CHICAGO, IL —
OSHA Inspection: DANIEL MOYA DBA DNE RESTORATION LLC
Planned inspection · Safety discipline
At a glance
On , OSHA opened a planned safety inspection of DANIEL MOYA DBA DNE RESTORATION LLC in 1228-1234 W. CARMEN AVE., CHICAGO, IL 60640 (NAICS 238140). OSHA activity number 342421112.
Where did this inspection happen?
- Establishment
- DANIEL MOYA DBA DNE RESTORATION LLC
- Site address
- 1228-1234 W. CARMEN AVE.
- City
- CHICAGO
- State
- IL
- ZIP
- 60640
- Mailing
- 1343 S. 58TH AVENUE, CICERO, IL 60804
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238140
- Employees
- 7
- Ownership type
- A
Citations
11 citations on file for this inspection.
1903.19 C01
- Issued
- Abate by
- Penalty
- Initial $311.00 · Current $311.00
General-duty citation text
29 CFR 1903.19(c)(1): The employer did not certify to OSHA, within 10 calendar days after the abatement date, that the cited violation had been abated: Daniel Moya dba DNE Restoration LLC., failed to certify to OSHA within 10 calendar days after the abatement date that each of the following cited violations had been corrected: Citation Number Item Number Abatement Date 01 01 01/25/2018 01 02a 12/27/2017 01 02b 12/27/2017 01 03a 12/27/2017 01 03b 12/27/2017 01 04 12/27/2017 01 05a 12/27/2017 01 05b 12/27/2017 01 05c 12/27/2017 02 01 12/27/2017 In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF THE CORRECTIVE ACTION WORKSHEET).
Recent events (1)
- — Z (O) $311
1926.20 B01
- Issued
- Abate by
- Penalty
- Initial $2716.00 · Current $2716.00
General-duty citation text
29 CFR 1926.20(b)(1): Program(s) were not initiated and/or maintained to comply with applicable safety and health provisions: a) On or about June 22, 2017, the employer did not maintain programs to provide for compliance with the OSH Act to control or minimize the safety and health hazards associated with masonry work that his employees are required to perform.
Recent events (1)
- — Z (S) $2716
1926.451 D03 VI
- Issued
- Abate by
- Penalty
- Initial $2716.00 · Current $2716.00
General-duty citation text
29 CFR 1926.451(d)(3)(vi): The outrigger beams which should be stabilized by bolts or other direct connections to the floor or roof deck were not secured by tiebacks: a) On June 22, 2017, the two point suspension scaffolding that the employer provided did not have the outrigger beams secured by tiebacks.
Recent events (1)
- — Z (S) $2716
1926.451 D04 I
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.451(d)(4)(i): Suspension scaffold outrigger beams were not provided with stop bolts or shackles at both ends: a) On June 22, 2017, on the west side of the building, the employer provided for employee use two point suspension scaffolding that was not equipped with a stop bolt or shackle at the end of the outrigger beams.
Recent events (1)
- — Z (S) $0
1926.451 D16
- Issued
- Abate by
- Penalty
- Initial $3803.00 · Current $3803.00
General-duty citation text
29 CFR 1926.451(d)(16): Suspension scaffold power-operated hoists or manually operated hoists did not have a braking device or locking pawl which engages automatically when a hoist makes either of the following uncontrolled movements: an instantaneous change in momentum or an accelerated over-speed: a) On June, 22, 2017, the employer provided for employee use on the east side of the building, a two-point suspension scaffold which did not have a braking device or locking pawl.
Recent events (1)
- — Z (S) $3803
1926.451 D17
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.451(d)(17): Manually operated hoists did not have a positive crank force to descend: a) On June 22, 2017, the employer provided for employee use on the east side of the building, a two-point suspension scaffold where the manually operated hoist did not have a positive crank force to descend.
Recent events (1)
- — Z (S) $0
1926.451 G01 II
- Issued
- Abate by
- Penalty
- Initial $3803.00 · Current $3803.00
General-duty citation text
29 CFR 1926.451(g)(1)(ii): Each employee on a single-point or two-point adjustable suspension scaffold was not protected by both a personal fall arrest system and a guardrail system: a) On June 22, 2017, the employer provided a, two-point suspension scaffolds for employee use where the employees were not protected by a personal fall arrest system.
Recent events (1)
- — Z (S) $3803
1926.451 G03 I
- Issued
- Abate by
- Penalty
- Initial $2716.00 · Current $2716.00
General-duty citation text
29 CFR 1926.451(g)(3)(i): Verical lifelines were not fastened to a fixed safe point of anchorage, independent of the scaffoldk, and protected from sharp edges and abrasion: a) On June 22, 2017, the employer provided for employee use vertical life lines for two, two-point suspension scaffolds that were not protected from abrasion when placed over the side/ edge of the roof to the scaffolding below.
Recent events (1)
- — Z (S) $2716
1926.451 G03 IV
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.451(g)(3)(iv): Vertical lifelines, independent support lines, and suspension ropes shall not be attached to each other, nor shall they be attached to or use the same point of anchorage, nor shall they be attached to the same point on the scaffold or personal fall arrest system: a) On June 22, 2017, the employer provided for employee use vertical lifelines for a two-point suspension scaffold located on the east side of the building that was attached to ropes being used as suspension scaffold tiebacks.
Recent events (1)
- — Z (S) $0
1926.451 G04 III
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.451(g)(4)(iii): Midrails, screens, mesh, intermediate vertical members, solid panels or equivalent structural members were not installed between the top edge of the guardrail system and the scaffold platform: a) On June 22, 2017, employees were performing masonry from a scaffold platform located on the east side of the building were there were no midrails or equivalent members were installed.
Recent events (1)
- — Z (S) $0
1926.451 D05 II
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.451(d)(5)(ii): Suspension scaffold support devices such as cornice hooks, roof hooks, roof irons, parapet clamps, or similar devices were not supported by bearing blocks: a) On June 22, 2017, employees were working from the east two point suspension scaffold where the right and left cornice hooks were not supported by bearing blocks.
Recent events (1)
- — Z (O) $0
More inspections in this industry (NAICS 238140)
RENO, NV—2026-07-16
DC MASONRY
WINNETKA, IL—2026-07-15
CHICAGO STUCCO CO.
LODI, NJ—2026-07-15
J & O MASONRY CONTRACTORS
DORAVILLE, GA—2026-07-14
SUDLOW CONCRETE, INC.
FLAGLER BEACH, FL—2026-07-14
PLANET DESIGN SERVICES, INC.
More inspections in IL
DEERFIELD, IL—2026-07-16
JOHN BURNS CONSTRUCTION COMPANY, LLC
BANNOCKBURN, IL—2026-07-16
BUILDER SERVICES GROUP, INC. DBA CJ INSULATION
BANNOCKBURN, IL—2026-07-16
ROOFING H.P. LLC
HIGHLAND PARK, IL—2026-07-16
UNITED PLUMBING AND DRAIN, INC.
FRANKLIN PARK, IL—2026-07-16
B & M PLASTIC INC.
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 342421112.