OSHA Inspection: PASTRIMAS PAINT COMPANY

Referral inspection · Safety discipline

On , OSHA opened a referral safety inspection of PASTRIMAS PAINT COMPANY in 301 WEST BENSON STREET, READING, OH 45215 (NAICS 238320). OSHA activity number 341812907.

Watch Pastrimas Paint Company — free Get an email when a new federal OSHA severe-injury report for Pastrimas Paint Company is published. One employer, no account, unsubscribe in one click.
Site address
301 WEST BENSON STREET
City
READING
State
OH
ZIP
45215
Mailing
1185 GREENERY LANE, CINCINNATI, OH 45233
Inspection type
Referral (C)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238320
Employees
11
Ownership type
A

4 citations on file for this inspection.

1926.451 C02 I

Serious Gravity 10 1 instance 1 exposed
Issued
Abate by
Penalty
Initial $4988.00 · Current $2494.00 Reduced
29 CFR 1926.451(c)(2)(i): Footings shall be level, sound, rigid, and capable of supporting the loaded scaffold without settling or displacement.    On October 4, 2016, the footing for the Up-Right SL-20 mobile scaffold could not support the load of the scaffold.
Recent events (2)
  • — I (S) $2494
  • — Z (S) $4988

1926.451 F03

Serious Gravity 10 1 instance 1 exposed
Issued
Abate by
Penalty
Initial $4988.00 · Current $0.00 Reduced
29 CFR 1926.451(f)(3): Scaffolds and scaffold components shall be inspected for visible defects by a competent person before each work shift, and after any occurrence which could affect a scaffold's structural integrity.    On October 4, 2016, the Up-Right SL-20 scaffold was not inspected prior to the work shift to discover a screwdriver used as a retaining pin in a hinge.
Recent events (2)
  • — I (S) $0
  • — Z (S) $4988

1926.451 F04

Serious Gravity 10 1 instance 1 exposed
Issued
Abate by
Penalty
Initial $0.00 · Current $0.00
29 CFR 1926.451(f)(4): Any part of a scaffold damaged or weakened such that its strength is less than that required by paragraph (a) of this section shall be immediately repaired or replaced, braced to meet those provisions, or removed from service until repaired.    On October 4, 2016, the Up-Right SL-20 mobile scaffold was not removed from service as a screwdriver was used as a retaining pin for a hinge pin on the boom.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1926.451 F06

Deleted Serious Gravity 10 1 instance 2 exposed
Issued
Abate by
Penalty
Initial $4988.00 · Current $0.00 Reduced
29 CFR 1926.451(f)(6): The clearance between scaffolds and power lines shall be as follows: Scaffolds shall not be erected, used, dismantled, altered, or moved such that they or any conductive material handled on them might come closer to exposed and energized power lines than as follows:                       *Insulated Lines  _____________________________________________________________________                                                    Voltage          Minimum distance           Alternatives ____________________ ________________________ _______________________                                               Less than 300 volts.  3 feet (0.9 m)           300 volts to 50 kv.  10 feet (3.1 m)          More than 50 kv.....  10 feet (3.1 m) plus     2 times the length                       0.4 inches (1.0 cm)      of the line                       for each 1 kv over       insulator, but never                       50 kv.                   less than 10                                                feet (3.1 m). ____________________ ________________________ _______________________                         *Uninsulated lines _____________________________________________________________________                                                   Voltage           Minimum distance         Alternatives ____________________ ________________________ _______________________                                               Less than 50 kv.....  10 feet (3.1 m).         More than 50 kv.....  10 feet (3.1 m) plus     2 times the length of                       0.4 inches (1.0 cm)      the line insulator,                       for each 1 kv over       but never less than                       50 kv.                   10 feet (3.1 m). ____________________ ________________________ _______________________  Exception to paragraph (f)(6): Scaffolds and materials may be closer to power lines than specified above where such clearance is necessary for performance of work, and only after the utility company, or electrical system operator, has been notified of the need to work closer and the utility company, or electrical system operator, has deenergized the lines, relocated the lines, or installed protective coverings to prevent accidental contact with the lines.  On October 4, 2016, the Up-Right SL-20 scaffold was positioned less than ten feet from an electrical line with greater than 300 volts while an employee worked on the scaffold's platform.
Recent events (2)
  • — I (S) $0
  • — Z (S) $4988

View PASTRIMAS PAINT COMPANY's full OSHA safety record →