OSHA Inspection: COLLINS PINE COMPANY, KANE HARDWOOD DIVISION

Referral inspection · Safety discipline

On , OSHA opened a referral safety inspection of COLLINS PINE COMPANY, KANE HARDWOOD DIVISION in 95 HARDWOOD DRIVE, KANE, PA 16735 (NAICS 321113). OSHA activity number 345020622.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Collins Pine Company, Kane Hardwood Division — free Get an email when a new federal OSHA severe-injury report for Collins Pine Company, Kane Hardwood Division is published. One employer, no account, unsubscribe in one click.
Site address
95 HARDWOOD DRIVE
City
KANE
State
PA
ZIP
16735
Mailing
95 HARDWOOD DRIVE, KANE, PA 16735
Inspection type
Referral (C)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
321113
Employees
92
Ownership type
A

4 citations on file for this inspection.

1910.147 D

Serious Gravity 10 1 instance 3 exposed
Issued
Jan 28, 2021
Abate by
Feb 24, 2021
Penalty
Initial $13,653 · Current $9,600 Reduced
29 CFR  1910.147(d): The established procedure for the application of energy control (the lockout or tagout procedures) did not cover the actions listed in and was not done in sequence as required by 29 CFR 1910.147(d)(1)-(6):  a.)  Collins Pine Company, Kane Hardwood Division; conveyor to stacker; sorter area -  On or about 11/12/20, at times prior thereto, the conveyor was not locked out prior to employees being near the conveyors, unguarded chains and sprockets when performing servicing and maintenance.  The area was being entered for employees to perform work including, but not limited to,  moving lumber from chain 1 to chain 2 of the conveyor.  ABATEMENT CERTIFICATION AND DOCUMENTATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation.  This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement. IN ADDITION, abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic, or video evidence or abatement or other written records.
Recent events (2)
  • — I (S) $9600
  • — Z (S) $13653

1910.265 C18 I

Serious Gravity 10 1 instance 5 exposed
Issued
Jan 28, 2021
Abate by
Feb 24, 2021
Penalty
Initial $0 · Current $0
29 CFR  1910.265(c)(18)(i): Construction, operation, and maintenance of conveyors were not in accordance with American National Standard B20:   a.)  Collin Company, Kane Hardwood Division; sorter area -- Chain/Sprocket Associated with the Conveyor - - On or about 11/5/20, and at times prior thereto, chains and sprockets were not  guarded to prevent employees from getting caught in them.  An accident occurred in which an employee's foot was pulled into the sprocket area causing the employee to sustain a 2 toe amputation. One or more methods of effective machine guarding were not provided to protect  employees in the conveyor area from hazards such as those created by  ingoing nip points and  rotating parts from chains and sprockets. In addition, the perimeter guarding was not so designed and constructed as to prevent the employees from being in the areas by the chain/sprocket in that employees could by-pass the perimeter guarding by utilizing two different stairways.  ABATEMENT CERTIFICATION AND DOCUMENTATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation.  This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement. IN ADDITION, abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic, or video evidence or abatement or other written records.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.219 C02 I

Serious Gravity 5 1 instance 5 exposed
Issued
Jan 28, 2021
Abate by
Feb 24, 2021
Penalty
Initial $0 · Current $0
29 CFR  1910.219(c)(2)(i):All exposed part(s) of horizontal shafting seven (7) feet or less from floor or working platform were not protected by stationary casing(s) enclosing shafting completely or by trough(s) enclosing sides and top or sides and bottom of shafting:  a.)  Collin Company, Kane Hardwood Division; sorter area - On or about 11/12/20, and at times prior thereto, two(2) shafts were unguarded.  The shafts ran from the motors to the chain and sprockets on the line and were at ground level.  In addition, the perimeter guarding was not so designed and constructed as to prevent the employees from being in the areas by the power transmission apparatus in that employees could by-pass the perimeter guarding by utilizing two different stairways.  ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below).  This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.219 F03

Serious Gravity 5 1 instance 5 exposed
Issued
Jan 28, 2021
Abate by
Feb 24, 2021
Penalty
Initial $0 · Current $0
29 CFR  1910.219(f)(3): Sprocket wheels and chains which were seven (7) feet or less above floors or platforms were not enclosed:   a.)  Collin Company, Kane Hardwood Division; sorter area -- Chain/Sprocket Assembly by Motor - - On or about 11/5/20, and at times prior thereto, chains and sprockets were not  guarded to prevent employees from getting caught in them.  The chain/sprocket assembly were located at ground level.  In addition, the perimeter guarding was not so designed and constructed as to prevent the employees from being in the areas by the power transmission apparatus in that employees could by-pass the perimeter guarding by utilizing two different stairways.   ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below).  This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

View Collins Pine Company, Kane Hardwood Division's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 345020622.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.