Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: ALLEGHENY METAL FINISHING

Planned inspection · Health discipline

On , OSHA opened a planned health inspection of ALLEGHENY METAL FINISHING in 8150 STEUBENVILLE PIKE, IMPERIAL, PA 15126 (NAICS 332813). OSHA activity number 341073724.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Allegheny Metal Finishing — free Get an email when a new federal OSHA severe-injury report for Allegheny Metal Finishing is published. One employer, no account, unsubscribe in one click.
Site address
8150 STEUBENVILLE PIKE
City
IMPERIAL
State
PA
ZIP
15126
Mailing
8150 STEUBENVILLE PIKE, IMPERIAL, PA 15126
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Health
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
332813
Employees
8
Ownership type
A

6 citations on file for this inspection.

1910.107 B05 I

Serious Gravity 1 3 instances 1 exposed
Issued
Feb 5, 2016
Abate by
Mar 24, 2016
Penalty
Initial $1,200 · Current $900 Reduced
29 CFR 1910.107(b)(5)(i): Visible gauges or audible alarms or pressure activated devices were not installed to indicate or insure that the required air velocity is maintained:      a)  At the left spray booth, on or about November 20, 2015 - A visible gauge, audible alarm, or a pressure activated device was not installed on the spray booth to ensure that the required air velocity was maintained.  Employees spray with Polane T Polyurethane Enamel, Carbide Black, a flammable, when spraying product.  b) At the middle spray booth, on or about November 20, 2105 -  A visible gauge, audible alarm, or a pressure activated device was not installed on the spray booth to ensure that the required air velocity was maintained.  Employees spray with Polane T Polyurethane Enamel, Carbide Black, a flammable, when spraying product.    c)  At the right spray booth, on or about November 20, 2015 -  A visible gauge, audible alarm, or a pressure activated device was not installed on the spray booth to ensure that the required air velocity was maintained.  Employees spray with Polane T Polyurethane Enamel, Carbide Black, a flammable, when spraying product.
Recent events (2)
  • — I (S) $900
  • — Z (S) $1200

1910.107 B05 IV

Serious Gravity 1 3 instances 1 exposed
Issued
Feb 5, 2016
Abate by
Mar 24, 2016
Penalty
Initial $0 · Current $0
29 CFR 1910.107(b)(5)(iv): Space within the spray booth on the downstream and upstream sides of filters were not protected with approved automatic sprinklers:  a)  At the left spray booth, on or about November 20 2015 - The space within the spray booth on the downstream and upstream sides of the filters was not protected with approved automatic sprinklers.  Employees spray with Polane T Polyurethane Enamel, Carbide Black, a flammable, when spraying product.  b)  At the middle spray booth, on or about November 20 2015 - The space within the spray booth on the downstream and upstream sides of the filters was not protected with approved automatic sprinklers.  Employees spray with Polane T Polyurethane Enamel, Carbide Black, a flammable, when spraying product.  c)  At the right spray booth, on or about November 20 2015 - The space within the spray booth on the downstream and upstream sides of the filters was not protected with approved automatic sprinklers.  Employees spray with Polane T Polyurethane Enamel, Carbide Black, a flammable, when spraying product.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.107 B09

Serious Gravity 1 1 instance 1 exposed
Issued
Feb 5, 2016
Abate by
Feb 18, 2016
Penalty
Initial $1,200 · Current $900 Reduced
29 CFR 1910.107(b)(9): A clear space of not less than 3 feet on all sides was not kept free from storage or combustible construction:  a)  At the Left Spray Booth, on or about November 20, 2015 -   The spray booth did not have a clear space of not less than 3 feet on all sides from storage or combustible construction.  An employee stored combustible material immediately outside of the spray booth.
Recent events (2)
  • — I (S) $900
  • — Z (S) $1200

1910.1200 E01

Serious Gravity 1 1 instance 2 exposed
Issued
Feb 5, 2016
Abate by
Mar 3, 2016
Penalty
Initial $1,200 · Current $900 Reduced
29 CFR 1910.1200(e)(1): The employer did not develop, implement and maintain at the workplace, a written hazard communication program which at least describes how the criteria specified in paragraphs (f), (g) and (h) of this section for labels and other forms of warning, material safety data sheets, and employee information and training will be met:  a)  At the facility, on or about November 20, 2105 - A written hazard communication was not developed and implemented at the workplace.  Employees spray with Polane T Polyurethane Enamel, Carbide Black, a flammable, when spraying product.
Recent events (2)
  • — I (S) $900
  • — Z (S) $1200

1910.1200 H03 IV

Serious Gravity 1 1 instance 2 exposed
Issued
Feb 5, 2016
Abate by
Mar 3, 2016
Penalty
Initial $0 · Current $0
29 CFR 1910.1200(h)(3)(iv):   The details of the hazard communication program developed by the employer, did not include an explanation of the labels received on shipped containers and the workplace labeling system used by their employer; the safety data sheet, including the order of information and how employee could obtain and use the appropriate hazard information:  a)  At the facility, on or about November 20, 2015 - Employees were not provided with training on the safety data sheet format and the new element of the workplace labeling system.  Employees spray with Polane T Polyurethane Enamel, Carbide Black, a flammable, when spraying product.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.107 L04 III

Other-than-serious 1 instance 1 exposed
Issued
Feb 5, 2016
Abate by
Mar 3, 2016
Penalty
Initial $0 · Current $0
29 CFR 1910.107(l)(4)(iii): "No Smoking" signs were not posted at all powder coating areas and powder storage rooms in large letters on contrasting color background shall be conspicuously posted at all powder coating areas and powder storage rooms.  a)  At the left powder coating booth, on or about November 20, 2015 - The employer did not post "No Smoking" signs in the area of powder coating booth.  b) At the right powder coating booth, on or about November 20, 2015 - The employer did not post "No Smoking" signs in the area of powder coating booth.
Recent events (2)
  • — I (O) $0
  • — Z (O) $0

View Allegheny Metal Finishing's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 341073724.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.