OSHA Inspection: METROMONT CORPORATION

Federal Agency inspection · Health discipline

On , OSHA opened a federal Agency health inspection of METROMONT CORPORATION in 4151 US HWY 17 S, BARTOW, FL 33830 (NAICS 327390). OSHA activity number 342766623.

Watch Metromont Corporation — free Get an email when a new federal OSHA severe-injury report for Metromont Corporation is published. One employer, no account, unsubscribe in one click.
Site address
4151 US HWY 17 S
City
BARTOW
State
FL
ZIP
33830
Mailing
4151 US HWY 17 S, BARTOW, FL 33830
Inspection type
Federal Agency (M)
Scope
Complete (A)
Discipline
Health
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
327390
Employees
172
Ownership type
A

7 citations on file for this inspection.

5(a)(1)

Serious Gravity 10 3 instances 1 exposed
Issued
May 9, 2018
Abate by
Jun 5, 2018
Penalty
Initial $12,934 · Current $8,000 Reduced
OSH ACT of 1970 Section (5)(a)(1): The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to the hazard(s) of being struck-by or crushed-by:     a) At the Double Tee Bed, employees were exposed to struck-by and crushed-by hazards while moving steel cable reels, on or about  Novener 10, 2017.
Recent events (3)
  • — R (S) $8000
  • — C (S) $12934
  • — Z (S) $12934

1910.23 B08

Deleted Serious Gravity 5 2 instances 2 exposed
Issued
May 9, 2018
Abate by
Jun 26, 2018
Penalty
Initial $8,130 · Current $0 Reduced
29 CFR 1910.23(b)(8): The employer did not ensure ladders were used only for the purposes for which they were designed:  a) At the East side yard area of the establishment, employees were using a crane, MI-Jack Products, Model: MJ 70, Travelift, SN: 1902PD, that had original cabin ladders replaced by a  portable aluminum 20 foot Werner ladder and 12 foot portable fiberglass Werner ladders, on or about January 10, 2018.  b) At the South East side yard area of the company, employees were using a crane, MI-Jack Products, Model: MJ 50, Travelift, SN: 1819P, that had the original cabin ladder replaced by a 9 foot portable aluminum unmarked ladder, on or about January 10, 2018.
Recent events (3)
  • — R (S) $0
  • — C (S) $8130
  • — Z (S) $8130

1910.151 C

Other-than-serious 1 instance 9 exposed
Issued
May 9, 2018
Abate by
Jun 26, 2018
Penalty
Initial $6,097 · Current $4,000 Reduced
29 CFR 1910.151(c): Where employees were exposed to injurious corrosive materials, suitable facilities for quick drenching or flushing of the eyes and body were not provided within the work area for immediate emergency use:    a) At the Double Tee Bed and Batch Plant, employees were working with Portland Cement without an eyewash station, on or about January 10, 2018.
Recent events (3)
  • — R (O) $4000
  • — C (S) $6097
  • — Z (S) $6097

1910.38 C02

Deleted Other-than-serious 1 instance 20 exposed
Issued
May 9, 2018
Abate by
Jun 26, 2018
Penalty
Initial $0 · Current $0
29 CFR 1910.38(c)(2): Procedures for emergency evacuation, including type of evacuation and exit route assignments were not implemented by the employer:  a) At the establishment, the emergency action plan did not establish the exit route assignments, on or about January 10, 2018.
Recent events (3)
  • — R (O) $0
  • — C (O) $0
  • — Z (O) $0

1910.38 C03

Deleted Other-than-serious 1 instance 20 exposed
Issued
May 9, 2018
Abate by
Jun 26, 2018
Penalty
Initial $0 · Current $0
29 CFR 1910.38(c)(3): The  emergency action plan did not include the procedures to be followed by employees who remain to operate critical plant operations before they evacuate:  a) At the establishment, the emergency action plan allowed employees to stay behind to care for essential plant operations but procedures to be followed were not established, on or about January 10, 2018.
Recent events (3)
  • — R (O) $0
  • — C (O) $0
  • — Z (O) $0

1910.38 C04

Other-than-serious 1 instance 20 exposed
Issued
May 9, 2018
Abate by
Jun 26, 2018
Penalty
Initial $0 · Current $0
29 CFR 1910.38(c)(4): The employer did not establish procedures to account for all employees after an evacuation:  a) At the establishment, the emergency action plan established that each supervisor will make a head count of their employees, but did not establish procedures on how to account for all employees, on or about January 10, 2018.
Recent events (3)
  • — R (O) $0
  • — C (O) $0
  • — Z (O) $0

1910.333 A01

Deleted Other-than-serious 1 instance 2 exposed
Issued
May 9, 2018
Abate by
Jun 26, 2018
Penalty
Initial $0 · Current $0
29 CFR 1910.333(a)(1): The employer failed to ensure that live parts were de-energized before employees began to work on or near live parts:  a) At the Double Tee Bed building, personnel authorized to repair/maintain the flying "bullet" bucket were exposed to an electrical hazard, in that, in Step 3 of the company's  LO/TO Procedure there was no specific step on how to test if it had been de-energized, on or about January 10, 2018.
Recent events (3)
  • — R (O) $0
  • — C (O) $0
  • — Z (O) $0

View Metromont Corporation's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 342766623.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.