OSHA Inspection: GONZALEZ CONCRETE CONSTRUCTION, LLC

Referral inspection · Health discipline

On , OSHA opened a referral health inspection of GONZALEZ CONCRETE CONSTRUCTION, LLC in 2029 OGILBY ROAD, ROCKFORD, IL 61102 (NAICS 238110). OSHA activity number 342967304.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Gonzalez Concrete Construction, LLC — free Get an email when a new federal OSHA severe-injury report for Gonzalez Concrete Construction, LLC is published. One employer, no account, unsubscribe in one click.
Site address
2029 OGILBY ROAD
City
ROCKFORD
State
IL
ZIP
61102
Mailing
2029 OGILBY ROAD, ROCKFORD, IL 61102
Inspection type
Referral (C)
Scope
Partial (B)
Discipline
Health
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238110
Employees
11
Ownership type
A

5 citations on file for this inspection.

1903.19 D01

Other-than-serious 4 instances 9 exposed
Issued
Nov 28, 2018
Abate by
Dec 19, 2018
Penalty
Initial $415 · Current $415
29 CFR 1903.19(d)(1): The employer did not submit to the Agency documents demonstrating that abatement is complete for each willful or repeat violation and for any serious violation for which the Agency indicates in the citation that such abatement documentation is required.   The employer failed to submit documentation of abatement within 10 days of the abatement date for Citation 1 Items 1a, 1b, 2a and 2b.
Recent events (1)
  • — Z (O) $415

1926.55 B

Serious Gravity 10 1 instance 9 exposed
Issued
Jun 20, 2018
Abate by
Jul 19, 2018
Penalty
Initial $5,174 · Current $3,363 Reduced

Hazardous substances C730

29 CFR 1926.55(b): Feasible administrative or engineering controls were not implemented to reduce employee exposure(s):    On or about February 22, 2018 employees were exposed to carbon monoxide levels that exceeded the 8 hour time weighted average of 50.0ppm.  Employees were using gas powered equipment to transport and smooth wet concrete and LP heaters to heat area to prevent the wet concrete from freezing.    a.  An employee  engaged in concrete pouring activities  on February 22, 2018 was exposed to carbon monoxide as an 8 hour time weighted average of 96.3ppm, approximately 1.8 times the permissible exposure limit of 50.0ppm; this limit was established to prevent adverse health effects.   The exposure level was derived from carboxyhemoglobin back calculation.  Employee exposure time was estimated to be 212 minutes, the remaining 268 minutes was calculated as zero (0) exposure time.    b.An employee  engaged in concrete pouring activities  on February 22, 2018 was exposed to carbon monoxide as an 8 hour time weighted average of 75.9 ppm, approximately 1.2 times the permissible exposure limit of 50.0ppm; this limit was established to prevent adverse health effects.   The exposure level was derived from carboxyhemoglobin back calculation.  Employee exposure time was estimated to be 212 minutes, the remaining 268 minutes was calculated as zero (0) exposure time.    c.  An employee  engaged in concrete pouring activities  on February 22, 2018 was exposed to carbon monoxide as an 8 hour time weighted average of 106.5 ppm, approximately 2.1 times the permissible exposure limit of 50.0ppm; this limit was established to prevent adverse health effects.   The exposure level was derived from carboxyhemoglobin back calculation.  Employee exposure time was estimated to be 212 minutes, the remaining 268 minutes was calculated as zero (0) exposure time.    d.  An employee  engaged in concrete pouring activities  on February 22, 2018 was exposed to carbon monoxide as an 8 hour time weighted average of 103.8 ppm, approximately 2.0 times the permissible exposure limit of 50.0ppm; this limit was established to prevent adverse health effects.   The exposure level was derived from carboxyhemoglobin back calculation.  Employee exposure time was estimated to be 212 minutes, the remaining 268 minutes was calculated as zero (0) exposure time.    e.  An employee  engaged in concrete pouring activities  on February 22, 2018 was exposed to carbon monoxide as an 8 hour time weighted average of 100.1 ppm, approximately 2.0 times the permissible exposure limit of 50.0ppm; this limit was established to prevent adverse health effects.   The exposure level was derived from carboxyhemoglobin back calculation.  Employee exposure time was estimated to be 212 minutes, the remaining 268 minutes was calculated as zero (0) exposure time.    f. An employee  engaged in concrete pouring activities  on February 22, 2018 was exposed to carbon monoxide as an 8 hour time weighted average of 94.1 ppm, approximately 1.9 times the permissible exposure limit of 50.0ppm; this limit was established to prevent adverse health effects.   The exposure level was derived from carboxyhemoglobin back calculation.  Employee exposure time was estimated to be 212 minutes, the remaining 268 minutes was calculated as zero (0) exposure time.    g.  An employee  engaged in concrete pouring activities  on February 22, 2018 was exposed to carbon monoxide as an 8 hour time weighted average of 136.3ppm, approximately 2.7 times the permissible exposure limit of 50.0ppm; this limit was established to prevent adverse health effects.   The exposure level was derived from carboxyhemoglobin back calculation.  Employee exposure time was estimated to be 212 minutes, the remaining 268 minutes was calculated as zero (0) exposure time.
Recent events (2)
  • — I (S) $3362.5
  • — Z (S) $5174

