OSHA Inspection: ONEIDA MOLDED PLASTICS,LLC

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of ONEIDA MOLDED PLASTICS,LLC in 104 S. WARNER STREET, ONEIDA, NY 13421 (NAICS 326199). OSHA activity number 340789106.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Oneida Molded Plastics,Llc — free Get an email when a new federal OSHA severe-injury report for Oneida Molded Plastics,Llc is published. One employer, no account, unsubscribe in one click.
Site address
104 S. WARNER STREET
City
ONEIDA
State
NY
ZIP
13421
Mailing
104 S. WARNER STREET, ONEIDA, NY 13421
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
326199
Employees
204
Ownership type
A

10 citations on file for this inspection.

1910.37 A02

Serious Gravity 5 1 instance 2 exposed
Issued
Aug 14, 2015
Abate by
Aug 26, 2015
Penalty
Initial $3,825 · Current $2,295 Reduced
29 CFR 1910.37(a)(2): Exit routes were not arranged so that employees would not have to travel toward a high hazard area:    a)  Flammable storage room, on or about 7/21/15:  The door to the outside out the building inside the flammable storage room was locked and marked NOT AN EXIT thus requiring employees exiting the room in an emergency to go through the paint room, a high hazard area, where paint spray booth operations are conducted.    Abatement certification must be submitted for this item.
Recent events (2)
  • — I (S) $2295
  • — Z (S) $3825

1910.107 B06

Serious Gravity 5 2 instances 2 exposed
Issued
Aug 14, 2015
Abate by
Sep 18, 2015
Penalty
Initial $4,500 · Current $2,700 Reduced
29 CFR 1910.107(b)(6): Spray booth(s) having a frontal area larger than 9 square feet did not have metal deflectors or curtains not less than 2 1/2 inches deep installed at the upper outer edge of the booth over the opening:    a)  Paint Room, on or about 7/21/15:  Spray booth #5 and #7 were not provided with metal deflectors at the upper outer edge of the booth.    Abatement certification must be submitted for this item.
Recent events (2)
  • — I (S) $2700
  • — Z (S) $4500

1910.107 B10

Serious Gravity 5 1 instance 1 exposed
Issued
Aug 14, 2015
Abate by
Sep 18, 2015
Penalty
Initial $0 · Current $0
29 CFR 1910.107(b)(10): Transparent panels used for illumination of spray booth(s) did not effectively isolate the spraying area from the area in which the lighting unit(s) were located:  a)  Paint Room Booth #4, on or about 7/21/15:  The transparent panel at the ceiling of the booth was cracked.  Abatement certification must be submitted for this item.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.107 G02

Serious Gravity 5 1 instance 1 exposed
Issued
Aug 14, 2015
Abate by
Sep 18, 2015
Penalty
Initial $0 · Current $0
29 CFR 1910.107(g)(2): All spraying areas were not kept as free from the accumulation of deposits of combustible residues as practical, with cleaning conducted daily if necessary and scrapers spuds, or other tools used for cleaning purposes were not of the nonsparking material:  a)  Paint Room, Booth #4, on or about 7/21/15: Spray booth had a heavy accumulation of Sherwin Williams Polane sprayfil polyurethane coating on the sides walls of the booth and the putty knife used for cleaning was not of the nonsparking type.  Abatement certification must be submitted for this item.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.147 C06 I

Serious Gravity 1 1 instance 20 exposed
Issued
Aug 14, 2015
Abate by
Sep 18, 2015
Penalty
Initial $2,295 · Current $1,377 Reduced
29 CFR 1910.147(c)(6)(i): The employer did not conduct periodic inspections of the energy control procedures at least annually to ensure that the procedures and the requirement of this standard were being followed:    a)  At the establishment, on or about 7/21/15:  Periodic inspections were not conducted on the energy control procedures (lockout/tagout) to ensure that the procedures and requirements of the standard were being followed.  Employees perform servicing and/or maintenance on various equipment, including, but not limited to injection molding machines, lathes, mills, grinders, saws, etc.    Abatement certification must be submitted for this item.
Recent events (2)
  • — I (S) $1377
  • — Z (S) $2295

