 m) above a lower level shall be protected from falling to that lower level. Paragraphs (g)(1)(i) through (vii) of this section establish the types of fall protection to be provided to the employees on each type of scaffold. Paragraph (g)(2) of this section addresses fall protection for scaffold erectors and dismantlers:   a)  Roof - On or about 03/31/2015, carpenters occupying the platform of a pole scaffold were not provided with fall protection and were exposed to a 30 foot fall from the end of the scaffold platform.   Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (1)
  • — Z (S) $2800

1926.501 B10

Serious Gravity 10 1 instance 3 exposed
Issued
Jun 12, 2015
Penalty
Initial $2,800 · Current $2,800
29 CFR 1926.501(b)(10): Each employee engaged in roofing activities on low-slope roofs with unprotected sides and edges 6 feet or more above lower levels and 50-feet (15.25 m) wide or less, was not protected from falling by guardrail systems, safety nets:   a)  Stair Tower Roof  On about 03/31/2015, carpenters constructing the roof framing for a stair tower were exposed to a 40 foot inside fall and were not provided with fall protection.
Recent events (1)
  • — Z (S) $2800

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 340508548.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.