OSHA Inspection: HAGERMAN CONSTRUCTION CORPORATION

Complaint inspection · Safety discipline

On , OSHA opened a complaint safety inspection of HAGERMAN CONSTRUCTION CORPORATION in 775 E. UPPER LEWISBURG- SALEM, BROOKVILLE, OH 45309 (NAICS 238140). OSHA activity number 342526357.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Hagerman Construction Corporation — free Get an email when a new federal OSHA severe-injury report for Hagerman Construction Corporation is published. One employer, no account, unsubscribe in one click.
Site address
775 E. UPPER LEWISBURG- SALEM
City
BROOKVILLE
State
OH
ZIP
45309
Mailing
10315 ALLISONVILLE ROAD, FISHERS, IN 46038
Inspection type
Complaint (B)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
A
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238140
Employees
11
Ownership type
A

4 citations on file for this inspection.

1926.451 F03

Deleted Serious Gravity 10 1 instance 5 exposed
Issued
Sep 18, 2017
Abate by
Oct 5, 2017
Penalty
Initial $11,408 · Current $0 Reduced
29 CFR 1926.451(f)(3): Scaffolds and scaffold components shall be inspected for visible defects by a competent person before each work shift, and after any occurrence which could affect a scaffold's structural integrity.  On July 24, 2017, at 775 E. Upper Lewisburg-Salem Road, Brookville, a fire station under construction, an inspection conducted by a competent person after an incident where one side of the Premier Pro Series Power Unit Mast climber dropped about 16-32 inches was inadequate in that the inspection did not detect damaged, bent cylinder hook and cylinder hook pin on the mast climber.
Recent events (2)
  • — I (S) $0
  • — Z (S) $11408

1926.451 F04

Other-than-serious 1 instance 5 exposed
Issued
Sep 18, 2017
Abate by
Oct 20, 2017
Penalty
Initial $0 · Current $0
29 CFR 1926.451(f)(4): Any part of a scaffold damaged or weakened such that its strength is less than that required by paragraph (a) of this section shall be immediately repaired or replaced, braced to meet those provisions, or removed from service until repaired.    On July 24, 2017, around 11:15 am at 775 E. Upper Lewisburg-Salem Road, Brookville, a fire station under construction, while operators lowered a Premier Pro Series Power Unit Model 724 mast climber, one side of the mast climber dropped 16-32 inches, the safety hooks and latches were bent and damaged and the mast climber was kept in operation and was not removed from service until the end of the following day.
Recent events (2)
  • — I (O) $0
  • — Z (S) $0

1926.451 F07

Deleted Serious Gravity 5 1 instance 5 exposed
Issued
Sep 18, 2017
Abate by
Oct 5, 2017
Penalty
Initial $8,149 · Current $0 Reduced
29 CFR 1926.451(f)(7): Scaffolds shall be erected, moved, dismantled, or altered only under the supervision and direction of a competent person qualified in scaffold erection, moving, dismantling or alteration. Such activities shall be performed only by experienced and trained employees selected for such work by the competent person.  On July 24, 2017, at 775 E. Upper Lewisburg-Salem Road, Brookville, a fire station under construction, a Premier Pro Series Power Unit Mast Climber was being lowered from approximately 20 ft. to the ground without the direction and supervision of a competent person and during the lowering one side of the mast climber got caught on a metal window frame, raised up and then one side dropped approximately 16-32 inches, damaging, bent cylinder hooks.
Recent events (2)
  • — I (S) $0
  • — Z (S) $8149

1926.454 B02

Other-than-serious 1 instance 5 exposed
Issued
Sep 18, 2017
Abate by
Oct 5, 2017
Penalty
Initial $9,778 · Current $9,778
29 CFR 1926.454(b)(2): The correct procedures for erecting, disassembling, moving, operating, repairing, inspecting, and maintaining the type of scaffold in question;    The employer had not ensured the adequacy of scaffold training received by employees operating the Premier Pro Series Power Unit Model 724 mast climber from other sources when on July 24, 2017 during the lowering of the Premier Pro Series Power Unit Model 724 mast climber when one side of the work platform dropped between approximately 16-32 inches, causing damage to the hooks and safety latches.
Recent events (2)
  • — I (O) $9778
  • — Z (S) $9778

View Hagerman Construction Corporation's full OSHA safety record →