Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: STONE BRIDGE LANDSCAPE & MASONRY LLC

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of STONE BRIDGE LANDSCAPE & MASONRY LLC in 690 MAMARONECK AVE., MAMARONECK, NY 10543 (NAICS 238140). OSHA activity number 343345591.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Stone Bridge Landscape & Masonry LLC — free Get an email when a new federal OSHA severe-injury report for Stone Bridge Landscape & Masonry LLC is published. One employer, no account, unsubscribe in one click.
Site address
690 MAMARONECK AVE.
City
MAMARONECK
State
NY
ZIP
10543
Mailing
15 CHELSEA RD., NEW ROCHELLE, NY 10805
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238140
Employees
8
Ownership type
A

14 citations on file for this inspection.

1926.451 C02 II

Serious Gravity 5 2 instances 4 exposed
Issued
Oct 10, 2018
Penalty
Initial $2,217 · Current $0 Reduced
29 CFR 1926.451(c)(2)(ii): Unstable objects were used to support scaffolds or platform units:    location: IFO building, lobby area  on or about: 7/31/18    a) Mason blocks were used to support the legs of the 1 frame wide by 2 frame high tubular welded frame scaffold. Employees were using the scaffold to access the lobby roof.       location: 1st floor, lobby area  on or about: 7/31/18    b) Mason blocks were used to support the legs of the 2 frame wide by 1 frame high tubular welded frame scaffold. Employees were working from the scaffold while engaged in masonry work.      NOTE: Because abatement of this violation is already documented in the inspection casefile, the employer need not submit certification or documentation of abatement for this violation as normally required by 29 CFR 1903.19.
Recent events (2)
  • — I (S) $0
  • — Z (S) $2217

1926.451 C02

Serious Gravity 5 2 instances 4 exposed
Issued
Oct 10, 2018
Penalty
Initial $2,217 · Current $1,400 Reduced
29 CFR 1926.451(c)(2): Supported scaffold poles, legs, posts, frames, and uprights did not bear on base plates, mud sills or other adequate firm foundation:      location: 1st floor, lobby area  on or about: 7/31/18    a) The legs of the 2 frame wide by 1 frame high tubular welded frame scaffold, used by employees engaged in masonry, did not bear on base plates.      location: IFO building, lobby area  on or about: 7/31/18    b) The legs of the 1 frame wide by 2 frame high tubular welded frame scaffold, used by employees to gain access to the lobby roof, did not bear on base plates.      NOTE: Because abatement of this violation is already documented in the inspection casefile, the employer need not submit certification or documentation of abatement for this violation as normally required by 29 CFR 1903.19.
Recent events (2)
  • — I (S) $1400
  • — Z (S) $2217

1926.451 E04 I

Serious Gravity 5 1 instance 1 exposed
Issued
Oct 10, 2018
Penalty
Initial $2,217 · Current $1,400 Reduced
29 CFR 1926.451(e)(4)(i): A stairrail consisting of a toprail and a midrail was not provided on each side of each scaffold stairway.    location: front of building  on or about: 7/31/18    a) The scaffold stairway, used by an employee to access the scaffold, did not have a toprail or midrail.        NOTE: Because abatement of this violation is already documented in the inspection casefile, the employer need not submit certification or documentation of abatement for this violation as normally required by 29 CFR 1903.19.
Recent events (2)
  • — I (S) $1400
  • — Z (S) $2217

1926.451 E06 VI

Serious Gravity 5 1 instance 3 exposed
Issued
Oct 10, 2018
Penalty
Initial $2,772 · Current $1,800 Reduced
29 CFR 1926.451(e)(6)(vi): Integral prefabricated scaffold access frames did not have a maximum spacing between rungs of 16 3/4 inches (43 cm). Non-uniform rung spacing caused by joining end frames together is exceed 16 3/4 inches (43 cm):    location: IFO building, lobby area  on or about: 7/31/18    a) The 2 section high tubular welded frame scaffold was used to access the lobby roof. The space between rungs was 18 inches and the spacing caused by joining end frames together was 20 inches.      NOTE: Because abatement of this violation is already documented in the inspection casefile, the employer need not submit certification or documentation of abatement for this violation as normally required by 29 CFR 1903.19.
Recent events (2)
  • — I (S) $1800
  • — Z (S) $2772

