OSHA Inspection: LEAKTITE CORPORATION

Complaint inspection · Safety discipline

On , OSHA opened a complaint safety inspection of LEAKTITE CORPORATION in 40 FRANCIS ST, LEOMINSTER, MA 01453 (NAICS 326199). OSHA activity number 341867430.

Watch Leaktite Corporation — free Get an email when a new federal OSHA severe-injury report for Leaktite Corporation is published. One employer, no account, unsubscribe in one click.
Site address
40 FRANCIS ST
City
LEOMINSTER
State
MA
ZIP
01453
Mailing
40 FRANCIS ST, LEOMINSTER, MA 01453
Inspection type
Complaint (B)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
326199
Employees
125
Ownership type
A

5 citations on file for this inspection.

1910.147 C04 I

Serious Gravity 10 1 instance 1 exposed
Issued
Abate by
Penalty
Initial $11224.00 · Current $7857.00 Reduced
29 CFR 1910.147(c)(4)(i): Procedures were not developed, documented and utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section:     40 Francis St, Leominster, MA    On October 26, 2016 and at times prior, the employer did not develop and utilize a written energy control procedure to protect employees from air/pneumatic and electrical sources of energy when employees performed maintenance and servicing activities on the Gasket Installer Machine.
Recent events (2)
  • — I (S) $7857
  • — Z (S) $11224

1910.147 C06 I A

Other-than-serious 1 instance 1 exposed
Issued
Abate by
Penalty
Initial $0.00 · Current $0.00
29 CFR 1910.147(c)(6)(i)(A): The periodic inspection of the energy control procedure was not performed by an authorized employee other than the one utilizing the energy control procedure being inspected:     40 Francis St, Leominster, MA    On October 26, 2016 and at times prior, the employee who performed the periodic inspection of the energy control procedure was not an authorized employee.
Recent events (2)
  • — I (O) $0
  • — Z (S) $0

1910.178 A04

Serious Gravity 5 1 instance 10 exposed
Issued
Abate by
Penalty
Initial $8017.00 · Current $5612.00 Reduced
29 CFR 1910.178(a)(4): Modifications and additions which affect capacity and safe operation shall not be performed by the customer or user without manufacturers prior written approval. Capacity, operation, and maintenance instruction plates, tags, or decals shall be changed accordingly.    40 Francis St, Leominster, MA    On October 26, 2016 and at times prior, employees operated a powered industrial truck with two types of tine-mounted lifting attachments that reduced the truck's lifting capacity.   The employer did not have written approval of the manufacturer to use the two attachments.
Recent events (2)
  • — I (S) $5612
  • — Z (S) $8017

1910.178 A05

Serious Gravity 5 1 instance 10 exposed
Issued
Abate by
Penalty
Initial $0.00 · Current $0.00
29 CFR 1910.178(a)(5): The powered industrial truck was equipped with front-end attachments other than factory installed attachments, and the employer did not request that the truck be marked to identify the attachments and show the approximate weight of the truck and attachment combination at maximum elevation with load laterally centered:  40 Francis St, Leominster, MA  On October 26, 2016 and at times prior, employees operated a powered industrial truck with two types of tine-mounted lifting attachments that reduced their lifting capacities.   The non-factory installed attachments were not identified on the data plate of the powered industrial truck.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.1200 E01

Other-than-serious 1 instance 75 exposed
Issued
Abate by
Penalty
Initial $0.00 · Current $0.00
29 CFR 1910.1200(e)(1): The employer did not develop, implement, and/or maintain at the workplace a written hazard communication program which describes how the criteria specified in 29 CFR 1910.1200(f), (g), and (h) will be met:    40 Francis St, Leominster, MA  On October 26, 2016 and at times prior, the employer had not developed a written hazard communication program that described the employer processes for training, labeling, and safety data sheet accessibility.
Recent events (2)
  • — I (O) $0
  • — Z (O) $0

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 341867430.