CHICAGO, IL ·
OSHA Inspection: FREDDY'S JR REMODELING INCORPORATED
Planned inspection · Safety discipline
At a glance
On , OSHA opened a planned safety inspection of FREDDY'S JR REMODELING INCORPORATED in 2815 N. RICHMOND ST., CHICAGO, IL 60618 (NAICS 238170). OSHA activity number 341200491.
OSHA opens inspections for many reasons: routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- FREDDY'S JR REMODELING INCORPORATED
- Site address
- 2815 N. RICHMOND ST.
- City
- CHICAGO
- State
- IL
- ZIP
- 60618
- Mailing
- 1700 US HIGHWAY 34, OSWEGO, IL 60543
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238170
- Employees
- 6
- Ownership type
- A
Citations
7 citations on file for this inspection.
1903.19 C01
- Issued
- Mar 15, 2016
- Abate by
- Apr 15, 2016
- Penalty
- Initial $400 · Current $400
General-duty citation text
29 CFR 1903.19(c)(1): The employer did not certify to OSHA, within 10 calendar days after the abatement date, that the cited violation had been abated: Freddy's Jr. Remodeling Incorporated, failed to certify to OSHA within 10 calendar days after the abatement date that each of the following cited violations had been corrected: Citation Number Item Number Abatement Date 01 01 02/08/2016 01 03 02/08/2016 01 04 02/08/2016 01 05 02/08/2016 01 06 03/07/2016 In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
- · Z (O) $400
1926.100 A
- Issued
- Feb 2, 2016
- Abate by
- Feb 8, 2016
- Penalty
- Initial $1,600 · Current $1,600
General-duty citation text
29 CFR 1926.100(a): Employees were not protected by protective helmets while working in areas where there was a possible danger of head injury from impact, or from falling or flying objects, or from electrical shock and burns: a) Employees were not wearing protective helmets where there was a possible danger of head injury. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
- · Z (S) $1600
1926.300 B01
- Issued
- Feb 2, 2016
- Penalty
- Initial $1,600 · Current $1,600
General-duty citation text
29 CFR 1926.300(b)(1): Power operated tool(s), designed to accommodate guards, were not equipped with such guards when in use: a) Employees were using unguarded Ryobi AG4531G grinder during siding installation work. No abatement certification or documentation is required for this item.
Recent events (1)
- · Z (S) $1600
1926.416 A01
- Issued
- Feb 2, 2016
- Abate by
- Feb 8, 2016
- Penalty
- Initial $2,000 · Current $2,000
General-duty citation text
29 CFR 1926.416(a)(1): Employees were permitted to work in proximity to electric power circuits and were not protected against electric shock by de-energizing and grounding the circuits or effectively guarding the circuits by insulation or other means: a) Employees were not protected against accidental contact with energized overhead power lines during siding installation work. The overhead power lines consisted of secondary lines having a voltage rating of 120/240 volts. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
- · Z (S) $2000
1926.451 E01
- Issued
- Feb 2, 2016
- Abate by
- Feb 8, 2016
- Penalty
- Initial $2,000 · Current $2,000
General-duty citation text
29 CFR 1926.451(e)(1): Safe access was not provided to scaffold platforms when the platforms were more than 2 feet above or below the point of access: a) Employees were not provided with safe access to a ladder jack scaffold platform being used at an elevation of approximately 15 feet above the ground. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
- · Z (S) $2000
1926.451 G01 I
- Issued
- Feb 2, 2016
- Abate by
- Feb 8, 2016
- Penalty
- Initial $2,800 · Current $2,800
General-duty citation text
29 CFR 1926.451(g)(1)(i): Each employee on a boatswains' chair, catenary scaffold, float scaffold, needle beam scaffold, or ladder jack scaffold was not protected by a personal fall arrest system: a) Employees were exposed to the hazard of falling while working from ladder jack scaffold platform elevated approximately 15 feet above the ground. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (1)
- · Z (S) $2800
1926.454 A
- Issued
- Feb 2, 2016
- Abate by
- Mar 7, 2016
- Penalty
- Initial $2,000 · Current $2,000
General-duty citation text
29 CFR 1926.454(a): The employer did not have each employee who performed work while on a scaffold trained by a person qualified in the subject matter to recognize the hazards associated with the type of scaffold being used and to understand the procedures to control or minimize those hazards: a) Employer did not provide training to each employee in order to recognize hazards associated with working from ladder jack scaffolding and to understand procedures to control or minimize those hazards. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
- · Z (S) $2000
More inspections in this industry (NAICS 238170)
More inspections in IL
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 341200491.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.