OSHA Inspection: THE A.G. MAURO COMPANY OF FLORIDA, INC.

Complaint inspection · Health discipline

On , OSHA opened a complaint health inspection of THE A.G. MAURO COMPANY OF FLORIDA, INC. in 1105 SAND POND ROAD, LAKE MARY, FL 32746 (NAICS 332321). OSHA activity number 342916590.

What this inspection record means

OSHA opens inspections for many reasons: routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch The A.G. Mauro Company of Florida, INC. for free Get an email when a new federal OSHA severe-injury report for The A.G. Mauro Company of Florida, INC. is published. One employer, no account, unsubscribe in one click.
Site address
1105 SAND POND ROAD
City
LAKE MARY
State
FL
ZIP
32746
Mailing
1105 SAND POND ROAD, LAKE MARY, FL 32746
Inspection type
Complaint (B)
Scope
Partial (B)
Discipline
Health
Advance notice
No
Union status
Non-union (B)
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
332321
Employees
30
Ownership type
Private (A)

11 citations on file for this inspection.

1910.95 C01

Serious Gravity 5 1 instance 2 exposed
Issued
May 1, 2018
Abate by
Jun 4, 2018
Penalty
Initial $6,467 · Current $3,880 Reduced
29 CFR 1910.95(c)(1): The employer did not administer a continuing, effective hearing conservation program as described in 29 CFR 1910.9(c) through (o) whenever employee noise exposures equal or exceed an 8-hour time-weighted average sound level of 85 decibels measured on the A scale, or equivalently a dose of fifty percent:  a) For a grinder who was exposed to continuous noise at 96.6% of the permissible daily exposure limit (8-hour time weighted average sound level of 85 dBA) or an equivalent sound level of approximately 89.75 dBA during the 432 minute monitoring period, on February 21, 2018.
Recent events (2)
  • · I (S) $3880.2
  • · Z (S) $6467

1910.212 A03 II

Serious Gravity 5 1 instance 6 exposed
Issued
May 1, 2018
Abate by
May 11, 2018
Penalty
Initial $7,760 · Current $4,656 Reduced
29 CFR 1910.212(a)(3)(ii): Point(s) of operation of machinery were not guarded to prevent employee(s) from having any part of their body in the danger zone(s) during operating cycle(s):  a) Welding Area - A DeWalt 20 inch sliding metal saw was not guarded along the periphery of the blade, on or about January 31, 2018.
Recent events (2)
  • · I (S) $4656
  • · Z (S) $7760

1910.252 B02 III

Serious Gravity 1 1 instance 2 exposed
Issued
May 1, 2018
Abate by
May 11, 2018
Penalty
Initial $3,880 · Current $2,328 Reduced
29 CFR 1910.252(b)(2)(iii): Workers and other persons adjacent to the welding area were not protected from the rays by noncombustible or flameproof screens or shields:  a) Welding Area - Welding screens were not provided around the 4 welding stations where there was welding being performed, on or about February 21, 2018.
Recent events (2)
  • · I (S) $2328
  • · Z (S) $3880

1910.252 B03

Serious Gravity 5 1 instance 4 exposed
Issued
May 1, 2018
Abate by
May 11, 2018
Penalty
Initial $6,467 · Current $3,880 Reduced
29 CFR 1910.252(b)(3): Employees exposed to the hazards created by welding, cutting, or brazing operations were not protected by personal protective equipment in accordance with the requirements of 29 CFR 1910.132:  a) Welding Area - Employees welding were only wearing 1 arm sleeve and glove, on or about February 21, 2018.
Recent events (2)
  • · I (S) $3880.2
  • · Z (S) $6467

1910.132 A

Serious Gravity 5 1 instance 2 exposed
Issued
May 1, 2018
Abate by
May 11, 2018
Penalty
Initial $0 · Current $0
29 CFR 1910.132(a): Protective equipment was not used when necessary whenever hazards capable of causing injury and impairment were encountered:   a) Grinding Area - Employees grinding with portable grinders were not wearing arm sleeves, on or about February 21, 2018.
Recent events (2)
  • · I (S) $0
  • · Z (S) $0

1910.107 D02

Other-than-serious 1 instance 2 exposed
Issued
May 1, 2018
Abate by
May 25, 2018
Penalty
Initial $0 · Current $0
29 CFR 1910.107(d)(2): All spraying areas were not provided with mechanical ventilation adequate to remove flammable vapors, mists, or powders to a safe location and to confine and control combustible residues so that life is not endangered:  a) Spraying Area - The roof fan used to remove paint vapors was not operational and the wall fan was not providing adequate vapor removal, on or about February 21, 2018.
Recent events (2)
  • · I (O) $0
  • · Z (O) $0

1910.134 C01

Other-than-serious 1 instance 6 exposed
Issued
May 1, 2018
Abate by
Jun 18, 2018
Penalty
Initial $0 · Current $0
29 CFR 1910.134(c)(1): A written respiratory protection program that included the provisions in 29 CFR 1910.134(c)(1)(i) - (ix) with worksite specific procedures was not established and implemented for required respirator use:  a) Shop- There was no written program, on or about January 31, 2018.
Recent events (2)
  • · I (O) $0
  • · Z (O) $0

1910.134 E01

Other-than-serious 1 instance 6 exposed
Issued
May 1, 2018
Abate by
Jun 18, 2018
Penalty
Initial $0 · Current $0
29 CFR 1910.134(e)(1): The employer did not provide a medical evaluation to determine the employee's ability to use a respirator, before the employee was fit tested or required to use the respirator in the workplace:  a) Shop- There were no medical evaluations conducted, on or about January 31, 2018.
Recent events (2)
  • · I (O) $0
  • · Z (O) $0

1910.134 F01

Other-than-serious 1 instance 6 exposed
Issued
May 1, 2018
Abate by
Jun 18, 2018
Penalty
Initial $0 · Current $0
29 CFR 1910.134(f)(1): The employer did not ensure that employee(s) required to use a tight-fitting facepiece respirator passed the appropriate qualitative fit test (QLFT) or quantitative fit test (QNFT):  a) Shop- There were no fit tests conducted, on or about January 31, 2018.
Recent events (2)
  • · I (O) $0
  • · Z (O) $0

1910.134 K03

Other-than-serious 1 instance 6 exposed
Issued
May 1, 2018
Abate by
Jun 18, 2018
Penalty
Initial $0 · Current $0
29 CFR 1910.134(k)(3): Training was not provided prior to requiring employees to use a respirator in the workplace:  a) Shop- There was no training conducted prior to the use of the respirators, on or about January 31, 2018.
Recent events (2)
  • · I (O) $0
  • · Z (O) $0

1910.252 C06 II

Other-than-serious 1 instance 4 exposed
Issued
May 1, 2018
Abate by
May 25, 2018
Penalty
Initial $0 · Current $0
29 CFR 1910.252(c)(6)(ii): Indoors, welding or cutting involving zinc-bearing base or filler metals coated with zinc-bearing materials was not done in accordance with 29 CFR 1910.252(c)(3):  (a) Welding Area - Ganvaneal steel, which contained zinc, was welded on and local exhaust hoods were not used to collect the fumes, on or about February 21, 2018.
Recent events (2)
  • · I (O) $0
  • · Z (O) $0

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). OSHA publishes its own view of this case as inspection number 342916590.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.