Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: CONCRETE PRECAST PRODUCTS, INC.

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of CONCRETE PRECAST PRODUCTS, INC. in 2033 NE 27TH AVE., GAINESVILLE, FL 32609 (NAICS 238110). OSHA activity number 343293429.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Concrete Precast Products, INC. — free Get an email when a new federal OSHA severe-injury report for Concrete Precast Products, INC. is published. One employer, no account, unsubscribe in one click.
Site address
2033 NE 27TH AVE.
City
GAINESVILLE
State
FL
ZIP
32609
Mailing
2033 NE 27TH AVE, GAINESVILLE, FL 32609
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238110
Employees
18
Ownership type
A

5 citations on file for this inspection.

5(a)(1)

Serious Gravity 10 1 instance 3 exposed
Issued
Aug 10, 2018
Abate by
Sep 6, 2018
Penalty
Initial $5,174 · Current $3,104 Reduced
OSH ACT of 1970 Section (5)(a)(1): The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees were exposed to crushing hazards:  a. On or about July 12,2018, throughout yard area, employees operating forklifts were not wearing seatbelts, exposing themselves to crushing hazards.  Among feasible means of abatement include but not limited to:  1.  Utilizing seatbelts in accordance with ASME/ANSI B56.1-2012, paragraphs 5.3.19 and 7.41.  2. Creating and enforcing a forklift safety program which ensures protective devices are used.
Recent events (2)
  • — I (S) $3104.4
  • — Z (S) $5174

1910.147 C01

Serious Gravity 10 1 instance 10 exposed
Issued
Aug 10, 2018
Abate by
Sep 6, 2018
Penalty
Initial $5,174 · Current $3,104 Reduced
29 CFR 1910.147(c)(1): The employer shall establish a program consisting of energy control procedures, employee training and periodic inspections to ensure that before any employee performs any servicing or maintenance on a machine or equipment where the unexpected energizing, startup or release of stored energy could occur and cause injury, the machine or equipment shall be isolated from the energy source and rendered inoperative:  a. On or about July 12, 2018, the employer's energy control program did not consist of energy control procedures for the concrete mixers.
Recent events (2)
  • — I (S) $3104.4
  • — Z (S) $5174

1910.147 C06 I

Serious Gravity 10 1 instance 10 exposed
Issued
Aug 10, 2018
Abate by
Sep 6, 2018
Penalty
Initial $0 · Current $0
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed:  a. On or about July 12, 2018, the employer had not conducted a periodic inspection of the energy control procedures since 2011.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.147 C07 I

Serious Gravity 10 1 instance 10 exposed
Issued
Aug 10, 2018
Abate by
Sep 6, 2018
Penalty
Initial $0 · Current $0
29 CFR 1910.147(c)(7)(i): The employer did not provide training to ensure that the purpose and function of the energy control program are understood by employees and that the knowledge and skills required for the safe application, usage, and removal of the energy controls are acquired by employees:  a. On or about July 12, 2018, all employees performing maintenance and repairs were not trained in the recognition of hazardous energy sources.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.178 L01 II

Other-than-serious 1 instance 10 exposed
Issued
Aug 10, 2018
Abate by
Sep 6, 2018
Penalty
Initial $0 · Current $0
29 CFR 1910.178(l)(1)(ii): The employer did not ensure that each operator had successfully completed the training required by paragraph (l), except as permitted by paragraph (l)(5), prior to permitting an employee to operate a forklift:  a. On or about July 12, 2018, the employer did not ensure that ell employees operating forklifts had been certified.
Recent events (2)
  • — I (O) $0
  • — Z (O) $0

View Concrete Precast Products, INC.'s full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 343293429.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.