HARTLY, DE —
OSHA Inspection: SWARTZENTRUBER SAWMILL COMPANY
Planned inspection · Health discipline
At a glance
On , OSHA opened a planned health inspection of SWARTZENTRUBER SAWMILL COMPANY in 1191 PEARSONS CORNER ROAD, HARTLY, DE 19953 (NAICS 321113). OSHA activity number 342626983.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- SWARTZENTRUBER SAWMILL COMPANY
- Site address
- 1191 PEARSONS CORNER ROAD
- City
- HARTLY
- State
- DE
- ZIP
- 19953
- Mailing
- 1191 PEARSONS CORNER ROAD, HARTLY, DE 19953
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Partial (B)
- Discipline
- Health
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 321113
- Employees
- 8
- Ownership type
- A
Citations
7 citations on file for this inspection.
1910.95 D01
- Issued
- Feb 9, 2018
- Abate by
- Mar 30, 2018
- Penalty
- Initial $2,772 · Current $1,663 Reduced
8111
General-duty citation text
29 CFR 1910.95(d)(1): When information indicated that any employee's exposure equaled or exceed the 8-hour time-weighted average of 85 decibels (dBAs), the employer did not develop and implement a monitoring program: (a) Sawmill Saw Cutting Areas - On or about September 15, 2017, the employer did not develop a noise monitoring program for employees exposed to levels of noise exceeding 85 dBAs. Pursuant to 29 CFR 1903.19, the employer must submit abatement certification, required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $1663.2
- — Z (S) $2772
1910.95 G01
- Issued
- Feb 9, 2018
- Abate by
- Mar 30, 2018
- Penalty
- Initial $0 · Current $0
8111
General-duty citation text
29 CFR 1910.95(g)(1): The employer did not establish and maintain an audiometric testing program as provided by 29 CFR 1910.95(g) by making audiometric testing available to all employees whose exposures equal or exceed an 8-hour time-weighted average of 85 decibels: (a) Sawmill Saw Cutting Areas - On or about September 15, 2017, the employer failed to establish an audiometric testing program for employees exposed to levels of noise exceeding 85 dBAs. Pursuant to 29 CFR 1903.19, the employer must submit abatement certification, required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $0
- — Z (S) $0
1910.95 K01
- Issued
- Feb 9, 2018
- Abate by
- Mar 30, 2018
- Penalty
- Initial $0 · Current $0
8111
General-duty citation text
29 CFR 1910.95(k)(1): The employer did not train each employee who is exposed to noise at or above an 8-hour time-weighted average of 85 decibels in accordance with the requirements of 29 CFR 1910.95(k). The employer did not institute a training program and ensure employee participation in the program: (a) Sawmill Saw Cutting Areas - On or about September 15, 2017, the employer did not train employees having noise exposures at levels exceeding 85 dBAs. Pursuant to 29 CFR 1903.19, the employer must submit abatement certification, required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $0
- — Z (S) $0
1910.132 A
- Issued
- Feb 9, 2018
- Abate by
- Feb 21, 2018
- Penalty
- Initial $3,326 · Current $1,996 Reduced
General-duty citation text
29 CFR 1910.132(a): Protective equipment was not used when necessary whenever hazards capable of causing injury and impairment were encountered: (a) Log Cutting Areas - On or about September 15, 2017, the employer failed to provide leg protection to employee(s) who operate a STIHL MS660 chain saw for cutting logs and lumber to various lengths, exposing employees to a laceration hazard. Pursuant to 29 CFR 1903.19, the employer must submit abatement certification, required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $1995.6
- — Z (S) $3326
1910.265 C20 VI
- Issued
- Feb 9, 2018
- Abate by
- Mar 16, 2018
- Penalty
- Initial $2,772 · Current $1,663 Reduced
E101M110
General-duty citation text
29 CFR 1910.265(c)(20)(vi): Provisions were not made for daily removal of refuse: (a) Sawmill Saw Cutting Areas - On or about September 15, 2017, the employer failed to clean this area of significant accumulations of combustible wood dust from surfaces including the overhead beams, floors, wood cutting machinery, and electrical equipment, exposing employees to a fire hazard. Pursuant to 29 CFR 1903.19, the employer must submit abatement certification, required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $1663.2
- — Z (S) $2772
1910.1200 E01
- Issued
- Feb 9, 2018
- Abate by
- Mar 30, 2018
- Penalty
- Initial $2,772 · Current $1,109 Reduced
General-duty citation text
29 CFR 1910.1200(e)(1): The employer had not developed or implemented a written hazard communication program to include the requirements outlined in 29 CFR 1910.1200(e)(1)(i) and (e)(1)(ii): (a) Swartzentruber Sawmill Company - On or about September 8, 2017, the employer failed to develop or implement a written hazard communication program to communicate and train employees on the hazards associated with working with combustible wood refuse. Pursuant to 29 CFR 1903.19, the employer must submit abatement certification, required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
- — I (O) $1108.8
- — Z (S) $2772
1910.1200 H03
- Issued
- Feb 9, 2018
- Abate by
- Mar 30, 2018
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.1200(h)(3): The employee training did not include the requirements of 29 CFR 1910.1200(h)(3)(i) through (h)(3)(iv): (a) Swartzentruber Sawmill Company - On or about September 8, 2017, the employer failed to train employees on the hazards associated with working with combustible wood refuse. Pursuant to 29 CFR 1903.19, the employer must submit abatement certification, required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
- — I (O) $0
- — Z (S) $0
More inspections at Swartzentruber Sawmill Company
View Swartzentruber Sawmill Company's full OSHA safety record →
More inspections in this industry (NAICS 321113)
More inspections in DE
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 342626983.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.