Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: CMC ROOFING, LLC

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of CMC ROOFING, LLC in 830 SIR THOMAS COURT, HARRISBURG, PA 17108 (NAICS 238160). OSHA activity number 344362637.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch CMC Roofing, LLC — free Get an email when a new federal OSHA severe-injury report for CMC Roofing, LLC is published. One employer, no account, unsubscribe in one click.
Establishment
CMC ROOFING, LLC
Site address
830 SIR THOMAS COURT
City
HARRISBURG
State
PA
ZIP
17108
Mailing
721 GINGRICH LANE, DAUPHIN, PA 17018
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238160
Employees
4
Ownership type
A

4 citations on file for this inspection.

1903.19 C01

Other-than-serious 3 instances 4 exposed
Issued
Dec 19, 2019
Abate by
Jan 23, 2020
Penalty
Initial $319 · Current $319
29 CFR 1903.19(c)(1): The employer did not certify to OSHA, within 10 calendar days after the abatement date, that the cited violation had been abated:  a) Location - Facility  On or about December 12, 2019, the employer did not certify that the violations had been corrected.
Recent events (1)
  • — Z (O) $319

1926.102 A01

Serious Gravity 5 1 instance 1 exposed
Issued
Oct 28, 2019
Abate by
Nov 22, 2019
Penalty
Initial $2,842 · Current $2,131 Reduced
29 CFR 1926.102(a)(1): Employees were not provided with eye and face protection equipment when machines or operations present potential eye or face injury from physical, chemical, or radiation agents:    a) Roof - On or about October 8, 2019, an employee was observed operating a pneumatic nail gun to secure shingles to the roof of a building and was not provided eye protection, exposed to ricochet nails and flying debris.    Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (S) $2131
  • — Z (S) $2842

1926.501 B11

Serious Gravity 5 1 instance 3 exposed
Issued
Oct 28, 2019
Abate by
Nov 22, 2019
Penalty
Initial $2,842 · Current $2,131 Reduced
29 CFR 1926.501(b)(11): Each employee on a steep roof with unprotected sides and edges 6 feet (1.8 m) or more above lower levels was not protected from falling by guardrail systems with toeboards, safety net systems or personal fall arrest systems:    a) Roof - On or about October 8, 2019, and times prior thereto, employees removing and installing roofing materials were permitted to work at elevated heights on a 6:12 sloped roof, as far as approximately 8 feet above ground level, and were not protected from falling.    Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (S) $2131
  • — Z (S) $2842

1926.503 A01

Serious Gravity 5 1 instance 3 exposed
Issued
Oct 28, 2019
Abate by
Dec 2, 2019
Penalty
Initial $0 · Current $0
29 CFR 1926.503(a)(1): A training program was not provided to each employee who might be exposed to fall hazards, to enable that employee to recognize the hazards of falling, and be trained in the procedures to be followed to minimize these hazards:  a) Roof - On or about October 8, 2019, and times prior thereto, employees were not trained in appropriate fall protection methods to avoid hazards associated with elevated work areas.  Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 344362637.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.