1926.451 E07

Serious Gravity 5 1 instance 3 exposed
Issued
Oct 10, 2018
Penalty
Initial $0 · Current $0
29 CFR 1926.451(e)(7): Steps and rungs of ladder and stairway type access did not line up vertically with each other between rest platforms:  location: IFO building, lobby area on or about: 7/31/18  a) The 2 section high tubular welded frame scaffold was used to access the lobby roof. The rungs of the 1st frame did not match up to the rungs of the 2nd frame.    NOTE: Because abatement of this violation is already documented in the inspection casefile, the employer need not submit certification or documentation of abatement for this violation as normally required by 29 CFR 1903.19.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1926.451 E08

Serious Gravity 5 1 instance 3 exposed
Issued
Oct 10, 2018
Penalty
Initial $2,772 · Current $1,800 Reduced
29 CFR 1926.451(e)(8): Direct access to or from another surface was used when the scaffold was more than 14 inches (36 cm) horizontally and/or 24 inches (61 cm) vertically from the other surface:    location: IFO building, lobby area  on or about: 7/31/18    a) The 11 feet high tubular welded frame scaffold was used to access the 14 feet lobby roof. The top of the scaffold was 3 feet below the roof.      NOTE: Because abatement of this violation is already documented in the inspection casefile, the employer need not submit certification or documentation of abatement for this violation as normally required by 29 CFR 1903.19.
Recent events (2)
  • — I (S) $1800
  • — Z (S) $2772

1926.451 F03

Serious Gravity 5 1 instance 9 exposed
Issued
Oct 10, 2018
Abate by
Oct 18, 2018
Penalty
Initial $2,772 · Current $1,800 Reduced
29 CFR 1926.451(f)(3): Scaffolds and scaffold components were not inspected for visible defects by a competent person before each work shift, and after any occurrence which could affect a scaffold's structural integrity:      location: throughout site  on or about: 7/31/18    a) Employees were engaged in masonry work were walking on/working from tubular welded frame scaffolds without having them inspected by a competent person.       NOTE: The employer is required to submit abatement certification for this item in accordance with 29 CFR 1903.19.
Recent events (2)
  • — I (S) $1800
  • — Z (S) $2772

1926.451 G01 V

Serious Gravity 5 1 instance 3 exposed
Issued
Oct 10, 2018
Penalty
Initial $2,772 · Current $1,800 Reduced
29 CFR 1926.451(g)(1)(v): Each employee on a walkway located within a scaffold was not protected by a guardrail system (with a minimum 200 pound toprail capacity) installed within 9.5 inches (24.1 cm) of and along at least one side of the walkway:    location: IFO building, lobby area  on or about: 7/31/18    a) The 11 feet high tubular welded frame scaffold, used by employees to gain access to the lobby roof, did not have guardrails.     NOTE: Because abatement of this violation is already documented in the inspection casefile, the employer need not submit certification or documentation of abatement for this violation as normally required by 29 CFR 1903.19.
Recent events (2)
  • — I (S) $1800
  • — Z (S) $2772

1926.454 A

Serious Gravity 10 9 instances 9 exposed
Issued
Oct 10, 2018
Abate by
Nov 13, 2018
Penalty
Initial $3,880 · Current $2,500 Reduced
29 CFR 1926.454(a): The employer did not have each employee who performed work while on a scaffold trained by a person qualified in the subject matter to recognize the hazards associated with the type of scaffold being used and to understand the procedures to control or minimize those hazards.    On or about 7/31/18  Location: entire site    a) Employees, working from tubular welded frame scaffolds, were not provide with scaffold safety training.        Note: In addition to abatement certification, the employer is required to provide abatement documentation for this item in accordance with 29 CFR 1903.19
Recent events (2)
  • — I (S) $2500
  • — Z (S) $3880