1926.154 A01

Serious Gravity 10 1 instance 9 exposed
Issued
Jun 20, 2018
Abate by
Jul 19, 2018
Penalty
Initial $0 · Current $0

Hazardous substances C730

29 CFR 1926.154(a)(1): Fresh air was not supplied in sufficient quantities to maintain the health and safety of workmen  On or about February 22, 2018 at 500 E. Leffler Street in Dodgeville WI. Employees were using gas powered equipment to transport and smooth wet concrete and LP heaters to heat area to prevent the wet concrete from freezing in a partially enclosed building.  Employees were exposed to carbon monoxide levels that exceeded the 8 hour time weighted average of 50.0ppm.   a.  An employee  engaged in concrete pouring activities  on February 22, 2018 was exposed to carbon monoxide as an 8 hour time weighted average of 96.3ppm, approximately 1.8 times the permissible exposure limit of 50.0ppm; this limit was established to prevent adverse health effects.   The exposure level was derived from carboxyhemoglobin back calculation.  Employee exposure time was estimated to be 212 minutes, the remaining 268 minutes was calculated as zero (0) exposure time.  b.An employee  engaged in concrete pouring activities  on February 22, 2018 was exposed to carbon monoxide as an 8 hour time weighted average of 75.9 ppm, approximately 1.2 times the permissible exposure limit of 50.0ppm; this limit was established to prevent adverse health effects.   The exposure level was derived from carboxyhemoglobin back calculation.  Employee exposure time was estimated to be 212 minutes, the remaining 268 minutes was calculated as zero (0) exposure time.  c.  An employee  engaged in concrete pouring activities  on February 22, 2018 was exposed to carbon monoxide as an 8 hour time weighted average of 106.5 ppm, approximately 2.1 times the permissible exposure limit of 50.0ppm; this limit was established to prevent adverse health effects.   The exposure level was derived from carboxyhemoglobin back calculation.  Employee exposure time was estimated to be 212 minutes, the remaining 268 minutes was calculated as zero (0) exposure time.  d.  An employee  engaged in concrete pouring activities  on February 22, 2018 was exposed to carbon monoxide as an 8 hour time weighted average of 103.8 ppm, approximately 2.0 times the permissible exposure limit of 50.0ppm; this limit was established to prevent adverse health effects.   The exposure level was derived from carboxyhemoglobin back calculation.  Employee exposure time was estimated to be 212 minutes, the remaining 268 minutes was calculated as zero (0) exposure time.  e.  An employee  engaged in concrete pouring activities  on February 22, 2018 was exposed to carbon monoxide as an 8 hour time weighted average of 100.1 ppm, approximately 2.0 times the permissible exposure limit of 50.0ppm; this limit was established to prevent adverse health effects.   The exposure level was derived from carboxyhemoglobin back calculation.  Employee exposure time was estimated to be 212 minutes, the remaining 268 minutes was calculated as zero (0) exposure time.  f. An employee  engaged in concrete pouring activities  on February 22, 2018 was exposed to carbon monoxide as an 8 hour time weighted average of 94.1 ppm, approximately 1.9 times the permissible exposure limit of 50.0ppm; this limit was established to prevent adverse health effects.   The exposure level was derived from carboxyhemoglobin back calculation.  Employee exposure time was estimated to be 212 minutes, the remaining 268 minutes was calculated as zero (0) exposure time.  g.  An employee  engaged in concrete pouring activities  on February 22, 2018 was exposed to carbon monoxide as an 8 hour time weighted average of 136.3ppm, approximately 2.7 times the permissible exposure limit of 50.0ppm; this limit was established to prevent adverse health effects.   The exposure level was derived from carboxyhemoglobin back calculation.  Employee exposure time was estimated to be 212 minutes, the remaining 268 minutes was calculated as zero (0) exposure time.     (LOCATION) (IDENTIFY SPECIFIC OPERATION(S) AND/OR CONDITION(S)) (DESCRIBE HAZARD(S) WHERE NECESSARY)
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.1200 E01

Serious Gravity 10 1 instance 9 exposed
Issued
Jun 20, 2018
Abate by
Jul 30, 2018
Penalty
Initial $5,174 · Current $3,363 Reduced

Hazardous substances C730

29 CFR 1910.1200(e)(1): Employer had not developed or implemented a written hazard communication program which at included the requirements outlined in 29 CFR 1910.1200(e)(1)(i) and (e)(1)(ii):     On or about February 22, 2018, a writing hazard communication program was not developed or implemented to convey the occupational health hazards of carbon monoxide and other chemicals to employees pouring and forming concrete.
Recent events (2)
  • — I (S) $3362.5
  • — Z (S) $5174

1910.1200 H03 I

Serious Gravity 10 1 instance 9 exposed
Issued
Jun 20, 2018
Abate by
Jul 30, 2018
Penalty
Initial $0 · Current $0

Hazardous substances C730

29 CFR 1910.1200(h)(3)(i): The employee training did not include the methods and observations used to detect the presence or release of a hazardous chemical in the work area:     On or about February 22, 2018, employees were not trained on methods to observe to detect the presence carbon monoxide in the workplace.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 342967304.