OSHA Inspection: SMART LINE CONTRACTORS, INC.

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of SMART LINE CONTRACTORS, INC. in CLUB HOUSE / LOT #48 W WOODS DRIVE, LITITZ, PA 17543 (NAICS 238130). OSHA activity number 340783711.

Watch Smart Line Contractors, INC. — free Get an email when a new federal OSHA severe-injury report for Smart Line Contractors, INC. is published. One employer, no account, unsubscribe in one click.
Site address
CLUB HOUSE / LOT #48 W WOODS DRIVE
City
LITITZ
State
PA
ZIP
17543
Mailing
PO BOX 6639 8400 BUSTELTON AVE SUITE 2, PHILADELPHIA, PA 19149
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238130
Employees
8
Ownership type
A

5 citations on file for this inspection.

1926.501 B11

Serious Gravity 5 1 instance 3 exposed
Issued
Abate by
Penalty
Initial $2000.00 · Current $2000.00
29 CFR 1926.501(b)(11): Each employee on a steep roof with unprotected sides and edges 6 feet (1.8 m) or more above lower levels was not protected from falling by guardrail systems with toeboards, safety net systems, or personal fall arrest systems:   a) Clubhouse area; Employees were installing plywood sheeting 16 feet 4 inches above the ground without the use of fall protection, on or about 07/17/2015.     Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (1)
  • — Z (S) $2000

1926.501 B13

Serious Gravity 5 1 instance 1 exposed
Issued
Abate by
Penalty
Initial $2000.00 · Current $2000.00
29 CFR 1926.501(b)(13): Each employee(s) engaged in residential construction activities 6 feet (1.8 m) or more above lower levels were not protected by guardrail systems, safety net system, or personal fall arrest system, nor were employee(s) provided with an alternative fall protection measure under another provision of paragraph 1926.501 (b):   a) Lot 48 West Wood Drive, Lititz, PA; An employee was installing plywood sheeting 10 feet 7 inches above the ground without the use of fall protection, on or about 07/17/2015.   Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (1)
  • — Z (S) $2000

1926.1053 B01

Serious Gravity 5 1 instance 1 exposed
Issued
Abate by
Penalty
Initial $2000.00 · Current $2000.00
29 CFR 1926.1053(b)(1): Where portable ladders were used for access to an upper landing surface and the ladder's length allows, the ladder side rails did not extend at least 3 feet (.9 m) above the upper landing surface being accessed:   a) Lot 48 West Wood Drive, Lititz, PA; Employees used a Werner 24 foot extension ladder that was not placed 3 feet above the landing to access and egress the roof work area, on about 07/17/2015.     Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (1)
  • — Z (S) $2000

1926.1053 B22

Serious Gravity 5 1 instance 1 exposed
Issued
Abate by
Penalty
Initial $2000.00 · Current $2000.00
29 CFR 1926.1053(b)(22): Employees  using ladders were carrying objects or loads that could cause the employee to lose balance and fall:   a) Lot 48 West Wood Drive, Lititz, PA; An employee was carrying plywood sheeting up a Werner 24 foot extension ladder, on or about 07/17/2015.  Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (1)
  • — Z (S) $2000

1926.1060 A

Serious Gravity 1 1 instance 4 exposed
Issued
Abate by
Penalty
Initial $1200.00 · Current $1200.00
29 CFR 1926.1060(a): The employer did not provide a training program for each employee using ladders and stairways, as necessary, which would train each employee in the procedures to be followed to minimize hazards related to ladders and stairways:   a) Lot 48 West Wood Drive, Lititz, PA; Employees were using a Werner 24 foot extension ladder without having been trained to recognize hazards related to ladder safety, on or about 07/17/2015.     Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (1)
  • — Z (S) $1200

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 340783711.