Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: RED WELL CONSTRUCTION

Referral inspection · Safety discipline

On , OSHA opened a referral safety inspection of RED WELL CONSTRUCTION in 324 HARVEST FIELD LANE, YORK, PA 17403 (NAICS 238160). OSHA activity number 342685922.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch RED Well Construction — free Get an email when a new federal OSHA severe-injury report for RED Well Construction is published. One employer, no account, unsubscribe in one click.
Site address
324 HARVEST FIELD LANE
City
YORK
State
PA
ZIP
17403
Mailing
148 MAPLE DRIVE, NEW HOLLAND, PA 17557
Inspection type
Referral (C)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238160
Employees
3
Ownership type
A

6 citations on file for this inspection.

1926.100 A

Deleted Serious Gravity 1 1 instance 1 exposed
Issued
Nov 9, 2017
Abate by
Dec 7, 2017
Penalty
Initial $1,630 · Current $0 Reduced
29 CFR 1926.100(a): Employees were not protected by protective helmets while working in areas where there was a possible danger of head injury from impact, or from falling or flying objects, or from electrical shock and burns:    a)  Roof - An employee was observed without head protection while operating a pneumatic nail gun to secure shingles to the roof of a 3-story townhome and was exposed to ricochet nails, on or about October 4, 2017.    Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (S) $0
  • — Z (S) $1630

1926.102 A01

Other-than-serious 1 instance 1 exposed
Issued
Nov 9, 2017
Abate by
Dec 7, 2017
Penalty
Initial $1,630 · Current $1,100 Reduced
1926.102(a)(1): Employees were not provided with eye and face protection equipment when machines or operations presented potential eye or face injury from physical, chemical, or radiation agents:    a)  Roof - An employee was observed without eye protection while operating a pneumatic nail gun to secure shingles to the roof of a 3-story townhome and was exposed to ricochet nails, on or about October 4, 2017.    Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (O) $1100
  • — Z (S) $1630

1926.451 G01

Serious Gravity 5 1 instance 1 exposed
Issued
Nov 9, 2017
Penalty
Initial $2,716 · Current $2,100 Reduced
29 CFR 1926.451(g)(1)(i): Each employee on a boatswains' chair, catenary scaffold, float scaffold, needle beam scaffold, or ladder jack scaffold were not protected by a personal fall arrest system:    a) Ladder Jack Scaffold - An employee worked from a ladder jack scaffold platform while not wearing a personal fall arrest system and was exposed to an approximate 23 foot fall hazard to the ground below, on or about October 4, 2017.    No abatement certification or documentation required.
Recent events (2)
  • — I (S) $2100
  • — Z (S) $2716

1926.452 K01

Serious Gravity 5 1 instance 1 exposed
Issued
Nov 9, 2017
Penalty
Initial $2,716 · Current $2,100 Reduced
29 CFR 1926.452(k)(1): Ladder jack scaffold platforms exceeded a height of 20 feet:    a) Ladder Jack Scaffold - An employee worked from a ladder jack scaffold platform which measured approximately 23 feet above ground, on or about October 4, 2017.    No abatement certification or documentation required.
Recent events (2)
  • — I (S) $2100
  • — Z (S) $2716

1926.501 B13

Serious Gravity 10 1 instance 3 exposed
Issued
Nov 9, 2017
Abate by
Dec 7, 2017
Penalty
Initial $3,803 · Current $2,400 Reduced
29 CFR 1926.501(b)(13): Each employee(s) engaged in residential construction activities 6 feet (1.8 m) or more above lower levels were not protected by guardrail systems, safety net system, or personal fall arrest system, nor were employee(s) provided with an alternative fall protection measure under another provision of paragraph 1926.501 (b):     a) Roof - Employees were observed conducting residential roofing operations on steep roofs and were not protected from an approximate 26 foot fall hazard to the ground below, on or about October 4, 2017.    Abatement certification and documentation required within 10 days after abatement date.  The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement.  Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (2)
  • — I (S) $2400
  • — Z (S) $3803

1926.1053 B01

Serious Gravity 5 1 instance 3 exposed
Issued
Nov 9, 2017
Penalty
Initial $2,716 · Current $2,100 Reduced
29 CFR 1926.1053(b)(1): Where portable ladders were used for access to an upper landing surface and the ladder's length allows, the ladder side rails did not extend at least 3 feet (.9 m) above the upper landing surface being accessed:    a) East Side of Townhome - Employees used a portable extension ladder to access and egress the roof of the building, and the side rails did not extend at least 3 feet above the landing surface, on or about October 4, 2017.    Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (S) $2100
  • — Z (S) $2716

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 342685922.