COLUMBUS, OH —
OSHA Inspection: COCHRAN ELECTRIC, INC
Referral inspection · Safety discipline
At a glance
On , OSHA opened a referral safety inspection of COCHRAN ELECTRIC, INC in 845 KADERLY DRIVE, COLUMBUS, OH 43228 (NAICS 238210). OSHA activity number 343099495.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- COCHRAN ELECTRIC, INC
- Site address
- 845 KADERLY DRIVE
- City
- COLUMBUS
- State
- OH
- ZIP
- 43228
- Mailing
- 90 GRACE DRIVE, POWELL, OH 43065
What kind of inspection was it?
- Inspection type
- Referral (C)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- A
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238210
- Employees
- 16
- Ownership type
- A
Citations
6 citations on file for this inspection.
1910.335 A01 I
- Issued
- Jul 17, 2018
- Abate by
- Jul 6, 2019
- Penalty
- Initial $5,174 · Current $5,000 Reduced
General-duty citation text
29 CFR 1910.335(a)(1)(i): Employees working in areas where there are potential electrical hazards shall be provided with, and shall use, electrical protective equipment that is appropriate for the specific parts of the body to be protected and for the work to be performed. Note: Personal protective equipment requirements are contained in subpart I of this part. a. On or about April 14, 2018, the employer did not ensure that employees were utilizing electrical protective equipment while verifying switchboards LVDP, MDP3 and MDP4 were deenergized, thereby exposing employees to arc flash/shock hazards.
Recent events (3)
- — F (O) $5000
- — C (S) $5174
- — Z (S) $5174
1910.137 C02 VIII
- Issued
- Jul 17, 2018
- Abate by
- Aug 6, 2018
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.137(c)(2)(viii): Electrical protective equipment shall be subjected to periodic electrical tests. Test voltages and the maximum intervals between tests shall be in accordance with Table I-4 and Table I-5. a. On or about April 14, 2018, the employer did not ensure that electrical protective gloves were tested on a semi-annual basis, thereby exposing employees to arc flash/shock hazards.
Recent events (3)
- — F (S) $0
- — C (S) $0
- — Z (S) $0
1910.333 A01
- Issued
- Jul 17, 2018
- Penalty
- Initial $5,174 · Current $5,000 Reduced
General-duty citation text
29 CFR 1910.333(a)(1): "Deenergized parts." Live parts to which an employee may be exposed shall be deenergized before the employee works on or near them, unless the employer can demonstrate that deenergizing introduces additional or increased hazards or is infeasible due to equipment design or operational limitations. Live parts that operate at less than 50 volts to ground need not be deenergized if there will be no increased exposure to electrical burns or to explosion due to electric arcs. a. On or about April 14, 2018, located in the indoor substation, employees were performing preventative maintenance activities inside the primary side of the 13,200 VAC Square D switchboard, MDP-2, without deenergizing live parts, thereby exposing employees to arc flash/shock hazards.
Recent events (3)
- — F (O) $5000
- — C (S) $5174
- — Z (S) $5174
1910.333 B02 II A
- Issued
- Jul 17, 2018
- Abate by
- Jul 6, 2019
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.333(b)(2)(ii)(A): Safe procedures for deenergizing circuits and equipment shall be determined before circuits or equipment are deenergized. a. On or about April 14, 2018, located in the substations, employees were performing preventative maintenance inside five electrical distribution switchboards, 120-13,200 VAC. The employer did not ensure that energy control procedures were developed and utilized to ensure that 1910.333(a)-(c) work practices were employed, such as, but not limited to, reviewing electrical circuits, determining electrical personal protective equipment requirements, procedures for verification of de-energized parts, use and application of grounding equipment, and application of lockout devices by exposed employees.
Recent events (3)
- — F (O) $0
- — C (S) $0
- — Z (S) $0
1910.333 B02 III A
- Issued
- Jul 17, 2018
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.333(b)(2)(iii)(A): A lock and a tag shall be placed on each disconnecting means used to deenergize circuits and equipment on which work is to be performed, except as provided in paragraphs (b)(2)(iii)(C) and (b)(2)(iii)(E) of this section. The lock shall be attached so as to prevent persons from operating the disconnecting means unless they resort to undue force or the use of tools. a. On or about April 14, 2018, employees were performing preventative maintenance inside five electrical distribution switchboards, 120-13,200 VAC. The employer did not ensure employees had control over the electrical energy sources. There were employees who did not place a lock on the group lockout box. The lockout box did not contain the only key(s) for the locks used.
Recent events (3)
- — F (O) $0
- — C (S) $0
- — Z (S) $0
1910.333 B02 IV B
- Issued
- Jul 17, 2018
- Penalty
- Initial $5,174 · Current $0 Reduced
General-duty citation text
29 CFR 1910.333(b)(2)(iv)(B): A qualified person shall use test equipment to test the circuit elements and electrical parts of equipment to which employees will be exposed and shall verify that the circuit elements and equipment parts are deenergized. The test shall also determine if any energized condition exists as a result of inadvertently induced voltage or unrelated voltage backfeed even though specific parts of the circuit have been deenergized and presumed to be safe. If the circuit to be tested is over 600 volts, nominal, the test equipment shall be checked for proper operation immediately after this test. a. On or about April 14, 2018, the employer did not ensure that electrical testing equipment was used to verify the deenergized state of the 13,200 VAC primary feed of the MDP-2 switchboard, thereby exposing employees to arc flash/shock hazards.
Recent events (3)
- — F (O) $0
- — C (S) $5174
- — Z (S) $5174
More inspections at Cochran Electric, INC
View Cochran Electric, INC's full OSHA safety record →
More inspections in this industry (NAICS 238210)
More inspections in OH
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 343099495.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.