LEBANON, PA —
OSHA Inspection: MURRY'S INCORPORATED
Planned inspection · Safety discipline
At a glance
On , OSHA opened a planned safety inspection of MURRY'S INCORPORATED in 1501 WILLOW STREET, LEBANON, PA 17042 (NAICS 311412). OSHA activity number 342751948.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- MURRY'S INCORPORATED
- Site address
- 1501 WILLOW STREET
- City
- LEBANON
- State
- PA
- ZIP
- 17042
- Mailing
- 1501 WILLOW STREET, LEBANON, PA 17042
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 311412
- Employees
- 175
- Ownership type
- A
Citations
7 citations on file for this inspection.
1910.119 D03 II
- Issued
- Apr 26, 2018
- Abate by
- May 31, 2018
- Penalty
- Initial $8,315 · Current $0 Reduced
General-duty citation text
29 CFR 1910.119(d)(3)(ii): The employer did not document that equipment complies with recognized and generally accepted good engineering practices. (a) 1501 Willow Street, Lebanon Pennsylvania, West Unit - The employer did not ensure that the all piping on Compressor #8 met the labeling requirements that comply with recognized and generally accepted good engineering practices, on or about November 3, 2017. (b) 1501 Willow Street, Lebanon Pennsylvania, West Unit - The employer did not ensure that all the piping on the Pump Package met the labeling requirements that comply with the recognized and generally accepted good engineering practices, on or about November 3, 2017. (c) 1501 Willow Street, Lebanon Pennsylvania, West Unit - Employees working in the west engine room were not provided an inside emergency shower as required by recognized and generally accepted good engineering practices, on or about November 3, 2017. (d) 1501 Willow Street, Lebanon Pennsylvania, West Unit - Employees working in the west engine room were not provided an outside emergency eye wash and shower within the required distance, that meet the requirements of recognized and generally accepted good engineering practices, on or about November 3, 2017. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (3)
- — F (S) $0
- — C (S) $8315
- — Z (S) $8315
1910.119 E05
- Issued
- Apr 26, 2018
- Abate by
- May 31, 2018
- Penalty
- Initial $4,989 · Current $0 Reduced
General-duty citation text
29 CFR 1910.119(e)(5): The employer did not establish a system to promptly address the team's findings and recommendations; assure that the recommendations were resolved in a timely manner and that the resolution was documented; document what actions were to be taken; complete actions as soon as possible; develop a written schedule of when these actions were to be completed; communicate the actions to operating, maintenance and other employees whose work assignments were in the process and who may have been affected by the recommendations or actions: (a) 1501 Willow Street, Lebanon Pennsylvania, West Unit - The employer did not resolve the finding of the PHA in a timely manner, on or about November 3, 2017. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (3)
- — F (S) $0
- — C (S) $4989
- — Z (S) $4989
1910.119 O04
- Issued
- Apr 26, 2018
- Abate by
- May 31, 2018
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.119(o)(4): The employer did not promptly determine and document an appropriate response to each of the findings of the compliance audit, and document that deficiencies had been corrected: (a) 1501 Willow Street, Lebanon Pennsylvania, West Unit - The employer did not document that the deficiencies found during the last compliance audit had been corrected, on or about November 3, 2017. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (3)
- — F (S) $0
- — C (S) $0
- — Z (S) $0
1910.119 J02
- Issued
- Apr 26, 2018
- Abate by
- May 31, 2018
- Penalty
- Initial $8,315 · Current $5,000 Reduced
General-duty citation text
29 CFR 1910.119(j)(2): The employer did not establish or implement written procedures to maintain the on-going integrity of process equipment: (a) 1501 Willow Street, Lebanon Pennsylvania, West Unit - The employer did not establish procedures in sufficient detail to provided inspectors instruction on how to conduct inspections and tests of insulated equipment such as piping, to assure their mechanical integrity, on or about November 3, 2017. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (3)
- — F (S) $5000
- — C (S) $8315
- — Z (S) $8315
1910.119 J03
- Issued
- Apr 26, 2018
- Abate by
- May 31, 2018
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.119(j)(3): The employer did not train each employee involved in maintaining the on-going integrity of process equipment in an overview of that process and its hazards and in the procedures applicable to the employee's job tasks to assure that the employee can perform the job tasks in a safe manner. (a) 1501 Willow Street, Lebanon Pennsylvania - An employee performing inspections of the ammonia system was not provided with training in the procedures applicable to the employee's job task, on or about November 3, 2017. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (3)
- — F (S) $0
- — C (S) $0
- — Z (S) $0
1910.119 J04 IV
- Issued
- Apr 26, 2018
- Abate by
- May 31, 2018
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.119(j)(4)(iv): The employer did not document each inspection and test that had been performed on process equipment. (a) 1501 Willow Street, Lebanon Pennsylvania, West Unit - The employer did not document each inspection and test that had been performed on process equipment, on or about November 3, 2017. Abatement Note: The documentation shall identify the date of the inspection or test, the name of the person who performed the inspection or test, the serial number or other identifier of the equipment on which the inspection or test was performed, a description of the inspection or test performed, and the results of the inspection or test. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (3)
- — F (S) $0
- — C (S) $0
- — Z (S) $0
1910.119 O01
- Issued
- Apr 26, 2018
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.119(o)(1): The employer did not certify that they have evaluated compliance with the provisions of this section at least every three years: (a) 1501 Willow Street, Lebanon Pennsylvania - The employer did not conduct a compliance audit at least once very 3 years as required by the standard, on or about November 3, 2017. No abatement certification or documentation required.
Recent events (3)
- — F (O) $0
- — C (O) $0
- — Z (O) $0
More inspections at Murry'S Incorporated
View Murry'S Incorporated's full OSHA safety record →
More inspections in this industry (NAICS 311412)
More inspections in PA
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 342751948.