1926.503 A01

Serious Gravity 10 4 instances 4 exposed
Issued
Oct 10, 2018
Abate by
Nov 13, 2018
Penalty
Initial $0 · Current $0
29 CFR 1926.503(a)(1): The employer did not provide a training program for each employee potentially exposed to fall hazards to enable each employee to recognize the hazards of falling and the procedures to be followed in order to minimize these hazards:   location: entire site on or about: 7/31/18  a) Employees, engaged in masonry work, were not provided with adequate fall protection safety training. The employees were exposed to a fall of 14 feet.     Note: In addition to abatement certification, the employer is required to provide abatement documentation for this item in accordance with 29 CFR 1903.19
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1926.501 B01

Serious Gravity 10 1 instance 4 exposed
Issued
Oct 10, 2018
Penalty
Initial $3,880 · Current $2,500 Reduced
29 CFR 1926.501(b)(1): "Unprotected sides and edges." Each employee on a walking/working surface (horizontal and vertical surface) with an unprotected side or edge which is 6 feet (1.8 m) or more above a lower level was not protected from falling by the use of guardrail systems, safety net systems, or personal fall arrest systems:    location: lobby roof  on or about: 7/31/18    a) Employees were engaged in masonry work on the lobby roof. The employees were not protected from falling and were exposed to a fall of 14'.       NOTE: Because abatement of this violation is already documented in the inspection casefile, the employer need not submit certification or documentation of abatement for this violation as normally required by 29 CFR 1903.19.
Recent events (2)
  • — I (S) $2500
  • — Z (S) $3880

1926.602 C01 VII

Serious Gravity 10 1 instance 4 exposed
Issued
Oct 10, 2018
Penalty
Initial $3,880 · Current $2,500 Reduced
29 CFR 1926.602(c)(1)(vii): Unauthorized personnel shall not be permitted to ride on powered industrial trucks. A safe place to ride shall be provided where riding of trucks is authorized:    location: front of building  on or about: 7/31/18    a) Employees were riding on a pallet placed on the forks of the JCB 510-56 rough terrain forklift. The employees were exposed to a fall of up to 14 feet.       NOTE: Because abatement of this violation is already documented in the inspection casefile, the employer need not submit certification or documentation of abatement for this violation as normally required by 29 CFR 1903.19.
Recent events (2)
  • — I (S) $2500
  • — Z (S) $3880

1926.602 D

Other-than-serious 2 instances 2 exposed
Issued
Oct 10, 2018
Penalty
Initial $2,772 · Current $0 Reduced
29 CFR 1926.602(d): The employer did not train and evaluate each operator as required by paragraph 29 CFR 1910.178(l): Note: The requirements applicable to construction work under paragraph (d) of this section are identical to those set forth at paragraph (l) of 29 CFR 1910.178:    location: entire site  on or about: 7/31/18    a) Employees were riding on a pallet placed on the forks of the JCB 510-56 rough terrain forklift. The employees that were operating the forklift were not provided with forklift training.       NOTE: Because abatement of this violation is already documented in the inspection casefile, the employer need not submit certification or documentation of abatement for this violation as normally required by 29 CFR 1903.19.
Recent events (2)
  • — I (O) $0
  • — Z (S) $2772

1926.1052 C01 II

Deleted Serious Gravity 5 1 instance 9 exposed
Issued
Oct 10, 2018
Penalty
Initial $2,217 · Current $0 Reduced
29 CFR 1926.1052(c)(1)(ii): Stairways having four or more risers or rising more than 30 inches (76 cm), whichever is less, were not equipped with a stairrail system along each unprotected side or edge:  Location: between 1st floor and retail level  On or about: 7/31/18  a) Employees used the stairs for access between the first floor and retail level. The stairs did not have a stair rail system along the open sides.    NOTE: Because abatement of this violation is already documented in the inspection casefile, the employer need not submit certification or documentation of abatement for this violation as normally required by 29 CFR 1903.19.
Recent events (2)
  • — I (S) $0
  • — Z (S) $2217

View Stone Bridge Landscape & Masonry LLC's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 343345591.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.