Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: RODRIQUEZ CONSTRUCTION, INC.

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of RODRIQUEZ CONSTRUCTION, INC. in 1506 Q STREET, NW, WASHINGTON, DC 20005 (NAICS 236118). OSHA activity number 340529361.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Rodriquez Construction, INC. — free Get an email when a new federal OSHA severe-injury report for Rodriquez Construction, INC. is published. One employer, no account, unsubscribe in one click.
Site address
1506 Q STREET, NW
City
WASHINGTON
State
DC
ZIP
20005
Mailing
306 S. WOLFE STREET, BALTIMORE, MD 21231
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
236118
Employees
7
Ownership type
A

8 citations on file for this inspection.

1926.21 B02

Serious Gravity 5 1 instance 6 exposed
Issued
Jun 29, 2015
Abate by
Jul 24, 2015
Penalty
Initial $3,500 · Current $3,500
29 CFR 1926.21(b)(2): The employer did not instruct each employee in the recognition and avoidance of unsafe conditions and the regulations applicable to his/her environment to control or eliminate any hazards or other exposure to illness or injury:  a) Job Site - Employees were not provided adequate training in the recognition and avoidance of hazards as evidenced by noted hazards such as but not limited to; not wearing eye and head protection,  not using a ground fault circuit interrupter, using damaged extension cords, and not using a personal fall arrest system, on or about 04/09/2015.  Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (1)
  • — Z (S) $3500

1926.102 A01

Serious Gravity 5 1 instance 1 exposed
Issued
Jun 29, 2015
Penalty
Initial $2,380 · Current $2,380
29 CFR 1926.102(a)(1): Eye and face protective equipment were not used when machines or operations presented potential eye or face injury from physical, chemical, or radiation agents:  a) Exterior Rear Lower Level - A laborer was observed cutting a piece of marble using a wet saw and not provided with eye protection, on or about 04/09/2015.
Recent events (1)
  • — Z (S) $2380

1926.100 A

Serious Gravity 5 1 instance 2 exposed
Issued
Jun 29, 2015
Abate by
Jul 6, 2015
Penalty
Initial $2,800 · Current $2,800
29 CFR 1926.100(a): Employees working in areas where there was a possible danger of head injury from impact, or falling or flying objects, or from electrical shock and burns, were not protected by protective helmets:  a) Exterior Rear - Employees were observed walking below a carpenter installing wood flooring on an exterior balcony and exposed to being struck by falling wood framing members, on or about 04/09/2015.  Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (1)
  • — Z (S) $2800

1926.404 B01 I

Serious Gravity 5 1 instance 1 exposed
Issued
Jun 29, 2015
Abate by
Jul 6, 2015
Penalty
Initial $2,800 · Current $2,800
29 CFR 1926.404(b)(1)(i): Employer did not use either ground fault circuit interrupters as specified in paragraph (b)(1)(ii) of this section, or an assured equipment grounding conductor program as specified in paragraph (b)(1)(iii) of this section to protect employees on construction sites:  a) Third Floor - A carpenter was using an extension cord to provide power to a DeWalt portable electric saw and was not provided with a ground fault circuit interrupter, on or about 04/09/2015.  Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (1)
  • — Z (S) $2800

1926.416 E01

Serious Gravity 5 1 instance 1 exposed
Issued
Jun 29, 2015
Abate by
Jul 6, 2015
Penalty
Initial $0 · Current $0
29 CFR 1926.416(e)(1): Worn or frayed electric cords or cables were used:  a) Exterior Rear Ground Level - A carpenter was using an extension cord to provide power to a portable air compressor and the extension cord was frayed with exposed copper conductor, on or about 04/09/2015.  Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (1)
  • — Z (S) $0

1926.453 B02 V

Serious Gravity 5 1 instance 1 exposed
Issued
Jun 29, 2015
Penalty
Initial $3,500 · Current $3,500
29 CFR 1926.453(b)(2)(v): A body belt was not worn and/or a lanyard was not attached to the boom or basket when working from an aerial lift*:   a) Exterior Rear of Building - An employee was observed in the basket of a JLG articulating boom lift basket not wearing a personal fall arrest system attached to the boom or basket, on or about 04/09/2015.   *Note:  As of January 1, 1998, subpart M of this part (1926.502(d)) provides that body belts are not acceptable as part of a personal fall arrest system. The use of a body belt in a tethering system or in a restraint system is acceptable and is regulated under 1926.502(e):
Recent events (1)
  • — Z (S) $3500

1926.501 B13

Serious Gravity 10 1 instance 1 exposed
Issued
Jun 29, 2015
Penalty
Initial $4,900 · Current $4,900
29 CFR 1926.501(b)(13): Each employee(s) engaged in residential construction activities 6 feet (1.8 m) or more above lower levels were not protected by guardrail systems, safety net system, or personal fall arrest system, nor were employee(s) provided with an alternative fall protection measure under another provision of paragraph 1926.501 (b):  a) Third Floor Balcony - An employee was observed standing on an unguarded balcony while installing wood floor members and exposed to a 35 ft., fall hazard, on or about 04/09/2015.
Recent events (1)
  • — Z (S) $4900

1926.503 A01

Serious Gravity 5 1 instance 2 exposed
Issued
Jun 29, 2015
Abate by
Jul 24, 2015
Penalty
Initial $0 · Current $0
29 CFR 1926.503(a)(1): The employer did not provide a training program for each employee potentially exposed to fall hazards to enable each employee to recognize the hazards of falling and the procedures to be followed in order to minimize these hazards:  a) Job Site - Employees were not provided with fall hazard recognition training as evidenced by noted hazards such as but not limited to; employee on an unguarded balcony exposed to a 35 ft., fall and an employee in the basket of a JLG articulating boom lift without fall protection and exposed to a 35 ft., fall hazard, on or about 04/09/2015.  Abatement certification is required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (1)
  • — Z (S) $0

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 340529361.