OSHA Inspection: CHEMTRADE SOLUTIONS LLC

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of CHEMTRADE SOLUTIONS LLC in 1421 WILLIS AVENUE, SYRACUSE, NY 13204 (NAICS 325188). OSHA activity number 343315842.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Chemtrade Solutions LLC — free Get an email when a new federal OSHA severe-injury report for Chemtrade Solutions LLC is published. One employer, no account, unsubscribe in one click.
Site address
1421 WILLIS AVENUE
City
SYRACUSE
State
NY
ZIP
13204
Mailing
1421 WILLIS AVENUE, SYRACUSE, NY 13204
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
A
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
325188
Employees
34
Ownership type
A

6 citations on file for this inspection.

1910.119 D03 II

Serious Gravity 5 2 instances 6 exposed
Issued
Jan 10, 2019
Abate by
Apr 30, 2019
Penalty
Initial $7,391 · Current $5,543 Reduced
29 CFR 1910.119(d)(3)(ii): The employer did not document that equipment complies with recognized and generally accepted good engineering practices.   a) Throughout the covered process, on or about 7/18/18: The employer did not ensure that equipment complied with recognized and generally accepted good engineering practices such as but not limited to ASME/ANSI A13.1 in that pipes containing anhydrous ammonia were not labeled in a manner that clearly identified their contents and flow direction.      b) On the North and South Vaporizers, on or about 7/18/18: Rupture disks used for pressure relief were set at a pressure exceeding the maximum pressure design of the vaporizers. The employer did not ensure that equipment complied with recognized and generally accepted good engineering practices such as, but not limited to ASME VIII. ASME VIII (2010) section UG-134 paragraph a states" When a single pressure relief device is used, the set pressure marked on the device shall not exceed the maximum allowable working pressure of the vessel".  Abatement certification must be submitted for this item.
Recent events (3)
  • — J (S) $5543.25
  • — C (S) $7391
  • — Z (S) $7391

1910.119 J02

Serious Gravity 5 1 instance 34 exposed
Issued
Jan 10, 2019
Abate by
Feb 14, 2019
Penalty
Initial $7,391 · Current $5,543 Reduced
29 CFR 1910.119(j)(2): The employer did not establish written procedures to maintain the on-going integrity of process equipment.     a) Throughout the covered process, on or about 7/18/18: The employer did not establish written procedures for process equipment including ammonia sensors, level sensors for ammonia storage tanks, pressure sensors for ammonia storage tanks, and steam line pressure sensors.      Abatement certification must be submitted for this item.
Recent events (3)
  • — J (S) $5543.25
  • — C (S) $7391
  • — Z (S) $7391

1910.119 J04 I

Serious Gravity 5 1 instance 34 exposed
Issued
Jan 10, 2019
Abate by
Oct 31, 2019
Penalty
Initial $0 · Current $0
29 CFR 1910.119(j)(4)(i): The employer did not perform inspection and tests on process equipment   a) Throughout the covered process, on or about 7/18/18: The employer did not perform inspection and tests for process equipment including ammonia sensors, level sensors for ammonia storage tanks, pressure sensors for ammonia storage tanks, and steam line pressure sensors.       Abatement certification must be submitted for this item.
Recent events (3)
  • — J (S) $0
  • — C (S) $0
  • — Z (S) $0

1910.119 J05

Serious Gravity 5 1 instance 34 exposed
Issued
Jan 10, 2019
Abate by
Oct 31, 2019
Penalty
Initial $0 · Current $0
29 CFR 1910.119(j)(5): The employer did not correct deficiencies in equipment that were outside acceptable limits (defined by the process safety information on paragraph (d) of this section) before use.   a) On the South Separator, on or about 7/18/18: Where a previous inspection showed that thickness of the west head was below the minimum allowable value for the piece of equipment, the employer did not take corrective action or take the piece of equipment out of service.      Abatement certification must be submitted for this item.
Recent events (3)
  • — J (S) $0
  • — C (S) $0
  • — Z (S) $0

1910.119 N

Other-than-serious Gravity 5 1 instance 6 exposed
Issued
Jan 10, 2019
Abate by
Feb 14, 2019
Penalty
Initial $7,391 · Current $0 Reduced
29 CFR 1910.119(n): The employer did not establish an emergency plan for the entire plant in accordance with the provisions of 29 CFR 1910.38. In addition the emergency action plan did not include procedures for handling small releases:    a) At the facility, on or about 7/18/18: The employers emergency action plan did not contain procedures for responding to and handling small releases.     Abatement certification must be submitted for this item.
Recent events (3)
  • — J (O) $0
  • — C (S) $7391
  • — Z (S) $7391

1910.119 D03 I B

Deleted Other-than-serious 1 instance 34 exposed
Issued
Jan 10, 2019
Abate by
Feb 14, 2019
Penalty
Initial $0 · Current $0
29 CFR 1910.119(d)(3)(i)(B): The employer did not develop piping and instrument diagrams for the equipment that was part of the process.   a) At the facility, on or about 7/18/2018:  The employers piping and instrument diagrams (P&ID's) did not include basic process industry recognized standard information or nomenclature, including P&ID Ammonia Piping South Train (Sheet 2 of 3) did not include at least the size, capacity, and design pressure of the vaporizer and the vaporizers associated rupture disk did not include information related to its burst pressure.  b) At the facility, on or about 7/18/2018: The employers piping and instrument diagrams (P&ID's) did not include basic process industry recognized standard information or nomenclature, including P&ID Ammonia Piping North Train (Sheet 3 of 3) did not include at least the size, capacity, and design pressure of the vaporizer and the vaporizers associated rupture disk did not include information related to its burst pressure.    Abatement certification must be submitted for this item.
Recent events (3)
  • — J (O) $0
  • — C (O) $0
  • — Z (O) $0

View Chemtrade Solutions LLC's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 343315842.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.