1910.157 G02

Other-than-serious Gravity 1 1 instance 25 exposed
Issued
Aug 14, 2015
Abate by
Sep 18, 2015
Penalty
Initial $2,295 · Current $0 Reduced
29 CFR 1910.157(g)(2): The educational program to familiarize employees with the general principles of fire extinguisher use and the hazards involved with incipient stage fire fighting was not provided to all employees upon initial employment, and at least annually thereafter:    a)  At the establishment, on or about 7/21/15:  Fire extinguisher training was not being conducted on an annual basis in that the last training conducted was on 6/5/12.    Abatement certification must be submitted for this item.
Recent events (2)
  • — I (O) $0
  • — Z (S) $2295

1910.212 A01

Serious Gravity 10 8 instances 5 exposed
Issued
Aug 14, 2015
Abate by
Sep 18, 2015
Penalty
Initial $6,300 · Current $3,780 Reduced
29 CFR 1910.212(a)(1): One or more methods of machine guarding was not provided to protect the operator and other employees in the machine area from hazards such as those created by point of operation, ingoing nip points, rotating parts, flying chips and sparks:    a)  Tool Room, on or about 7/21/15:  Unused portion of blade on a Johnson horizontal bandsaw, Serial #J13824, was not guarded on the right side.    b)  Tool Room, on or about 7/21/15:  Rotating chuck on a Speedmaster radial drill was not guarded.    c)  Tool Room, on or about 7/21/15:  Rotating chuck on an AL Supermill milling machine was not guarded.    d)  Tool Room, on or about 7/21/15:  Rotating chuck and collet on a Feeler EDM lathe #60 were not guarded.    e)  Tool Room, on or about 7/21/15:  Rotating chuck on a Jet drill press #12 was not guarded.    f)  Tool Room, on or about 7/21/15:  Rotating chuck and spindle on a Clausing drill press next to disconnect #8 were not guarded.    g)  Molding Dept., on or about 7/21/15:  Point of operation was not adequately guarded on a PD2L molding press in that the light curtains were not functioning.    h)  Mold Room C, on abou7/21/15:  Point of operation was not adequately guarded on an Engle C2 molding press in that the Plexiglas guard was broken.    Abatement documentation must be submitted for these items.
Recent events (2)
  • — I (S) $3780
  • — Z (S) $6300

1910.332 B01

Serious Gravity 5 1 instance 3 exposed
Issued
Aug 14, 2015
Abate by
Sep 18, 2015
Penalty
Initial $3,825 · Current $2,295 Reduced
29 CFR 1910.332(b)(1): Employees were not trained in and familiar with the safety-related work practices required by 1910.331 through 1910.335 that pertained to their respective job assignments:    a)  Throughout the facility, on or about 7/21/15:  Employees performing troubleshooting and repairs electrical equipment were not provided training in regards to safety related work practices and the use of appropriate personal protective equipment.    Abatement certification must be submitted for this item.
Recent events (2)
  • — I (S) $2295
  • — Z (S) $3825

1910.333 B02 I

Serious Gravity 5 1 instance 3 exposed
Issued
Aug 14, 2015
Abate by
Sep 18, 2015
Penalty
Initial $0 · Current $0
29 CFR 1910.333(b)(2)(i): The employer did not make a written copy of the procedures outlined in paragraph (b)(2) of 29 CFR 1910.333 available for inspection by employees and by the Assistant Secretary of Labor and his or her authorized representatives:   a)  Throughout the facility, on or about 7/21/15:  There was no written safety related work practice program in place to prevent electrical shock or other injuries to employees when working on electrical parts of machines or equipment.  Abatement certification must be submitted for this item.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.335 A01

Serious Gravity 5 1 instance 3 exposed
Issued
Aug 14, 2015
Abate by
Sep 18, 2015
Penalty
Initial $0 · Current $0
29 CFR 1910.335(a)(1): Employees working in areas where there were potential electrical hazards were not provided with, and/or did not use, electrical protective equipment that was appropriate for the specific parts of the body to be protected and for the work to be performed:  a)  Throughout the facility, on or about 7/21/15:  Employees performing troubleshooting and repairs on electrical equipment were not provided appropriate personal protective equipment for the work to be performed.  Abatement certification must be submitted for this item.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

View Oneida Molded Plastics,Llc's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 340789106.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.