OSHA Inspection: FAST CONSTRUCTION & RESTORATION

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of FAST CONSTRUCTION & RESTORATION in 1414 83RD STREET, BROOKLYN, NY 11228 (NAICS 238170). OSHA activity number 344110366.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Fast Construction & Restoration — free Get an email when a new federal OSHA severe-injury report for Fast Construction & Restoration is published. One employer, no account, unsubscribe in one click.
Site address
1414 83RD STREET
City
BROOKLYN
State
NY
ZIP
11228
Mailing
2107 76TH STREET APT 1F, BROOKLYN, NY 11214
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238170
Employees
3
Ownership type
A

4 citations on file for this inspection.

1926.451 B01

Serious Gravity 10 1 instance 2 exposed
Issued
Sep 25, 2019
Penalty
Initial $3,978 · Current $2,500 Reduced
29 CFR 1926.451(b)(1): Platform(s) on all working levels of scaffolds, were not fully planked or decked between the front uprights and guardrail supports such that the space between adjacent units, and the space between the platform and the uprights.      Location:   a) Supported scaffold on the northeast exterior side of the jobsite:      On or about 06/24/2019, employees were installing bricks and pointing on the fourth tier platform of a four-tier-high supported scaffold, and the working level was planked by 3 planks.
Recent events (2)
  • — I (S) $2500
  • — Z (S) $3978

1926.451 G01 VII

Serious Gravity 10 1 instance 2 exposed
Issued
Sep 25, 2019
Penalty
Initial $3,978 · Current $2,500 Reduced
29 CFR 1926.451(g)(1)(vii): Each employee on a scaffold, not otherwise specified in paragraphs (g)(1)(i) through (g)(1)(vi) of this section, more than 10 feet (3.1 m) above lower level was not protected from falls by the use of personal fall arrest systems or guardrail systems meeting the requirements of paragraph (g)(4) of this section.      Location:  a) Supported scaffold on the northeast exterior side of the jobsite:      On or about 06/24/2019, employees were installing bricks and pointing on the fourth tier platform of a four-tier-high supported scaffold, and were not protected from falling approximately 24 feet to a lower level.
Recent events (2)
  • — I (S) $2500
  • — Z (S) $3978

1926.451 C03

Serious Gravity 5 1 instance 2 exposed
Issued
Sep 25, 2019
Penalty
Initial $2,842 · Current $1,500 Reduced
29 CFR 1926.451(c)(3): Supported scaffold poles, legs, post, frames, and/or uprights were not plumb and braced to prevent swaying and displacement      Location:  a) Supported scaffold on the northeast exterior side of the jobsite:      On or about 06/24/2019, employees were installing bricks and pointing on the fourth tier platform of a four-tier-high supported scaffold. The supported scaffold poles, legs, post, frames, and/or uprights were not braced to prevent swaying and displacement.
Recent events (2)
  • — I (S) $1500
  • — Z (S) $2842

1926.451 E01

Serious Gravity 5 1 instance 2 exposed
Issued
Sep 25, 2019
Penalty
Initial $2,842 · Current $0 Reduced
29 CFR 1926.451(e)(1): When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, structure, personnel hoist, or similar surface was not used.  Scaffold frames and cross bracing were used as a means of access.      Location:   a) Supported scaffold on the northeast exterior side of the jobsite:      On or about 06/24/2019, employees climbed the scaffold frames and cross bracing as a mean of access from the fourth tier platform of a four-tier-high supported scaffold to the ground level.
Recent events (2)
  • — I (S) $0
  • — Z (S) $2842

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 344110366.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.