On , OSHA opened a complaint health inspection of EMPACT CONSTRUCTION SERVICES, INC. in 1124 W. WILSON AVE., CHICAGO, IL 60640 (NAICS 236118). OSHA activity number 343747374.
OSHA opens inspections for many reasons: routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- EMPACT CONSTRUCTION SERVICES, INC.
- Site address
- 1124 W. WILSON AVE.
- City
- CHICAGO
- State
- IL
- ZIP
- 60640
- Mailing
- 1135 W. CHICAGO AVE. 1E, CHICAGO, IL 60642
What kind of inspection was it?
- Inspection type
- Complaint (B)
- Scope
- Partial (B)
- Discipline
- Health
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 236118
- Employees
- 9
- Ownership type
- A
Citations
6 citations on file for this inspection.
1926.1101 D05
- Issued
- Apr 25, 2019
- Abate by
- May 29, 2019
- Penalty
- Initial $3,789 · Current $1,700 Reduced
9020
General-duty citation text
29 CFR 1926.1101(d)(5): As supervisor of the entire project, the general contractor did not ascertain whether the asbestos contractor was in compliance with the asbestos standard, and did not require such contractor to come into compliance with this standard: a) The employer, acting as a General Contractor, requested, directed and approved of sub-contractor employee(s) to conduct interior demolition. While demolishing wall structures, subcontractor employee(s) damaged pipe(s) covered with ACM/PACM thermal system insulation. The General Contractor did not require the sub-contractors performing demolition work to come into compliance with 1926.1101 asbestos standard. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
- · I (S) $1700
- · Z (S) $3789
1926.1101 G09
- Issued
- Apr 25, 2019
- Abate by
- May 29, 2019
- Penalty
- Initial $3,789 · Current $1,700 Reduced
9020
General-duty citation text
29 CFR 1926.1101(g)(9): Class III asbestos work was not conducted using engineering and work practice controls which minimized the exposure to employees performing the asbestos work and to bystander employees: a) On or about January 29, 2019, the employer did not ensure that their employees, conducting demolition activities, did not damage pipe thermal system insulation (TSI) containing 50% asbestos. Employee(s) performed work likely to disturb ACM/PACM pipe TSI and did not use one or more of the following engineering and work practice controls: wet methods; local exhaust ventilation; impermeable drop-cloths; mini-enclosures; or glove bag systems, thereby exposing their employees to the hazards associated with asbestos. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
- · I (S) $1700
- · Z (S) $3789
1926.1101 H01
- Issued
- Apr 25, 2019
- Abate by
- May 29, 2019
- Penalty
- Initial $3,789 · Current $1,700 Reduced
9020
General-duty citation text
29 CFR 1926.1101(h)(1): For employees who use respirators required by 29 CFR 1926.1101, the employer did not provide each employee an appropriate respirator that complied with the requirements of this paragraph. Respirators must be used during activities listed in sections (i) through (viii) of this paragraph. a) On or about January 29, 2019, the employer did not ensure that their employees, while conducting demolition activities which damaged Presumed Asbestos Containing Material (PACM) in the Thermal System Insulation (TSI), used respiratory protection, thereby exposing them to the hazards associated with asbestos. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
- · I (S) $1700
- · Z (S) $3789
1910.134 C01
- Issued
- Apr 25, 2019
- Abate by
- May 29, 2019
- Penalty
- Initial $0 · Current $0
9020
General-duty citation text
29 CFR 1910.134(c)(1): A written respiratory protection program that included the provisions in 29 CFR 1910.134(c)(1)(i) - (ix) with worksite specific procedures was not established and implemented for required respirator use: a) On or about January 29, 2019, the employer did not establish and implement a written respiratory protection program for required respirator use. Employees were exposed to asbestos while conducting demolition activities which damaged Presumed Asbestos Containing Material (PACM) in the Thermal System Insulation (TSI), used respiratory protection, thereby exposing them to the hazards associated with asbestos. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
- · I (S) $0
- · Z (S) $0
1926.1101 K09 I
- Issued
- Apr 25, 2019
- Abate by
- May 29, 2019
- Penalty
- Initial $3,789 · Current $1,700 Reduced
9020
General-duty citation text
29 CFR 1926.1101(k)(9)(i): The employer did not institute, at no cost to employees, a training program for each employee who was likely to be exposed in excess of the permissible exposure limit (PEL) and for each employee who performed Class I through IV asbestos operations: a) On or about January 29, 2019, the employer did not institute a training program for employees conducting demolition activities likely to disturb ACM/PACM (Class III work) and cleaning up the resulting dust, waste and debris (Class IV work). During their work, employees damaged pipe thermal system insulation (TSI) containing 50% asbestos, were to the hazards associated with asbestos. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
- · I (S) $1700
- · Z (S) $3789
1926.1101 O01
- Issued
- Apr 25, 2019
- Abate by
- May 29, 2019
- Penalty
- Initial $3,789 · Current $1,700 Reduced
9020
General-duty citation text
29 CFR 1926.1101(o)(1): The employer did not designate a competent person on construction worksites, having the qualifications and authorities for ensuring worker safety and health required by 29 CFR 1926.1101(C), General Safety and Health Provisions for Construction 29 CFR 1926.20 through 29 CFR 1926.32: a) On or about January 29, 2019, the employer did not designate a competent person at 1124 W. Wilson Ave, Chicago, IL 60640. Employees were exposed to asbestos while conducting demolition activities which damaged Presumed Asbestos Containing Material (PACM) in the Thermal System Insulation (TSI). In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
- · I (S) $1700
- · Z (S) $3789
More inspections at Empact Construction Services, INC.
View Empact Construction Services, INC.'s full OSHA safety record →
More inspections in this industry (NAICS 236118)
More inspections in IL
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 343747374.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.