OSHA Inspection: DEBONO BROTHERS BUILDERS & DEVELOPERS INC.

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of DEBONO BROTHERS BUILDERS & DEVELOPERS INC. in 53 BEACH STREET, NEW YORK, NY 10013 (NAICS 236220). OSHA activity number 342328101.

Watch Debono Brothers Builders & Developers INC. — free Get an email when a new federal OSHA severe-injury report for Debono Brothers Builders & Developers INC. is published. One employer, no account, unsubscribe in one click.
Site address
53 BEACH STREET
City
NEW YORK
State
NY
ZIP
10013
Mailing
3310 DELAVALL AVENUE, BRONX, NY 10475
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
236220
Employees
5
Ownership type
A

6 citations on file for this inspection.

1926.25 A

Serious Gravity 1 1 instance 4 exposed
Issued
Abate by
Penalty
Initial $2173.00 · Current $1660.00 Reduced
29 CFR 1926.25(a): During the course of construction, alteration, or repairs, form or scrap lumber with protruding nails was not kept clear from work areas:    a) On or about 5/9/2017, 6th Floor:  Sheets of plywood with protruding nails were present on the sixth floor.     Abatement certification is required for this item.
Recent events (3)
  • — C (S) $2173
  • — F (S) $1660
  • — Z (S) $2173

1926.1052 C01 II

Serious Gravity 5 1 instance 4 exposed
Issued
Abate by
Penalty
Initial $2897.00 · Current $1915.00 Reduced
29 CFR 1926.1052(c)(1)(ii): Stairways having four or more risers or rising more than 30 inches (76 cm), whichever is less, were not equipped with a stairrail system along each unprotected side or edge:    a) On or about 5/9/2017, 6th Floor:  The stairway to the 6th floor was not provided with a rail system on its open side.      b) On or about 5/9/2017, 7th Floor:  The stairway to the 7th floor was not provided with a midrail on its open side.       Abatement certification is required for this item.
Recent events (3)
  • — C (S) $2897
  • — F (S) $1915
  • — Z (S) $2897

1926.403 I02 I

Serious Gravity 5 1 instance 4 exposed
Issued
Abate by
Penalty
Initial $3622.00 · Current $2765.00 Reduced
29 CFR 1926.403(i)(2)(i): Live parts of electric equipment operating at 50 volts or more were not guarded against accidental contact by cabinets or other forms of enclosures, nor by any of the means listed in subparagraphs (A) through (D) of this paragraph:    a) On or about 5/9/2017, 6th Floor:  Employees were exposed to energized buss bars of two breaker boxes.     Abatement certification is required for this item.
Recent events (3)
  • — C (S) $3622
  • — F (S) $2765
  • — Z (S) $3622

1926.404 B01 I

Serious Gravity 5 1 instance 4 exposed
Issued
Abate by
Penalty
Initial $3622.00 · Current $0.00 Reduced
29 CFR 1926.404(b)(1)(i): Employer did not use either ground fault circuit interrupters as specified in paragraph (b)(1)(ii) of this section, or an assured equipment grounding conductor program as specified in paragraph (b)(1)(iii) of this section to protect employees on construction sites:    a) On or about 5/9/2017, 6th Floor:  Employees were utilizing electrical tools such as a chop saw and screw guns, which were powered through extension cords.  No GFCI's  were in use.      Abatement certification is required for this item.
Recent events (3)
  • — C (S) $3622
  • — F (S) $0
  • — Z (S) $3622

1926.404 F06

Serious Gravity 1 1 instance 4 exposed
Issued
Abate by
Penalty
Initial $2173.00 · Current $1660.00 Reduced
29 CFR 1926.404(b)(1)(i): Employer did not use either ground fault circuit interrupters as specified in paragraph (b)(1)(ii) of this section, or an assured equipment grounding conductor program as specified in paragraph (b)(1)(iii) of this section to protect employees on construction sites:    a) On or about 5/9/2017, 6th Floor:  Employees were utilizing a DeWalt chop saw without a continuous path to ground.      Abatement certification is required for this item.
Recent events (3)
  • — C (S) $2173
  • — F (S) $1660
  • — Z (S) $2173

1926.405 A02 II E

Serious Gravity 1 1 instance 4 exposed
Issued
Abate by
Penalty
Initial $2173.00 · Current $0.00 Reduced
29 CFR 1926.405(a)(2)(ii)(E): Lamps used in temporary wiring for general illumination were not protected from accidental contact or breakage:    a) On or about 5/9/2017, 6th and 7th floors:  Numerous light bulbs on strings of temporary lights were not provided with guards.    Abatement certification is required for this item.
Recent events (3)
  • — C (S) $2173
  • — F (S) $0
  • — Z (S) $2173

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 342328101.