OSHA Inspection: HYDRITE CHEMICAL COMPANY

Referral inspection · Health discipline

On , OSHA opened a referral health inspection of HYDRITE CHEMICAL COMPANY in 191 W. 28TH AVE, OSHKOSH, WI 54902 (NAICS 424690). OSHA activity number 342440518.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Hydrite Chemical Company — free Get an email when a new federal OSHA severe-injury report for Hydrite Chemical Company is published. One employer, no account, unsubscribe in one click.
Site address
191 W. 28TH AVE
City
OSHKOSH
State
WI
ZIP
54902
Mailing
191 W. 28TH AVE, OSHKOSH, WI 54902
Inspection type
Referral (C)
Scope
Partial (B)
Discipline
Health
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
424690
Employees
75
Ownership type
A

3 citations on file for this inspection.

1910.119 D03 II

Deleted Serious Gravity 5 3 instances 12 exposed
Issued
Nov 21, 2017
Abate by
Dec 20, 2017
Penalty
Initial $8,465 · Current $0 Reduced
29 CFR 1910.119(d)(3)(ii): The employer shall document that equipment complies with recognized and generally accepted good engineering practices.  a) On or about July 3, 2017, the supply valve and the vacuum valve for the 3 Ton Container and 2 Cylinder Filling stations used a wrench to open, adjust and close each valve. Using wrenches does not provide a positive visual indication of the valve position since the wrenches can be placed on the valves in different positions. The supply valve and the vacuum valve for the 3 Ton Container and 2 Cylinder Filling stations are the same valves used for chlorine ton containers. Usage of ton container valves in a stationary piping system does not provide positive valve position indication and is not recommended by The Chlorine Institute March 2013 Pamphlet 6 Section 5.4.  b) On or about July 24, 2017, the following Chlorine Header instruments were not identified with tags or other means: TT-100, TE-101, PG-310, PIT-310 and PI-310A. Instrument identification is necessary to document instrument inspections as recommended by The Chlorine Institute May 2011 Pamphlet 17 Section 2.4.b.
Recent events (2)
  • — I (S) $0
  • — Z (S) $8465

1910.119 E06

Serious Gravity 5 1 instance 75 exposed
Issued
Nov 21, 2017
Penalty
Initial $8,465 · Current $5,079 Reduced
29 CFR 1910.119(e)(6): At least every five (5) years after the completion of the initial process hazard analysis, the process hazard analysis shall be updated and revalidated by a team meeting the requirements in paragraph (e)(4) of this section, to assure that the process hazard analysis is consistent with the current process.    a) On or about July 3, 2017, the last process hazard analysis for the Chlorine Cylinder Filling System was conducted on August 31, 2011.
Recent events (2)
  • — I (S) $5079
  • — Z (S) $8465

1910.119 F01 III B

Serious Gravity 5 1 instance 6 exposed
Issued
Nov 21, 2017
Abate by
Dec 20, 2017
Penalty
Initial $8,465 · Current $5,079 Reduced
29 CFR 1910.119(f)(1)(iii)(B): The employer shall develop and implement written operating procedures that provide clear instructions for safely conducting activities involved in each covered process consistent with the process safety information and shall address at least the following elements: Precautions necessary to prevent exposure, including engineering controls, administrative controls, and personal protective equipment.    a) Chlorine Railcar Unloading - Packaging Department Standard Operating Procedure Number P6011OS, used on July 3, 2017, did not indicate two chlorine rail cars are connected to the chlorine supply system that provides chlorine to the Chlorine Cylinder Filling Stations and Powell Bleach Plant.      b) Chlorine Railcar Unloading - Packaging Department Standard Operating Procedure Number P6011OS, used on July 3, 2017, did not include engineering or administrative controls to prevent one chlorine railcar charging the chlorine supply system before the other chlorine railcar hook-up procedures have been completed.
Recent events (2)
  • — I (S) $5079
  • — Z (S) $8465

View Hydrite Chemical Company's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 342440518.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.