OSHA Inspection: ECS MANAGEMENT, LLC

Referral inspection · Safety discipline

On , OSHA opened a referral safety inspection of ECS MANAGEMENT, LLC in 6034 ATLANTA HWY., FLOWERY BRANCH, GA 30542 (NAICS 238110). OSHA activity number 342962297.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch ECS Management, LLC — free Get an email when a new federal OSHA severe-injury report for ECS Management, LLC is published. One employer, no account, unsubscribe in one click.
Establishment
ECS MANAGEMENT, LLC
Site address
6034 ATLANTA HWY.
City
FLOWERY BRANCH
State
GA
ZIP
30542
Mailing
6034 ATLANTA HWY., FLOWERY BRANCH, GA 30542
Inspection type
Referral (C)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238110
Employees
6
Ownership type
A

5 citations on file for this inspection.

1926.651 C02

Serious Gravity 10 1 instance 5 exposed
Issued
Apr 12, 2018
Abate by
May 8, 2018
Penalty
Initial $3,880 · Current $2,499 Reduced
29 CFR 1926.651(c)(2): A stairway, ladder, ramp or other safe means of egress was not located in trench excavations that were 4 feet (1.22m) or more in depth so as to require no more than 25 feet (7.62m) of lateral travel for employees:    a) Site - On or about 02/21/18 and at times prior thereto employees working inside the 9.0 ft. deep excavation did not have a ladder for safe egress.    In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
  • — I (S) $2499
  • — Z (S) $3880

1926.651 J02

Serious Gravity 10 1 instance 5 exposed
Issued
Apr 12, 2018
Abate by
May 8, 2018
Penalty
Initial $3,880 · Current $2,499 Reduced
29 CFR 1926.651(j)(2): Protection was not provided by placing and keeping excavated or other materials or equipment at least 2 feet (.61m) from the edge of excavations, or by the use of retaining devices that were sufficient to prevent materials or equipment from falling or rolling into excavations, or by a combination of both if necessary:    a) Site - On or about 02/21/18 and at times prior thereto employees worked inside the 9.0 ft. deep excavation and the spoil pile of excavated material was not kept at least two feet away from the edge of the excavation.     In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
  • — I (S) $2499
  • — Z (S) $3880

1926.651 K01

Serious Gravity 10 1 instance 5 exposed
Issued
Apr 12, 2018
Abate by
May 8, 2018
Penalty
Initial $3,880 · Current $2,499 Reduced
29 CFR 1926.651(k)(1): An inspection of the excavations, the adjacent areas, and protective systems was not conducted by the competent person prior to the start of work and as needed throughout the shift:    a) Site -  On or about 02/21/18 and at times prior thereto daily inspections of excavations, the adjacent areas, and protective systems were not made by a competent person for evidence of a situation that could have resulted in possible cave-ins (rain water), indications of failure of protective systems, hazardous atmospheres, or other hazardous conditions.     In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
  • — I (S) $2499
  • — Z (S) $3880

1926.651 H01

Serious Gravity 10 1 instance 5 exposed
Issued
Apr 12, 2018
Abate by
May 8, 2018
Penalty
Initial $0 · Current $0
29 CFR 1926.651(h)(1): Employees were working in excavations in which there was accumulated water, or excavations in which water was accumulating, and adequate precautions had not been taken to protect employees against the hazards posed by water accumulation:  a) Site - On 02/21/18 employees were removing concrete forms inside a 9.0 ft. deep excavation in which there was accumulated rain water, and no precautions were taken.     In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1926.652 A01

Serious Gravity 10 1 instance 5 exposed
Issued
Apr 12, 2018
Abate by
May 8, 2018
Penalty
Initial $3,880 · Current $2,499 Reduced
29 CFR 1926.652(a)(1): Each employee in an excavation was not protected from cave-ins by an adequate protective system designed in accordance with 29 CFR 1926.652 (b) or (c):    a) Site - On or about 02/21/18 and at times prior thereto  employees performing concrete work inside a 9.0 ft. deep excavation (cut with vertical walls) were not protected from cave-ins by an adequate protective system.    In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
  • — I (S) $2499
  • — Z (S) $3880

View ECS Management, LLC's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 342962297.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.